The Neidpath wall
Build a crinkle crankle wall above the Tweed.
Survey, access, delivery, foundations, curved brickwork and handover must respect their dependencies. Some tasks can be grouped differently while the work and its necessary order stay the same.
Explore the order of work, a chain that certifies a suitable partition, and the choices between complete groupings of concurrent work. The three essais use explicitly distinguished Neidpath teaching models.
Explore the questions
Hover over a tile for details. Click to enter.Tap a tile to enter.
This is an imagined wall, not a Neidpath works proposal. Group positions are not dates; precedence-compatible groupings still need readiness, resource and planning-purpose checks.