Project Contract Lab

Lesson 1 · a seven-card journey

A ventilation system, from Scope to Defects

Contract basis: NEC4 Engineering and Construction Contract (ECC), June 2017 edition revised January 2023, Option A: priced contract with activity schedule. This is a small, unamended teaching example; a live contract’s options, Contract Data, Scope and amendments must be read together.

Open a card to see its scenario, contractual connection and a question to consider. More than one can stay open.

Edition and form: NEC publisher’s NEC4 suite.

  1. Describe
  2. Specify
  3. Programme
  4. Warn
  5. Assess change
  6. Assess payment
  7. Correct defects
1Scope statement · what is being provided?

Scenario: the Contractor will install a modern heating, ventilation and air-conditioning (HVAC) system in a new office building. “State of the art” expresses an ambition, but does not by itself give a measurable acceptance criterion.

Connection: NEC4 uses Scope for requirements and constraints. This overview and the specification in card 2 belong to that same Scope; they are not two independent contractual definitions.

What must the system do, and what evidence will show that it does it?

NEC: terminology changes in NEC4 works contracts.

2Detailed Scope · the measurable requirement

Scenario: maintain 68–72°F (about 20–22°C), with separate controls for each floor and a minimum stated efficiency of 18 SEER. These are the example’s requirements, not a recommended HVAC specification.

Connection: in NEC4 this is Scope; Works Information is the older NEC3 terminology. A real specification would also need an appropriate rating standard, test conditions, operating limits and evidence. “Year-round” alone leaves those conditions unclear.

Could two people interpret the temperature or efficiency requirement differently?

NEC: Works Information becomes Scope.

3Programme · clauses 31 and 32

Scenario: plan installation in weeks 12–15 and testing and commissioning in week 16. The original five-week window includes one week for commissioning.

Connection: the accepted programme supports coordination and assessment of change. Updating it to show a delay does not by itself change the contractual Completion Date; that is a separate contractual process.

Which preceding delivery, access or design decision makes the week-12 start possible?

NEC: the accepted programme and additional time.

4Early warning · clause 15

Scenario: the Contractor learns that the specified unit has a ten-week lead time which could delay installation. Raise the matter promptly so the team can consider earlier ordering, sequencing or another unit.

Connection: NEC4 ECC early warnings sit in clause 15. They bring potential effects on price, time or performance into joint risk management. Giving an early warning does not itself create a compensation event or a payment entitlement.

What action might avoid the delay before anyone assesses its contractual consequences?

NEC4 guidance mapping, clause 15.1; NEC: early warnings and compensation events are distinct (2017 article uses earlier clause numbering).

5Compensation events · clause 60 onwards

Scenario: the Project Manager instructs an upgrade to the Client’s specified HVAC requirements. Assume it is a genuine change to the Client’s Scope, not correction of the Contractor’s non-compliant design.

Connection: a qualifying instruction to change Scope is a compensation event, subject to exceptions. Notification, quotation, assessment and implementation still matter. Its assessed effect may concern time, money, both or neither; it is not simply the difference between two catalogue prices.

What changes in installation, commissioning and planned Completion as well as purchase cost?

NEC: introduction to compensation events; NEC: Scope-change exceptions.

6Price for Work Done to Date · Option A

Scenario: the activity schedule allocates £150,000 of an initial £1,000,000 total to one HVAC installation-and-testing activity. That is 15% by our assumption; NEC does not prescribe a 15% HVAC milestone.

Connection: under Option A, Price for Work Done to Date (PWDD) uses prices for completed activities or groups of activities. Assume this single activity satisfies the contract’s completion test. Part-progress alone does not earn a fraction of that activity’s price.

This activity’s PWDD contribution: £0

This illustration excludes other activities, compensation-event adjustments, retention, tax, prior payments and other amounts due. £150,000 is a contribution to PWDD, not an assessed net payment or permission to invoice.

NEC: Option A pricing and completed activities.

7Defects · definition 11.2(6), clauses 43 and 44

Scenario: testing shows that a zone cannot achieve the temperature range under the agreed test conditions. If the works do not comply with the Scope, that can constitute a Defect; a problem caused by operation outside those conditions is not automatically the same thing.

Connection: NEC4 defines Defects by compliance with Scope and, for Contractor-designed work, relevant law and accepted design. The Contractor and Supervisor have notification duties. The defects date and a notified defect’s correction period are distinct; the Contractor’s obligation to correct is not created only by a notification.

Which requirement failed, how was it tested, and which notification and correction provisions apply?

NEC: defining, notifying and correcting defects.

The sequence is a reading route, not a complete administration workflow. Warnings, programmes, change and defect processes can overlap. The linked publisher guidance was checked on 3 October 2026; it does not replace the actual contract.

Lesson 2 · five packages, four turns each

Can both parties accept a price?

A rail programme is buying bridge, tunnel, station, signalling and electrification packages. You play both parties, with all information visible. Costs, values and offers use price units from 0 to 100, not percentages, pounds or HS2 data.

How to work through the packages

For each package, review the assumptions, set the supplier’s provisional ask, set the client’s provisional bid, then analyse and record the result. You can go back before recording. Five recorded packages end the exercise; Start again clears that run.

Results stay in this tab and are lost when it is reloaded.

Package 1 of 5

Bridge construction

  1. 1. Scenario
  2. 2. Supplier
  3. 3. Client
  4. 4. Analysis

No packages recorded yet.

Your recorded packages

0 agreements · 0 of 5 packages recorded

Record the fourth step of a package to keep its outcome here.

About these lessons

Scope · obligations · agreement

Toy scenario

An office needs a new ventilation system. A rail programme needs five work packages. Explore how a contract connects the first job’s requirements, changes and payment, then see when a price could suit both sides of a negotiation.

Two related lessons: a contract journey from scope through warning to payment, and a price line showing where supplier and client limits overlap.

Two separate teaching examples. The bargaining rule is not an NEC contract procedure. Contractual entitlement asks what follows from the agreed contract and its facts. A mutually acceptable price asks whether both parties prefer an agreement to their alternatives. A price can satisfy the second question without settling the first. This page is educational, not legal, procurement or engineering advice.