Portfolio selection for organisational learning · Essai 01

The kitchen that stays open

The council can renew one school kitchen this term. Elm can move its hot lunch to the hall. At Larch, children will keep coming to the hatch while the fitters work.

Larch asks for two extra crew-days. A year from now another crew will open a third kitchen, Ash. What could Larch teach that would earn those days back?

Commission one kitchen

Larch uses 8 crew-days and keeps hot lunch at the hatch. Elm’s renewal waits a term.

22 crew-days · one hot lunch service lost

At Ash, the new crew follows Larch’s report and takes the hatch out first. Returning trolleys meet pupils in the only corridor.

This replay starts with crossing routes at Ash and a report alone. Change either in Try it.

Stand in Ash’s kitchen

The equipment bank and the hatch must both come out. Take the hatch first and a temporary counter can be ready in seven crew-days. Take the equipment out in stages and the old hatch can serve throughout. That sequence takes eleven.

Larch’s report gives the new crew a hatch-first plan. It records where the counter stood and leaves out the path of returning trolleys at lunchtime.

8 first job + 0 handover + 14 at Ash = 22 crew-days.

Seven of Ash’s days are redesign. The counter moves after the first hot service is lost.

Try the two jobs with a straight route, then with a crossing. A useful handover may recommend a different sequence from the one that worked the first time.

What did the board buy?

Elm’s cook can tell the next crew how to serve a hot lunch in a hall. At Ash there is no hall. The Elm crew therefore leaves a cautious instruction for a single-hatch school. Keep the serving hatch working and take the equipment out in stages. That costs eleven days, and lunch carries on.

Larch’s report contains a more ambitious drawing. It puts a temporary counter beside the kitchen door. In Ash’s straight corridor, following the drawing saves four days on the second job. The board spent two to get that experience. Across both jobs it comes out two days ahead.

Follow the same drawing at the crossing and the saving reverses. The cook remembers what the drawing omits. At Larch the tray trolleys used a separate way back. She stands beside the kitchen door at Ash, follows a trolley through the lunch queue and asks where the temporary counter would go. The new crew keeps the old hatch. Here the most valuable thing she passes on is a reason to abandon her own project’s solution.

At a price of one crew-day that visit saves two days overall against simply copying Larch and preserves a hot lunch. Yet the ordinary Elm commission, followed by its cautious advice, would have served both lunches and finished three days sooner. The walk rescues a poor application of the precedent. The earlier decision to seek the precedent still has to earn its keep.

Suppose the board faces only straight and crossing layouts, does not yet know which one Ash has, and requires hot lunch throughout. Larch plus the one-day walk takes 16 days on a straight route and 20 at a crossing. Elm plus its report takes 17 in either layout. Larch’s expected crew time is lower only if the board puts the chance of a straight route above three in four. Neither paper supplies that probability. A board could also give greater weight to which school waits for renewal.

The two commissions on paper

The figures below follow the receiving crew’s advice and charge one combined crew-day for a walk. Each cell gives total crew-days across both schools. All first jobs keep a hot service. The staff would switch to a cold meal for the one disrupted service at Ash.

First job & handoverStraightCrossingSpare hatch
Elm · report171713
Elm · walk181814
Larch · report1522 · one hot service lost15
Larch · walk162016

How to reconstruct any replay

Start with six days at Elm or eight at Larch. Add the walk price if bought. At Ash add seven days for hatch-first or eleven for staged equipment. At the crossing only, hatch-first adds seven days of redesign and interrupts one hot service. The visibly spare hatch makes hatch-first the advice of either crew. At a single hatch, Elm advises staging. Larch advises hatch-first unless its cook sees the crossing. A second crew can override either recommendation.

The replay covers 144 settings across two commissions, three layouts, two handovers, four walk prices and three crew decisions. Some settings produce the same outcome, including every change to the price of a walk nobody took. The table covers all twelve combinations at the standard price using the recommended sequence. These are invented fixtures. The walk assumes the cook and crew can recognise the crossing, and the model leaves the cost of deferring either first school unpriced.

Sources

Mihaela Stan and Freek Vermeulen found steeper learning curves in British fertility clinics that admitted more difficult cases. That finding motivates a board choosing work before the experience exists. It supplies no school cost or estimate of transfer to another crew. Selection at the Gate.

Manon Eikelenboom and Alfons van Marrewijk describe the difficulty of carrying circular-construction knowledge into a municipal waste-hub project despite earlier pilots and extra budget. Their account gives the kitchen trial its receiving crew and its dependence on someone who can interpret a previous job. Tied islands.