An essay in constructing project work

The work that
must exist.

A finished tunnel contains its equipment. It contains none of the temporary access that made installation possible.

Can the outcome tell us what work is missing? Give this model a goal and permitted methods. It generates a route, then tests which actions can be avoided.

A synthetic two-unit tunnel fit-out. The methods and acceptance rules below are supplied assumptions, not Solway engineering requirements.

Change the brief. Watch the work change.

The generated work

Choose an action to inspect its reason

A reason for each action

Follow an outcome back to the work supporting it.

These links trace facts produced and consumed by this route. A later step is not automatically dependent on the step before it.

What survives a smaller scope?

The comparison below always uses the same access and methods with both units requested. Shared work retains one identity when B is removed.

What does “must” mean?

For each chosen action, the solver forbids it and searches again. If another successful route exists, that action is method-dependent. If none exists, it is unavoidable in this model.

Both methods still require temporary access. A particular setup action can be avoidable even when the broader function it serves is necessary.

This tests grounded actions against the declared methods. It does not establish necessity in every possible real project.