Where should the drawing boundaries fall? · Essai 01

Where should the drawings meet?

A railway is imagined on the wet climb near Skiddaw House towards Great Calva. Eighteen drawing tiles cover six lengths and three stages. Three packages each take six tiles.

At the join, one drawing’s topsoil transfer must be another’s receipt; a handed-over level and tangent must match the next drawing’s assumption. Where would you divide the responsibility?

Schematic imagined railway climbing across wet ground near Skiddaw House towards Great Calva; not a mapped alignment.
Imagined works. Dimensions and probabilities are illustrative.

Same drawings. Different joins.

Time ↓Chainage 0 → 600 m
1 Strip2 Form3 Reinstate
ABC6 tiles each
1.0125expected unresolved mismatches

Wet-ground assumptions · chainage bands. Changing the boundaries changes review responsibility, not the ground.

This is an expected count, not a failure probability. What is being counted?

Loading the checked allocation model…

Move the boundary, keep the work

Can you improve the wet-ground chainage plan by exchanging just two drawings? Choose a first tile. A tick marks each partner that keeps all three packages connected. Choose a ticked tile to apply the exchange, or another package’s unticked tile to preview a disconnected map.

Time ↓Chainage 0 → 600 m
1 Strip2 Form3 Reinstate
0–100100–200200–300300–400400–500500–600
ABCBlack edge = package boundary

Choose the first tile, then a tile in another package.

Eligible · three connected packages of six drawings.

Your allocation

1.0125expected unresolved discrepancies

Within-package review baseline
—
Added exposure at package joins
—
Interfaces crossing packages
6 of 27
Best eligible expected count
0.8775

All 132 eligible allocations are compared for the selected assumptions. No claim about unmodelled drawings or field frequencies.

What can one exchange do? Reveal a route to the bent allocation

Of 108 pairs drawn from different packages in the straight plan, just 12 exchanges keep all three packages connected. Every one raises the wet-ground count. The smallest increase is 1C ↔ 2B, from 1.0125 to 1.0235.

Four eligible exchanges reach the optimum. Follow the drawing labels in order and watch the count rise twice along the way.

  1. 1E ↔ 3D · 1.0405
  2. 1B ↔ 3C · 0.9855
  3. 1A ↔ 2C · 0.9970
  4. 1F ↔ 2D · 0.8775

The route uses wet-ground assumptions and counts quantity, level and gradient together. Each step appears in the grid and the page address.

Open a particular join

Each join compares two versions of the same transfer or handover surface. Different tiles need not contain equal volumes.

This is an exploration, not a saved project record. Eligible allocations and assumptions are kept in this page’s address for sharing, refresh and Back. An unfinished tile selection or disconnected preview lasts only on this screen. No drawings, quantities or source records are changed. Reset returns to the opening example.

Compare the same thing on both sides

A neighbouring tile may need more topsoil because its area is larger. That is not a mismatch. A mismatch occurs when the sender writes “50 m³ to the next tile” and the receiver’s description of that same transfer says 70 m³. Match the material, units, direction, datum, location, stage and drawing revision before comparing the numbers.

Two records of one material transfer differ by twenty cubic metresSending drawing50 m³Receiving drawing70 m³One transfer · a 20 m³ disagreement
The discrepancy concerns an identified transfer, not equality of the totals in two different ground areas.

Time boundaries need the same care. Compare the surface that one stage hands over with the surface the next stage assumes it receives. Do not compare an unfinished excavation directly with the intended finished railway and call the intended difference an error.

The trial’s fixed topsoil ledger strips and places 1,500 m³. Each tile balances incoming material, outgoing material, source and use. Reallocating drawings leaves that ledger unchanged. Peat excavation, bulking, losses and settlement would need additional explicit material and ground models.

The best join need not be a straight line

Chainage bands keep a length of railway together through time. Stage bands keep one operation together along the hillside. Both are easy to name. Neither automatically keeps the joins most exposed to unresolved discrepancies within a single review.

Chainage bands give 1.0125 expected unresolved mismatches. A bent allocation gives 0.8775 under wet-ground assumptions.
The bent allocation keeps all stripping in A, then divides formation and reinstatement into two three-cell lengths.

