  "version": "calva-earthworks-1",
  "title": "The Calva earthworks handover",
  "fiction": "An invented railway alignment, schematic placement relative to the real hostel, geometry and probability model. Not surveyed Calva conditions or engineering advice.",
  "probabilityDenominator": 10000,
  "probabilityMeaning": "Assumed marginal probability that a named discrepancy remains unresolved at the agreed handover checkpoint. These numbers are chosen illustrative inputs, not frequencies inferred from observations.",
  "objectiveMeaning": "Expected number of unresolved named seam discrepancies = sum of their marginal probabilities. A seam can contribute quantity, level and gradient events separately. No independence assumption, and not the probability of at least one failure.",
  "ownershipMeaning": "An allocation changes responsibility and assumed review efficacy. It does not repair geometry, change quantities, alter the fixed transfer ledger, or remove a known discrepancy.",
  "packageConstraint": "Three interchangeable packages, exactly six tiles each; connected packages are the principal admissible set. Unrestricted balanced partitions are also enumerated as a lower-bound comparison.",
  "stages": [
    "Strip and store",
    "Formation and drainage",
    "Trim and reinstate"
  ],
  "tiles": [
    {
      "id": 0,
      "code": "1A",
      "stage": 0,
      "stageName": "Strip and store",
      "chainageCell": 0,
      "chainageStartM": 0,
      "chainageEndM": 100,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 180,
      "topsoilPlacedM3": 0
    },
    {
      "id": 1,
      "code": "1B",
      "stage": 0,
      "stageName": "Strip and store",
      "chainageCell": 1,
      "chainageStartM": 100,
      "chainageEndM": 200,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 240,
      "topsoilPlacedM3": 0
    },
    {
      "id": 2,
      "code": "1C",
      "stage": 0,
      "stageName": "Strip and store",
      "chainageCell": 2,
      "chainageStartM": 200,
      "chainageEndM": 300,
      "context": "Bog beside the imagined youth hostel",
      "topsoilStrippedM3": 300,
      "topsoilPlacedM3": 0
    },
    {
      "id": 3,
      "code": "1D",
      "stage": 0,
      "stageName": "Strip and store",
      "chainageCell": 3,
      "chainageStartM": 300,
      "chainageEndM": 400,
      "context": "Bog beside the imagined youth hostel",
      "topsoilStrippedM3": 360,
      "topsoilPlacedM3": 0
    },
    {
      "id": 4,
      "code": "1E",
      "stage": 0,
      "stageName": "Strip and store",
      "chainageCell": 4,
      "chainageStartM": 400,
      "chainageEndM": 500,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 240,
      "topsoilPlacedM3": 0
    },
    {
      "id": 5,
      "code": "1F",
      "stage": 0,
      "stageName": "Strip and store",
      "chainageCell": 5,
      "chainageStartM": 500,
      "chainageEndM": 600,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 180,
      "topsoilPlacedM3": 0
    },
    {
      "id": 6,
      "code": "2A",
      "stage": 1,
      "stageName": "Formation and drainage",
      "chainageCell": 0,
      "chainageStartM": 0,
      "chainageEndM": 100,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 0
    },
    {
      "id": 7,
      "code": "2B",
      "stage": 1,
      "stageName": "Formation and drainage",
      "chainageCell": 1,
      "chainageStartM": 100,
      "chainageEndM": 200,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 0
    },
    {
      "id": 8,
      "code": "2C",
      "stage": 1,
      "stageName": "Formation and drainage",
      "chainageCell": 2,
      "chainageStartM": 200,
      "chainageEndM": 300,
      "context": "Bog beside the imagined youth hostel",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 0
    },
    {
      "id": 9,
      "code": "2D",
      "stage": 1,
      "stageName": "Formation and drainage",
      "chainageCell": 3,
      "chainageStartM": 300,
      "chainageEndM": 400,
      "context": "Bog beside the imagined youth hostel",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 0
    },
    {
      "id": 10,
      "code": "2E",
      "stage": 1,
      "stageName": "Formation and drainage",
      "chainageCell": 4,
      "chainageStartM": 400,
      "chainageEndM": 500,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 0
    },
    {
      "id": 11,
      "code": "2F",
      "stage": 1,
      "stageName": "Formation and drainage",
      "chainageCell": 5,
      "chainageStartM": 500,
      "chainageEndM": 600,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 0
    },
    {
      "id": 12,
      "code": "3A",
      "stage": 2,
      "stageName": "Trim and reinstate",
      "chainageCell": 0,
      "chainageStartM": 0,
      "chainageEndM": 100,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 200
    },
    {
      "id": 13,
      "code": "3B",
      "stage": 2,
      "stageName": "Trim and reinstate",
      "chainageCell": 1,
      "chainageStartM": 100,
      "chainageEndM": 200,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 220
    },
    {
      "id": 14,
      "code": "3C",
      "stage": 2,
      "stageName": "Trim and reinstate",
      "chainageCell": 2,
      "chainageStartM": 200,
      "chainageEndM": 300,
