Work can be generated.
With explicit initial facts, final obligations and permissible actions, search produces a route without being given a project task list. Shared setup and eventual removal arise through those rules.
An essay in constructing project work
A finished tunnel contains its equipment. It contains none of the temporary access that made installation possible.
Can the outcome tell us what work is missing? Give this model a goal and permitted methods. It generates a route, then tests which actions can be avoided.
Toy scenario
Method & limits → A first comparison, the complete method note and its sources.
A reason for each action
These links trace facts produced and consumed by this route. A later step is not automatically dependent on the step before it.
The comparison below always uses the same access and methods with both units requested. Shared work retains one identity when B is removed.
For each chosen action, the solver forbids it and searches again. If another successful route exists, that action is method-dependent. If none exists, it is unavoidable in this model.
Both methods still require temporary access. A particular setup action can be avoidable even when the broader function it serves is necessary.
This tests grounded actions against the declared methods. It does not establish necessity in every possible real project.
Four different relationships
A product structure describes physical things. A work breakdown groups the processes needed to deliver them. A process can change a product, use temporary equipment and produce evidence. “Is part of”, “contributes to”, “uses” and “produces” mean different things.
These views interpret this brief’s declared model. Select an item to follow its computed support. The process descriptions are proposed work, not records of work performed.
One route, more than one useful decomposition
Change the packaging rule. Each action is owned once; cross-package support remains visible. These are two supplied organisational choices, not a discovered best organisation.
When the work changes → Refine or regroup this gantry route, then compare a specific handover with waiting for a whole package.
Give both routes the same problem
One route compiles explicit semantic rules into a planning problem. The other uses a separately written PDDL domain and an independent parser and search. Both receive the same brief and count one step per action.
The completion profile is explicitly authored domain knowledge. Scope chooses the local objects to which it applies. The ontology does not discover engineering requirements from their names.
The foundational layer distinguishes objects, processes, qualities and information. The domain layer classifies a requested installation as a unit that needs acceptance evidence. Explicit domain methods and local access and handover rules supply the bridge from those meanings to actions.
The Turtle file is compiled into the model used here. The compiler and rule provenance are inspectable. Merely naming something “equipment” does not tell a planner how to install it.
Planning parity is an informative result. The semantic route makes the origin of obligations and support links explicit; a PDDL application could add the same explanations. We have not measured human modelling effort or established that ontology is better.
Our process search is ordinary finite planning. This essay does not implement the functorial plan-transfer algorithm in the source paper.
The restricted result
With explicit initial facts, final obligations and permissible actions, search produces a route without being given a project task list. Shared setup and eventual removal arise through those rules.
Restrict access or remove a method and previously replaceable work can become unavoidable. Remove a goal and some work disappears; a shared prerequisite can remain.
Causal support does not uniquely choose responsibility or hierarchy. Two packaging rules preserve the same work and expose different interfaces.
A complete WBS for a real tunnel. Automatic discovery of engineering methods. Real safety, resources, time and cost. Full OWL reasoning or general PDDL support. A measurable productivity gain from ontology. Those would each require additional evidence.