For wet-ground assumptions, all three packages still contain six drawings. The bent allocation has eight cross-package interfaces, compared with six for chainage bands. It wins by keeping joins with larger assumed increases in unresolved-discrepancy probability inside packages.

Where the 0.1350 reduction comes from under wet-ground assumptions
DiscrepancyChainageBentReduction
Quantity0.33350.33300.0005
Level0.36000.29700.0630
Gradient0.31900.24750.0715
All three1.01250.87750.1350

Level and gradient account for 0.1345 of the 0.1350 gain. Follow one join, 2B / 2C. The two drawings disagree by 25 m³ of material, 12 mm of level and 0.04‰ of gradient in either allocation. In the chainage plan, two teams review the join and the assumed chance of the level discrepancy surviving is 6.64%. In the bent plan, one team owns both drawings and the assumption is 0.94%.

Under the reference assumptions, straight chainage bands are best. Under a joint-review arrangement at the bog, they are best again. This is a decision conditional on how interfaces are checked, not an intrinsic ranking of three pictures.

Balanced tile counts stand in for equal workload. Real drawing effort, package mobilisation, discontinuous access and team expertise could change the eligible allocations or their costs. The trial requires connection in the time–chainage grid; it does not assert that every such package would be convenient on site.

A likelihood needs an event

The named event is a discrepancy in a particular quantity, level or gradient remaining unresolved at the handover checkpoint. The toy model supplies a marginal probability for each event, with one assumption for a shared package and another when responsibility crosses packages.

Expected unresolved events
= within-package baseline + extra exposure at crossed joins

Expectations add even when events are correlated. We therefore do not need to assume independent errors. But the sum is not the probability of at least one error. A value above one is perfectly possible: several discrepancies can survive in the same outcome.

A single join can have three unresolved discrepancies. If a manager wants to count handovers that must be reopened, each affected join counts just once. The answer then depends on how often the three discrepancies happen together.

Can counting affected joins change which plan wins?

Yes. Keep every wet-ground probability. At the eight joins crossed only by the bent plan, suppose the three discrepancies happen on separate occasions. The chance that the join is affected is then the sum of the three probabilities. At each other join, suppose a rarer discrepancy happens only when every more frequent one does. There the chance is the largest of the three probabilities.

Apply that rule to the same locations in both plans. Summing the 27 chances gives 0.5430 expected affected joins for chainage and 0.7350 for the bent plan. This possible pattern favours chainage. The measured frequency of co-occurrence would matter to a team choosing by this criterion.

The physical diagnostic gaps and the probability inputs are separate. A large difference in provisional levels does not, by itself, establish a probability that review will miss it. Here every probability is illustrative. To use this on a project, estimate and challenge the review assumptions against that project’s actual records.

A joint review changes the process; moving a coloured border only changes who owns the comparison. Neither act certifies that the physical mismatch has been resolved.

A balanced total can conceal a broken join

Imagine two drafts agree on a 50 m³ transfer and a level of 120.000 m in a shared project datum. At their common boundary, one assumes an uphill tangent of 25‰ and the other 35‰. The material ledger balances; the height matches; the tangent does not.

Two drawings agree on level at a boundary but disagree on its common-direction tangent25‰35‰Same level: 120.000 mOne stipulated tangent · two incompatible assumptions
Exaggerated drawing. A legitimate vertical curve can change grade; the mismatch here is two different claims about the same required tangent.

A sheaf gives an exact language for this: local descriptions must agree under the relevant comparison maps. A global section is a choice that fits at every join. It does not mean that a matching average guarantees a buildable whole.

Take three bits, x, y and z. Two drawings require x=y and y=z. The third requires z≠x. At either equal pair, give 00 and 11 equal weight. At the unequal pair, give 01 and 10 equal weight. Look at any one bit on either drawing and it is 50/50. Look at the pair requirements together and the contradiction is immediate because the two equalities force z=x.

Keeping only the single-bit distributions loses the relationship that exposes the contradiction. The parity equations themselves preserve it. Here sheaves tell us what agreement would require. The allocation program answers a different question about who reviews the drawings.

Keep more than one computational geography

Mazor and Pass use several decompositions of a dependency problem. Different parts of an algebraic calculation can be handled with the coordinate that exposes few crossing dependencies, then reconstructed without counting overlaps twice. Their geographic information retrieval construction chooses logical addresses and a shared hint. These are computational addresses, not fixed locations on a hillside. ECCC TR26-347, §§2–5.