      "context": "Bog beside the imagined youth hostel",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 250
    },
    {
      "id": 15,
      "code": "3D",
      "stage": 2,
      "stageName": "Trim and reinstate",
      "chainageCell": 3,
      "chainageStartM": 300,
      "chainageEndM": 400,
      "context": "Bog beside the imagined youth hostel",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 330
    },
    {
      "id": 16,
      "code": "3E",
      "stage": 2,
      "stageName": "Trim and reinstate",
      "chainageCell": 4,
      "chainageStartM": 400,
      "chainageEndM": 500,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 260
    },
    {
      "id": 17,
      "code": "3F",
      "stage": 2,
      "stageName": "Trim and reinstate",
      "chainageCell": 5,
      "chainageStartM": 500,
      "chainageEndM": 600,
      "context": "Steep railway climb",
      "topsoilStrippedM3": 0,
      "topsoilPlacedM3": 240
    }
  ],
  "edges": [
    {
      "id": 0,
      "u": 0,
      "v": 1,
      "kind": "space",
      "nearBog": false,
      "label": "1A / 1B",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 5,
      "levelGapMm": 6,
      "gradientGapMilliPermille": 20,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 26,
            "crossBp": 106
          },
          "wet_bog": {
            "withinBp": 26,
            "crossBp": 106
          },
          "bog_joint_review": {
            "withinBp": 26,
            "crossBp": 106
          }
        },
        "level": {
          "reference": {
            "withinBp": 13,
            "crossBp": 53
          },
          "wet_bog": {
            "withinBp": 13,
            "crossBp": 53
          },
          "bog_joint_review": {
            "withinBp": 13,
            "crossBp": 53
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 10,
            "crossBp": 30
          },
          "wet_bog": {
            "withinBp": 10,
            "crossBp": 30
          },
          "bog_joint_review": {
            "withinBp": 10,
            "crossBp": 30
          }
        }
      }
    },
    {
      "id": 1,
      "u": 1,
      "v": 2,
      "kind": "space",
      "nearBog": true,
      "label": "1B / 1C",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 20,
      "levelGapMm": 8,
      "gradientGapMilliPermille": 30,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 60,
            "crossBp": 240
          },
          "wet_bog": {
            "withinBp": 90,
            "crossBp": 630
          },
          "bog_joint_review": {
            "withinBp": 60,
            "crossBp": 105
          }
        },
        "level": {
          "reference": {
            "withinBp": 23,
            "crossBp": 93
          },
          "wet_bog": {
            "withinBp": 34,
            "crossBp": 244
          },
          "bog_joint_review": {
            "withinBp": 23,
            "crossBp": 40
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 10,
            "crossBp": 35
          },
          "wet_bog": {
            "withinBp": 15,
            "crossBp": 90
          },
          "bog_joint_review": {
            "withinBp": 10,
            "crossBp": 16
          }
        }
      }
    },
    {
      "id": 2,
      "u": 2,
      "v": 3,
      "kind": "space",
      "nearBog": true,
      "label": "1C / 1D",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 20,
      "levelGapMm": 10,
      "gradientGapMilliPermille": 40,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 46,
            "crossBp": 186
          },
          "wet_bog": {
            "withinBp": 69,
            "crossBp": 489
          },
          "bog_joint_review": {
            "withinBp": 46,
            "crossBp": 81
          }
        },
        "level": {
          "reference": {
            "withinBp": 28,
            "crossBp": 113
          },
          "wet_bog": {
            "withinBp": 42,
            "crossBp": 297
          },
          "bog_joint_review": {
            "withinBp": 28,
            "crossBp": 49
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 10,
            "crossBp": 40
          },
          "wet_bog": {
            "withinBp": 15,
            "crossBp": 105
          },
          "bog_joint_review": {
            "withinBp": 10,
            "crossBp": 17
          }
        }
      }
    },
    {
      "id": 3,
      "u": 3,
      "v": 4,
      "kind": "space",
      "nearBog": true,
      "label": "1D / 1E",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 20,
      "levelGapMm": 12,
      "gradientGapMilliPermille": 50,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 33,
            "crossBp": 133
          },
          "wet_bog": {
            "withinBp": 49,
            "crossBp": 349
          },
          "bog_joint_review": {
            "withinBp": 33,
            "crossBp": 58
          }
        },
        "level": {
          "reference": {
            "withinBp": 21,
            "crossBp": 86
          },
          "wet_bog": {
            "withinBp": 31,
            "crossBp": 226
          },
          "bog_joint_review": {
            "withinBp": 21,
            "crossBp": 37
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 16,
            "crossBp": 66
          },
          "wet_bog": {
