Timing and aggregation in project controls · Essai 01

The winter lanterns

The clerk lays two papers on the harbour committee’s table. One is a £7,200 invoice for twelve winter lanterns. The other has the harbourmaster’s signature against the four already in place. The treasurer divides the first figure by the second and writes £1,800 per light.

Beside that figure the clerk has room for one line. What would you let the minutes say? Move the meeting past two more tides before you settle on the wording.

The clerk’s account

£1,800 invoiced per signed installation

Friday. All four lanterns due by this tide have been signed off.

Harbour ledger · £7,200 invoiced for the batch
TideDueSignedStill due£ per signed light
Friday440£1,800
Monday541 · east light£1,800
Tuesday651 · east light£1,440
Invoice and signed installations

£7,200 invoiced ÷ 4 signed installations.

4 of 12

The same invoice and sign-off rule apply at every cut. The dated ledger is in Evidence.

Write the next minute

A week later someone will have these minutes and neither of the two people who wrote them. The expenditure and the signed count are copied automatically. Which other entry would you leave them? Fix a date, then take entries out one at a time.

Carry into the minute

Tuesday. £7,200 invoiced for the batch. 5 installations signed. 6 due, 5 signed. 1 installation outstanding against plan.

Try leaving only the balance in store. The seven lanterns still on a shelf explain much of Tuesday’s £1,440. They say nothing about how many ought to be there. Put the programme back and the clerk can name the shortfall. The tide book can then identify the job to carry forward.

The job that Monday lost

On Friday the harbour had bought the winter’s supply and fitted its first four lanterns on time. The committee could have made quite a fuss over £1,800. It is exactly the figure it would have seen on Monday, after a crew came back without fitting the east light. Two identical numbers, one of them earned on a day when something went wrong.

Tuesday’s crew fitted the light scheduled for Tuesday. It did nothing to repair Monday’s loss. Yet the treasurer’s figure fell by a fifth, to £1,440. A committee meeting only on Friday and Tuesday could reasonably record a welcome increase in the number of working lights. The crew waiting for the east mounting shoe has a different use for the minutes.

The harbour paid £600 for each lantern. Of Tuesday’s invoice, £3,000 bought the five now in place and £4,200 bought the seven still in store. That allocation uses the equal purchase prices. No one has brought the clerk a timesheet, a boat charge or a bill for the fitting. An installation cost or a promise about crew productivity would need those papers too.

Stewart Brand pictured systems whose fast parts try things and whose slow parts remember them. Here remembering can be quite cheap. A plain return with the invoice, the programme and the sign-offs already tells the committee on Monday that one is overdue. The dated exception earns its line when the committee needs to know which light, and what to send to the quay.

Evidence and replay

A single fictional consignment of twelve identical £600 lanterns arrives before Friday’s review. Each signature consumes one lantern. No further purchases, damage, returns or labour charges are recorded. The plan is held fixed. Four installations fall due by Friday, then one at each of the next two tides.

The account closed on three dates. The invoice is £7,200 throughout.
CutDueSignedIn storeInvoice ÷ signed
Friday448£1,800
Monday548£1,800
Tuesday657£1,440
Reconstruct any of the eight minutes at each cut. Start with the invoice and signed count above, then include or omit each of these three rows.
Additional entryFridayMondayTuesday
ProgrammeAll four due signedOne short of fiveOne short of six
Stores8 remain8 remain7 remain
Tide bookNo missed tide recordedMonday’s east mounting shoe missingMonday’s entry carried forward

The railway precedent. In its 20 May 2010 audit of Network Rail’s Unit Cost Framework, Arup observed that bulk purchases could be charged to a maintenance unit before the associated work, sometimes in a different financial year (§3.54). The regulator later identified this audit and its successor in a public letter. The November report describes the follow-up audit of costs and work volumes. The harbour and every number here are invented. ORR’s letter, p. 1 and note 1 · November follow-up audit

The conceptual source. Brand describes change and continuity at different speeds. The ledger is a small test of what a slow meeting retains of fast work. Stewart Brand, Pace Layering

Replay every choice with Python 3. The script contains the fictional inputs and checks its results before printing them. Download run.py · Download results.json