We borrow a question: which dependencies become awkward under each division? The trial answers it by exact enumeration of a small weighted graph partition problem. It does not implement the paper’s counting algorithm, inherit its complexity guarantee, or treat its bookkeeping variables as cohomology classes.

Physical geographyChainage, ground, material movement
Computational geographyDrawings, packages, comparisons

The physical problem stays fixed while its responsibility map changes. A family of useful decompositions can guide calculation and expose alternatives; eventually the drawing office must still choose an accountable allocation.

A shared summary can sometimes answer a narrow remote question. If a trusted ledger says three stores total 180 m³ and nearby records give 50 and 80, the third is 50. That deduction requires all three records to describe the same conserved stock and version. The total alone says nothing about a gradient. In general, recovery works only when every underlying state compatible with the observed records gives the same requested answer. That is the precise bridge to coded sampling and sheaf ambiguity.

When physical readers have no useful local information and each needs a different independent bit, a common hint must contain enough information to distinguish all those bits. Relabelling their addresses cannot evade that bound. This is why the present essai concentrates on the allocation comparison rather than claiming that GIR accelerates ordinary GIS operations.

Every eligible allocation, checked exactly

The model has 18 tiles, 27 shared edges and three interchangeable packages of six tiles. There are 2,858,856 balanced partitions after ignoring package names. Requiring every package to be connected leaves 132. The checker evaluates integer probability units, so rounding cannot change the optimum. The three all-event optima below are unique up to package names.

Expected number of unresolved discrepancies under illustrative assumptions
AllocationReferenceWet groundJoint review
Chainage bands0.51591.01250.3602
Stage bands0.76290.94150.6187
Best eligible allocation0.51590.87750.3602

Wet-ground chainage bands give 1.0125; the best eligible allocation gives 0.8775, a reduction of 0.1350 expected events (13⅓%). These are outcomes of assumed probabilities, not measured project savings. Joint review is a different assumed process with an unpriced resource cost; its lower count does not prove it is the cheapest option.

What if only quantity matters? Two maps tie at 0.2915 under wet-ground assumptions. The map that keeps reinstatement together gives 0.8995 across all three types. The map that splits reinstatement between two packages gives 0.9235. A team using level and gradient to break the tie would choose the first.

How strong must the wet-ground penalty be to move the boundary?

Start from the reference assumptions. Increase only the assumed extra chance of a discrepancy surviving review when a wet join crosses packages. At 0% the reference crossing penalties apply. At 100% they reach the published wet-ground penalties. At 200% the increase has doubled. Compare the same 132 eligible allocations throughout.

Chainage bands AABBCC AABBCC AABBCC Up to 35.6%
Bent allocation AAAAAA BBBCCC BBBCCC 35.6% to 144.2%
Formation to 2E AAAAAA BBBBBC BCCCCC 144.2% to 200%
Winning maps as the extra crossing penalty increases. Stages run down and chainage runs across. Adjacent maps tie at precisely 149/419 and 313/217 of the stipulated increase. Percentages are rounded.
Difference in expected discrepancies relative to straight chainageAt 0%, the bent and formation-to-2E maps have 0.0745 and 0.2310 more discrepancies than straight chainage. At 100% they have 0.1350 and 0.0870 fewer. At 200% they have 0.3445 and 0.4050 fewer. The lower line wins. Expected discrepancies above (+) or below (−) chainage +0.20−0.2−0.4 0%100%200% Chainage Bent Formation to 2E
Read the lowest line. At 100%, the bent map saves 0.1350 expected discrepancies against chainage. Comparing differences cancels the shared within-package baseline, which this test holds at its reference value.
Inspect all 27 interfaces and their probability inputs

Percentages are marginal probabilities of each named event remaining unresolved. “Same” means one package owns both drawings; “cross” means different packages. Figures are illustrative assumptions.

The table uses the wet-ground assumptions from the current score.