            "withinBp": 24,
            "crossBp": 174
          },
          "bog_joint_review": {
            "withinBp": 16,
            "crossBp": 28
          }
        }
      }
    },
    {
      "id": 4,
      "u": 4,
      "v": 5,
      "kind": "space",
      "nearBog": false,
      "label": "1E / 1F",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 5,
      "levelGapMm": 14,
      "gradientGapMilliPermille": 60,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 20,
            "crossBp": 80
          },
          "wet_bog": {
            "withinBp": 20,
            "crossBp": 80
          },
          "bog_joint_review": {
            "withinBp": 20,
            "crossBp": 80
          }
        },
        "level": {
          "reference": {
            "withinBp": 11,
            "crossBp": 46
          },
          "wet_bog": {
            "withinBp": 11,
            "crossBp": 46
          },
          "bog_joint_review": {
            "withinBp": 11,
            "crossBp": 46
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 28,
            "crossBp": 113
          },
          "wet_bog": {
            "withinBp": 28,
            "crossBp": 113
          },
          "bog_joint_review": {
            "withinBp": 28,
            "crossBp": 113
          }
        }
      }
    },
    {
      "id": 5,
      "u": 6,
      "v": 7,
      "kind": "space",
      "nearBog": false,
      "label": "2A / 2B",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 10,
      "levelGapMm": 10,
      "gradientGapMilliPermille": 30,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 20,
            "crossBp": 80
          },
          "wet_bog": {
            "withinBp": 20,
            "crossBp": 80
          },
          "bog_joint_review": {
            "withinBp": 20,
            "crossBp": 80
          }
        },
        "level": {
          "reference": {
            "withinBp": 30,
            "crossBp": 120
          },
          "wet_bog": {
            "withinBp": 30,
            "crossBp": 120
          },
          "bog_joint_review": {
            "withinBp": 30,
            "crossBp": 120
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 20,
            "crossBp": 80
          },
          "wet_bog": {
            "withinBp": 20,
            "crossBp": 80
          },
          "bog_joint_review": {
            "withinBp": 20,
            "crossBp": 80
          }
        }
      }
    },
    {
      "id": 6,
      "u": 7,
      "v": 8,
      "kind": "space",
      "nearBog": true,
      "label": "2B / 2C",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 25,
      "levelGapMm": 12,
      "gradientGapMilliPermille": 40,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 53,
            "crossBp": 213
          },
          "wet_bog": {
            "withinBp": 79,
            "crossBp": 559
          },
          "bog_joint_review": {
            "withinBp": 53,
            "crossBp": 93
          }
        },
        "level": {
          "reference": {
            "withinBp": 63,
            "crossBp": 253
          },
          "wet_bog": {
            "withinBp": 94,
            "crossBp": 664
          },
          "bog_joint_review": {
            "withinBp": 63,
            "crossBp": 110
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 30,
            "crossBp": 120
          },
          "wet_bog": {
            "withinBp": 45,
            "crossBp": 315
          },
          "bog_joint_review": {
            "withinBp": 30,
            "crossBp": 52
          }
        }
      }
    },
    {
      "id": 7,
      "u": 8,
      "v": 9,
      "kind": "space",
      "nearBog": true,
      "label": "2C / 2D",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 25,
      "levelGapMm": 14,
      "gradientGapMilliPermille": 50,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 40,
            "crossBp": 160
          },
          "wet_bog": {
            "withinBp": 60,
            "crossBp": 420
          },
          "bog_joint_review": {
            "withinBp": 40,
            "crossBp": 70
          }
        },
        "level": {
          "reference": {
            "withinBp": 70,
            "crossBp": 280
          },
          "wet_bog": {
            "withinBp": 105,
            "crossBp": 735
          },
          "bog_joint_review": {
            "withinBp": 70,
            "crossBp": 122
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 40,
            "crossBp": 160
          },
          "wet_bog": {
            "withinBp": 60,
            "crossBp": 420
          },
          "bog_joint_review": {
            "withinBp": 40,
            "crossBp": 70
          }
        }
      }
    },
    {
      "id": 8,
      "u": 9,
      "v": 10,
      "kind": "space",
      "nearBog": true,
      "label": "2D / 2E",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 25,
      "levelGapMm": 16,
      "gradientGapMilliPermille": 60,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 43,
            "crossBp": 173
          },
          "wet_bog": {
            "withinBp": 64,
            "crossBp": 454
          },
          "bog_joint_review": {
            "withinBp": 43,
            "crossBp": 75
          }
        },
        "level": {
          "reference": {
            "withinBp": 46,
            "crossBp": 186
          },
          "wet_bog": {
            "withinBp": 69,
            "crossBp": 489
          },
          "bog_joint_review": {
            "withinBp": 46,
            "crossBp": 81
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 60,
            "crossBp": 240
          },
          "wet_bog": {
            "withinBp": 90,
            "crossBp": 630
          },
          "bog_joint_review": {
            "withinBp": 60,
            "crossBp": 105
          }
        }
      }
    },
    {
      "id": 9,
      "u": 10,
      "v": 11,
      "kind": "space",
      "nearBog": false,
      "label": "2E / 2F",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 10,
      "levelGapMm": 18,
      "gradientGapMilliPermille": 70,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 26,
            "crossBp": 106
          },
          "wet_bog": {
            "withinBp": 26,
            "crossBp": 106
          },
          "bog_joint_review": {
            "withinBp": 26,
            "crossBp": 106
          }
        },
        "level": {
          "reference": {
            "withinBp": 30,
            "crossBp": 120
          },
          "wet_bog": {
            "withinBp": 30,
            "crossBp": 120
          },
          "bog_joint_review": {
            "withinBp": 30,
            "crossBp": 120
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 73,
            "crossBp": 293
          },
          "wet_bog": {
            "withinBp": 73,
            "crossBp": 293
          },
          "bog_joint_review": {
            "withinBp": 73,
            "crossBp": 293
          }
        }
      }
    },
    {
      "id": 10,
      "u": 12,
      "v": 13,
      "kind": "space",
      "nearBog": false,
      "label": "3A / 3B",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": -20,
      "quantityPlanGapM3": 20,
      "levelGapMm": 14,
      "gradientGapMilliPermille": 40,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 10,
            "crossBp": 40
          },
          "wet_bog": {
            "withinBp": 10,
            "crossBp": 40
          },
          "bog_joint_review": {
            "withinBp": 10,
            "crossBp": 40
          }
        },
        "level": {
          "reference": {
            "withinBp": 36,
            "crossBp": 146
          },
          "wet_bog": {
            "withinBp": 36,
            "crossBp": 146
          },
          "bog_joint_review": {
            "withinBp": 36,
            "crossBp": 146
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 30,
            "crossBp": 120
          },
          "wet_bog": {
            "withinBp": 30,
            "crossBp": 120
          },
          "bog_joint_review": {
            "withinBp": 30,
            "crossBp": 120
          }
        }
      }
    },
    {
      "id": 11,
      "u": 13,
      "v": 14,
      "kind": "space",
      "nearBog": true,
      "label": "3B / 3C",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 0,
      "quantityPlanGapM3": 30,
      "levelGapMm": 16,
      "gradientGapMilliPermille": 50,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 13,
            "crossBp": 53
          },
          "wet_bog": {
            "withinBp": 19,
            "crossBp": 139
          },
          "bog_joint_review": {
            "withinBp": 13,
            "crossBp": 23
          }
        },
        "level": {
          "reference": {
            "withinBp": 43,
            "crossBp": 173
          },
          "wet_bog": {
            "withinBp": 64,
            "crossBp": 454
          },
          "bog_joint_review": {
            "withinBp": 43,
            "crossBp": 75
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 33,
            "crossBp": 133
          },
          "wet_bog": {
            "withinBp": 49,
            "crossBp": 349
          },
          "bog_joint_review": {
            "withinBp": 33,
            "crossBp": 58
          }
        }
      }
    },
    {
      "id": 12,
      "u": 14,
      "v": 15,
      "kind": "space",
      "nearBog": true,
      "label": "3C / 3D",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 50,
      "quantityPlanGapM3": 35,
      "levelGapMm": 18,
      "gradientGapMilliPermille": 60,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 11,
            "crossBp": 46
          },
          "wet_bog": {
            "withinBp": 16,
            "crossBp": 121
          },
          "bog_joint_review": {
            "withinBp": 11,
            "crossBp": 19
          }
        },
        "level": {
          "reference": {
            "withinBp": 50,
            "crossBp": 200
          },
          "wet_bog": {
            "withinBp": 75,
            "crossBp": 525
          },
          "bog_joint_review": {
            "withinBp": 50,
            "crossBp": 87
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 46,
            "crossBp": 186
          },
          "wet_bog": {
            "withinBp": 69,
            "crossBp": 489
          },
          "bog_joint_review": {
            "withinBp": 46,
            "crossBp": 81
          }
        }
      }
    },
    {
      "id": 13,
      "u": 15,
      "v": 16,
      "kind": "space",