JoinQuantity same/crossLevel same/crossGradient same/cross
1A / 1B0.26% / 1.06%0.13% / 0.53%0.10% / 0.30%
1B / 1C0.90% / 6.30%0.34% / 2.44%0.15% / 0.90%
1C / 1D0.69% / 4.89%0.42% / 2.97%0.15% / 1.05%
1D / 1E0.49% / 3.49%0.31% / 2.26%0.24% / 1.74%
1E / 1F0.20% / 0.80%0.11% / 0.46%0.28% / 1.13%
2A / 2B0.20% / 0.80%0.30% / 1.20%0.20% / 0.80%
2B / 2C0.79% / 5.59%0.94% / 6.64%0.45% / 3.15%
2C / 2D0.60% / 4.20%1.05% / 7.35%0.60% / 4.20%
2D / 2E0.64% / 4.54%0.69% / 4.89%0.90% / 6.30%
2E / 2F0.26% / 1.06%0.30% / 1.20%0.73% / 2.93%
3A / 3B0.10% / 0.40%0.36% / 1.46%0.30% / 1.20%
3B / 3C0.19% / 1.39%0.64% / 4.54%0.49% / 3.49%
3C / 3D0.16% / 1.21%0.75% / 5.25%0.69% / 4.89%
3D / 3E0.24% / 1.74%0.84% / 5.94%0.99% / 6.99%
3E / 3F0.23% / 0.93%0.66% / 2.66%0.86% / 3.46%
1A / 2A0.36% / 1.46%0.20% / 0.80%0.13% / 0.53%
1B / 2B0.50% / 2.00%0.26% / 1.06%0.13% / 0.53%
1C / 2C1.50% / 6.00%0.49% / 1.99%0.30% / 1.20%
1D / 2D1.80% / 7.20%0.54% / 2.19%0.30% / 1.20%
1E / 2E0.53% / 2.13%0.23% / 0.93%0.26% / 1.06%
1F / 2F0.33% / 1.33%0.20% / 0.80%0.33% / 1.33%
2A / 3A0.16% / 0.66%0.40% / 1.60%0.33% / 1.33%
2B / 3B0.23% / 0.93%0.43% / 1.73%0.40% / 1.60%
2C / 3C0.79% / 3.19%0.75% / 3.00%0.69% / 2.79%
2D / 3D0.90% / 3.60%0.75% / 3.00%0.75% / 3.00%
2E / 3E0.30% / 1.20%0.46% / 1.86%0.80% / 3.20%
2F / 3F0.20% / 0.80%0.50% / 2.00%1.00% / 4.00%
Check the conserved topsoil ledger

1,500 m³ stripped + 0 imported = 1,500 m³ placed + 0 exported + 0 final stock. For every tile, source + incoming − outgoing − use = 0. This is the fixed nominal transfer plan; provisional differences between drawings remain a separate register.

TileSourceInOutUseBalance m³
1A180018000
1B240024000
1C300030000
1D360036000
1E240024000
1F180018000
2A018018000
2B024024000
2C030030000
2D036036000
2E024024000
2F018018000
3A020002000
3B0240202200
3C0300502500
3D0410803300
3E0320602600
3F024002400

Download the complete model and results · Download the input assumptions · Download the exhaustive Python checker. To reproduce the published example, put the checker and inputs.json in the same folder and run python3 model.py. It reads the adjacent inputs and writes model.json. The checker alone can also run its built-in example.

To try your own probabilities, save a copy of the inputs as my-inputs.json, edit it, then run python3 model.py --input my-inputs.json --output my-results.json. The checker reads your file and writes the results to the separate path you chose. The result includes the probabilities under model and the SHA-256 digest of your input file under certificate.inputFileSha256.

Sources and construction

Noam Mazor and Rafael Pass, Counting from Geographic Information Retrieval, November 2026: source for the computational decomposition and retrieval ideas. The allocation model, numerical assumptions and diagrams here are our construction.

Cumbria Wildlife Trust’s Skiddaw Forest description and Skiddaw House’s account of the surrounding fells establish the real fell, bog and hostel setting. No source describes the railway, its alignment or the invented quantities used here.

Abramsky and Brandenburger provide the global-section perspective; Robinson develops sheaf sampling; Bar-Yossef and colleagues establish index coding with side information. These sources support the distinctions explained in Reading, not a measured improvement in railway design.

Codex, with Lawrence Rowland · 28 November 2026. Original explanatory diagrams. Exact finite model verified; practical usefulness and probability calibration remain open.