      "nearBog": true,
      "label": "3D / 3E",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 80,
      "quantityPlanGapM3": 35,
      "levelGapMm": 20,
      "gradientGapMilliPermille": 70,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 16,
            "crossBp": 66
          },
          "wet_bog": {
            "withinBp": 24,
            "crossBp": 174
          },
          "bog_joint_review": {
            "withinBp": 16,
            "crossBp": 28
          }
        },
        "level": {
          "reference": {
            "withinBp": 56,
            "crossBp": 226
          },
          "wet_bog": {
            "withinBp": 84,
            "crossBp": 594
          },
          "bog_joint_review": {
            "withinBp": 56,
            "crossBp": 98
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 66,
            "crossBp": 266
          },
          "wet_bog": {
            "withinBp": 99,
            "crossBp": 699
          },
          "bog_joint_review": {
            "withinBp": 66,
            "crossBp": 116
          }
        }
      }
    },
    {
      "id": 14,
      "u": 16,
      "v": 17,
      "kind": "space",
      "nearBog": false,
      "label": "3E / 3F",
      "comparison": "Same geographic interface in one stage",
      "nominalSignedTransferM3": 60,
      "quantityPlanGapM3": 20,
      "levelGapMm": 22,
      "gradientGapMilliPermille": 80,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 23,
            "crossBp": 93
          },
          "wet_bog": {
            "withinBp": 23,
            "crossBp": 93
          },
          "bog_joint_review": {
            "withinBp": 23,
            "crossBp": 93
          }
        },
        "level": {
          "reference": {
            "withinBp": 66,
            "crossBp": 266
          },
          "wet_bog": {
            "withinBp": 66,
            "crossBp": 266
          },
          "bog_joint_review": {
            "withinBp": 66,
            "crossBp": 266
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 86,
            "crossBp": 346
          },
          "wet_bog": {
            "withinBp": 86,
            "crossBp": 346
          },
          "bog_joint_review": {
            "withinBp": 86,
            "crossBp": 346
          }
        }
      }
    },
    {
      "id": 15,
      "u": 0,
      "v": 6,
      "kind": "time",
      "nearBog": false,
      "label": "1A / 2A",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 180,
      "quantityPlanGapM3": 10,
      "levelGapMm": 4,
      "gradientGapMilliPermille": 20,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 36,
            "crossBp": 146
          },
          "wet_bog": {
            "withinBp": 36,
            "crossBp": 146
          },
          "bog_joint_review": {
            "withinBp": 36,
            "crossBp": 146
          }
        },
        "level": {
          "reference": {
            "withinBp": 20,
            "crossBp": 80
          },
          "wet_bog": {
            "withinBp": 20,
            "crossBp": 80
          },
          "bog_joint_review": {
            "withinBp": 20,
            "crossBp": 80
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 13,
            "crossBp": 53
          },
          "wet_bog": {
            "withinBp": 13,
            "crossBp": 53
          },
          "bog_joint_review": {
            "withinBp": 13,
            "crossBp": 53
          }
        }
      }
    },
    {
      "id": 16,
      "u": 1,
      "v": 7,
      "kind": "time",
      "nearBog": false,
      "label": "1B / 2B",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 240,
      "quantityPlanGapM3": 10,
      "levelGapMm": 5,
      "gradientGapMilliPermille": 30,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 50,
            "crossBp": 200
          },
          "wet_bog": {
            "withinBp": 50,
            "crossBp": 200
          },
          "bog_joint_review": {
            "withinBp": 50,
            "crossBp": 200
          }
        },
        "level": {
          "reference": {
            "withinBp": 26,
            "crossBp": 106
          },
          "wet_bog": {
            "withinBp": 26,
            "crossBp": 106
          },
          "bog_joint_review": {
            "withinBp": 26,
            "crossBp": 106
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 13,
            "crossBp": 53
          },
          "wet_bog": {
            "withinBp": 13,
            "crossBp": 53
          },
          "bog_joint_review": {
            "withinBp": 13,
            "crossBp": 53
          }
        }
      }
    },
    {
      "id": 17,
      "u": 2,
      "v": 8,
      "kind": "time",
      "nearBog": true,
      "label": "1C / 2C",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 300,
      "quantityPlanGapM3": 25,
      "levelGapMm": 6,
      "gradientGapMilliPermille": 40,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 100,
            "crossBp": 400
          },
          "wet_bog": {
            "withinBp": 150,
            "crossBp": 600
          },
          "bog_joint_review": {
            "withinBp": 100,
            "crossBp": 175
          }
        },
        "level": {
          "reference": {
            "withinBp": 33,
            "crossBp": 133
          },
          "wet_bog": {
            "withinBp": 49,
            "crossBp": 199
          },
          "bog_joint_review": {
            "withinBp": 33,
            "crossBp": 58
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 20,
            "crossBp": 80
          },
          "wet_bog": {
            "withinBp": 30,
            "crossBp": 120
          },
          "bog_joint_review": {
            "withinBp": 20,
            "crossBp": 35
          }
        }
      }
    },
    {
      "id": 18,
      "u": 3,
      "v": 9,
      "kind": "time",
      "nearBog": true,
      "label": "1D / 2D",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 360,
      "quantityPlanGapM3": 25,
      "levelGapMm": 7,
      "gradientGapMilliPermille": 50,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 120,
            "crossBp": 480
          },
          "wet_bog": {
            "withinBp": 180,
            "crossBp": 720
          },
          "bog_joint_review": {
            "withinBp": 120,
            "crossBp": 210
          }
        },
        "level": {
          "reference": {
            "withinBp": 36,
            "crossBp": 146
          },
          "wet_bog": {
            "withinBp": 54,
            "crossBp": 219
          },
          "bog_joint_review": {
            "withinBp": 36,
            "crossBp": 63
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 20,
            "crossBp": 80
          },
          "wet_bog": {
            "withinBp": 30,
            "crossBp": 120
          },
          "bog_joint_review": {
            "withinBp": 20,
            "crossBp": 35
          }
        }
      }
    },
    {
      "id": 19,
      "u": 4,
      "v": 10,
      "kind": "time",
      "nearBog": false,
      "label": "1E / 2E",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 240,
      "quantityPlanGapM3": 10,
      "levelGapMm": 8,
      "gradientGapMilliPermille": 60,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 53,
            "crossBp": 213
          },
          "wet_bog": {
            "withinBp": 53,
            "crossBp": 213
          },
          "bog_joint_review": {
            "withinBp": 53,
            "crossBp": 213
          }
        },
        "level": {
          "reference": {
            "withinBp": 23,
            "crossBp": 93
          },
          "wet_bog": {
            "withinBp": 23,
            "crossBp": 93
          },
          "bog_joint_review": {
            "withinBp": 23,
            "crossBp": 93
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 26,
            "crossBp": 106
          },
          "wet_bog": {
            "withinBp": 26,
            "crossBp": 106
          },
          "bog_joint_review": {
            "withinBp": 26,
            "crossBp": 106
          }
        }
      }
    },
    {
      "id": 20,
      "u": 5,
      "v": 11,
      "kind": "time",
      "nearBog": false,
      "label": "1F / 2F",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 180,
      "quantityPlanGapM3": 10,
      "levelGapMm": 9,
      "gradientGapMilliPermille": 70,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 33,
            "crossBp": 133
          },
          "wet_bog": {
            "withinBp": 33,
            "crossBp": 133
          },
          "bog_joint_review": {
            "withinBp": 33,
            "crossBp": 133
          }
        },
        "level": {
          "reference": {
            "withinBp": 20,
            "crossBp": 80
          },
          "wet_bog": {
            "withinBp": 20,
            "crossBp": 80
          },
          "bog_joint_review": {
            "withinBp": 20,
            "crossBp": 80
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 33,
            "crossBp": 133
          },
          "wet_bog": {
            "withinBp": 33,
            "crossBp": 133
          },
          "bog_joint_review": {
            "withinBp": 33,
            "crossBp": 133
          }
        }
      }
    },
    {
      "id": 21,
      "u": 6,
      "v": 12,
      "kind": "time",
      "nearBog": false,
      "label": "2A / 3A",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 180,
      "quantityPlanGapM3": 15,
      "levelGapMm": 7,
      "gradientGapMilliPermille": 20,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 16,
            "crossBp": 66
          },
          "wet_bog": {
            "withinBp": 16,
            "crossBp": 66
          },
          "bog_joint_review": {
            "withinBp": 16,
            "crossBp": 66
          }
        },
        "level": {
          "reference": {
            "withinBp": 40,
            "crossBp": 160
          },
          "wet_bog": {
            "withinBp": 40,
            "crossBp": 160
          },
          "bog_joint_review": {
            "withinBp": 40,
            "crossBp": 160
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 33,
            "crossBp": 133
          },
          "wet_bog": {
            "withinBp": 33,
            "crossBp": 133
          },
          "bog_joint_review": {
            "withinBp": 33,
            "crossBp": 133
          }
        }
      }
    },
    {
      "id": 22,
      "u": 7,
      "v": 13,
      "kind": "time",
      "nearBog": false,
      "label": "2B / 3B",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 240,
      "quantityPlanGapM3": 15,
      "levelGapMm": 8,
      "gradientGapMilliPermille": 30,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 23,
            "crossBp": 93
          },
          "wet_bog": {
            "withinBp": 23,
            "crossBp": 93
          },
          "bog_joint_review": {
            "withinBp": 23,
            "crossBp": 93
          }
        },
        "level": {
          "reference": {
            "withinBp": 43,
            "crossBp": 173
          },
          "wet_bog": {
            "withinBp": 43,
            "crossBp": 173
          },
          "bog_joint_review": {
            "withinBp": 43,
            "crossBp": 173
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 40,
            "crossBp": 160
          },
          "wet_bog": {
            "withinBp": 40,
            "crossBp": 160
          },
          "bog_joint_review": {
            "withinBp": 40,
            "crossBp": 160
          }
        }
      }
    },
    {
      "id": 23,
      "u": 8,
      "v": 14,
      "kind": "time",
      "nearBog": true,
      "label": "2C / 3C",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 300,
      "quantityPlanGapM3": 30,
      "levelGapMm": 9,
      "gradientGapMilliPermille": 40,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 53,
            "crossBp": 213
          },
          "wet_bog": {
            "withinBp": 79,
            "crossBp": 319
          },
          "bog_joint_review": {
            "withinBp": 53,
            "crossBp": 93
          }
        },
        "level": {
          "reference": {
            "withinBp": 50,
            "crossBp": 200
          },
          "wet_bog": {
            "withinBp": 75,
            "crossBp": 300
          },
          "bog_joint_review": {
            "withinBp": 50,
            "crossBp": 87
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 46,
            "crossBp": 186
          },
          "wet_bog": {
            "withinBp": 69,
            "crossBp": 279
          },
          "bog_joint_review": {
            "withinBp": 46,
            "crossBp": 81
          }
        }
      }
    },
    {
      "id": 24,
      "u": 9,
      "v": 15,
      "kind": "time",
      "nearBog": true,
      "label": "2D / 3D",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 360,
      "quantityPlanGapM3": 30,
      "levelGapMm": 10,
      "gradientGapMilliPermille": 50,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 60,
            "crossBp": 240
          },
          "wet_bog": {
            "withinBp": 90,
            "crossBp": 360
          },
          "bog_joint_review": {
            "withinBp": 60,
            "crossBp": 105
          }
        },
        "level": {
          "reference": {
            "withinBp": 50,
            "crossBp": 200
          },
          "wet_bog": {
            "withinBp": 75,
            "crossBp": 300
          },
          "bog_joint_review": {
            "withinBp": 50,
            "crossBp": 87
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 50,
            "crossBp": 200
          },
          "wet_bog": {
            "withinBp": 75,
            "crossBp": 300
          },
          "bog_joint_review": {
            "withinBp": 50,
            "crossBp": 87
          }
        }
      }
    },
    {
      "id": 25,
      "u": 10,
      "v": 16,
      "kind": "time",
      "nearBog": false,
      "label": "2E / 3E",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 240,
      "quantityPlanGapM3": 15,
      "levelGapMm": 11,
      "gradientGapMilliPermille": 60,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 30,
            "crossBp": 120
          },
          "wet_bog": {
            "withinBp": 30,
            "crossBp": 120
          },
          "bog_joint_review": {
            "withinBp": 30,
            "crossBp": 120
          }
        },
        "level": {
          "reference": {
            "withinBp": 46,
            "crossBp": 186
          },
          "wet_bog": {
            "withinBp": 46,
            "crossBp": 186
          },
          "bog_joint_review": {
            "withinBp": 46,
            "crossBp": 186
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 80,
            "crossBp": 320
          },
          "wet_bog": {
            "withinBp": 80,
            "crossBp": 320
          },
          "bog_joint_review": {
            "withinBp": 80,
            "crossBp": 320
          }
        }
      }
    },
    {
      "id": 26,
      "u": 11,
      "v": 17,
      "kind": "time",
      "nearBog": false,
      "label": "2F / 3F",
      "comparison": "Previous-stage handover surface versus next-stage inherited starting surface",
      "nominalSignedTransferM3": 180,
      "quantityPlanGapM3": 15,
      "levelGapMm": 12,
      "gradientGapMilliPermille": 70,
      "risk": {
        "quantity": {
          "reference": {
            "withinBp": 20,
            "crossBp": 80
          },
          "wet_bog": {
            "withinBp": 20,
            "crossBp": 80
          },
          "bog_joint_review": {
            "withinBp": 20,
            "crossBp": 80
          }
        },
        "level": {
          "reference": {
            "withinBp": 50,
            "crossBp": 200
          },
          "wet_bog": {
            "withinBp": 50,
            "crossBp": 200
          },
          "bog_joint_review": {
            "withinBp": 50,
            "crossBp": 200
          }
        },
        "gradient": {
          "reference": {
            "withinBp": 100,
            "crossBp": 400
          },
          "wet_bog": {
            "withinBp": 100,
            "crossBp": 400
          },
          "bog_joint_review": {
            "withinBp": 100,
            "crossBp": 400
          }
        }
      }
    }
  ],
  "profiles": [
    {
      "id": "reference",
      "label": "Reference assumptions"
    },
    {
      "id": "wet_bog",
      "label": "Wet bog handoffs"
    },
    {
      "id": "bog_joint_review",
      "label": "Joint review at the bog"
    }
  ],
  "materialLedger": {
    "material": "Topsoil only; fixed nominal conserved transfer plan, distinct from provisional quantity disagreements",
    "strippedM3": 1500,
    "placedM3": 1500,
    "exportedM3": 0,
    "importedM3": 0,
    "endingStoredM3": 0,
    "tiles": [
      {
        "tile": 0,
        "sourceStrippedM3": 180,
        "incomingM3": 0,
        "outgoingM3": 180,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 1,
        "sourceStrippedM3": 240,
        "incomingM3": 0,
        "outgoingM3": 240,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 2,
        "sourceStrippedM3": 300,
        "incomingM3": 0,
        "outgoingM3": 300,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 3,
        "sourceStrippedM3": 360,
        "incomingM3": 0,
        "outgoingM3": 360,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 4,
        "sourceStrippedM3": 240,
        "incomingM3": 0,
        "outgoingM3": 240,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 5,
        "sourceStrippedM3": 180,
        "incomingM3": 0,
        "outgoingM3": 180,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 6,
        "sourceStrippedM3": 0,
        "incomingM3": 180,
        "outgoingM3": 180,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 7,
        "sourceStrippedM3": 0,
        "incomingM3": 240,
        "outgoingM3": 240,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 8,
        "sourceStrippedM3": 0,
        "incomingM3": 300,
        "outgoingM3": 300,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 9,
        "sourceStrippedM3": 0,
        "incomingM3": 360,
        "outgoingM3": 360,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 10,
        "sourceStrippedM3": 0,
        "incomingM3": 240,
        "outgoingM3": 240,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 11,
        "sourceStrippedM3": 0,
        "incomingM3": 180,
        "outgoingM3": 180,
        "sinkPlacedM3": 0,
        "balanceM3": 0
      },
      {
        "tile": 12,
        "sourceStrippedM3": 0,
        "incomingM3": 200,
        "outgoingM3": 0,
        "sinkPlacedM3": 200,
        "balanceM3": 0
      },
      {
        "tile": 13,
        "sourceStrippedM3": 0,
        "incomingM3": 240,
        "outgoingM3": 20,
        "sinkPlacedM3": 220,
        "balanceM3": 0
      },
      {
        "tile": 14,
        "sourceStrippedM3": 0,
        "incomingM3": 300,
        "outgoingM3": 50,
        "sinkPlacedM3": 250,
        "balanceM3": 0
      },
      {
        "tile": 15,
        "sourceStrippedM3": 0,
        "incomingM3": 410,
        "outgoingM3": 80,
        "sinkPlacedM3": 330,
        "balanceM3": 0
      },
      {
        "tile": 16,
        "sourceStrippedM3": 0,
        "incomingM3": 320,
        "outgoingM3": 60,
        "sinkPlacedM3": 260,
        "balanceM3": 0
      },
      {
        "tile": 17,
        "sourceStrippedM3": 0,
        "incomingM3": 240,
        "outgoingM3": 0,
        "sinkPlacedM3": 240,
        "balanceM3": 0
      }
    ]
  },
  "geometryCounterexample": {
    "description": "Two draft models at the same interface both give level 120.000 m and agree on a 50 m3 transfer. Their common-direction tangent grades are +25 and +35 per mille. The quantity ledger balances and the levels match, yet the tangent difference is 10 per mille. This example stipulates a shared tangent target at that interface; it is not a claim that every legitimate vertical curve must have one constant grade.",
    "quantityTransferM3": 50,
    "leftLevelMm": 120000,
    "rightLevelMm": 120000,
    "leftGradePermille": 25,
    "rightGradePermille": 35
  },
  "limitations": [
    "Package labels are interchangeable; no specialist competence, cost, duration or resource differences are modelled.",
    "Tile count is the declared workload proxy. Equal tile counts do not establish equal engineering effort.",
    "Only adjacent cells in the time-by-chainage diagram share seams. Long-range drainage, geotechnical dependencies and temporary works are outside this model.",
    "A temporal seam compares inherited starting conditions, not deliberately changed levels at different stages.",
    "Transfer quantities refer to the same named transfer and material. Adjacent cells need not excavate or consume equal volumes.",
    "The model requires within and cross probabilities to be recalibrated before operational use."
  ]
}