Cost allocation and project sequencing · Essai 01

Who orders the second kiln?

Move one booking

Five firing slots come with the lease. The workshop that takes confirmed demand above five pays six counters for another kiln.

Jugs pays six. Its three slots take demand from four to seven.

Tiles 4 → Jugs 7 → Bowls 9 cumulative slots.

A signature worth six counters

Three potters share a former brickworks. Tiles needs four firings a week, Jugs three, Bowls two. On Monday the tile maker signs. The potter who makes jugs has the Tuesday appointment. She can sign then or risk losing a small autumn commission by coming back on Friday.

Putting Bowls ahead of her transfers the entire kiln bill. In the trial she takes Friday, and the kiln order slips from Tuesday to Wednesday. Agreeing the bills across all possible orders brings her back to Tuesday.

Take the jug maker’s appointment →

Would you come back on Friday?

Tiles and Bowls have pencilled in Monday and Wednesday. Your jug commission earns eight counters before the kiln charge. Choose a contract and see what you keep on Tuesday, on Friday or by walking away. The second result allows all three potters to reconsider.

The lease and the order book

You keep two counters. The commission earns eight and the kiln costs you six. Returning on Friday would leave seven.

Once all three can change their booking, the only stable dates are Monday for Tiles, Friday for Jugs and Wednesday for Bowls. Bowls orders the kiln on Wednesday. Jugs bears the one-counter loss from waiting.

Here “stable” means that no single potter can improve their return by changing the date or withdrawing while the others keep their bookings. Two potters striking a side deal would be a different game.

Who wants Tuesday?

On the central programme, moving Jugs later looks perverse. Demand for the kiln is already there, the building is available, and a late signature costs a potter a commission. From her end of the table, paying one counter to escape a six-counter bill is a perfectly good use of Friday.

A different lease averages the cost of joining across every possible arrival order. Tiles tips the works over the limit four times in six. Jugs and Bowls do it once each. If everyone signs, their shares are four, one and one. The figure for Tiles has a curious explanation. Jugs and Bowls together can live within the old lease. Tiles paired with either neighbour needs the second kiln.

That settles an attribution question. To see whether it changes the programme, we have to give the potters their diaries back. When all have binding commissions, both contracts bring them in on their original dates. If the jug commission earns only two counters, the crossing charge makes withdrawal worthwhile even with those fixed dates. A rule on paper can alter the order, the attendance, or just the invoices.

Six orders and four runs of the booking game

The workshop whose signature orders the kiln
Signing orderCrossingCharge
Tiles, Jugs, BowlsJugs, 4 → 76
Tiles, Bowls, JugsBowls, 4 → 66
Jugs, Tiles, BowlsTiles, 3 → 76
Jugs, Bowls, TilesTiles, 5 → 96
Bowls, Tiles, JugsTiles, 2 → 66
Bowls, Jugs, TilesTiles, 5 → 96

Each workshop chooses independently, knowing everyone’s appointments and prices. The original diary reads Tiles Monday, Jugs Tuesday, Bowls Wednesday. Their late appointments are Thursday, Friday morning and Friday afternoon. Withdrawal pays zero. A signed workshop earns 9, 8 or 8 counters respectively, less its bill and any lost commission. In the base run the losses for waiting are 7, 1 and 7. The shared-charge contract recomputes shares among the workshops that actually sign. The kiln is ordered when the threshold is crossed and a later settlement collects the shares.

Every stable schedule, after trying every single-workshop change
TermsCrossing chargeAverage share
Wait costs 7, 1, 7Jugs waits. Bowls orders Wednesday.All early. Jugs orders Tuesday.
Wait costs 1, 1, 1No stable choice of dates.All early. Jugs orders Tuesday.
Fixed datesAll early. Jugs orders Tuesday.All early. Jugs orders Tuesday.
Fixed dates, Jugs earns 2Jugs withdraws. Bowls orders Wednesday.All early. Jugs orders Tuesday.

The two flexible weeks each have 27 possible schedules per contract. Each fixed week has eight. We tested all 140 contract-and-schedule combinations. When waiting costs everyone one, somebody can always gain by changing a date under the crossing charge. This result concerns definite dates. It makes no prediction about randomised booking, bargaining or how long real people would wait.

John Ward’s Northern Line Extension study, p. 41, describes a prospective connection charge in Nine Elms that could leave one developer meeting most of a primary substation’s cost. The study supplies the exposure. The workshops, appointments, money and resulting delay are constructed here. Ward, infrastructure interdependencies, 2014

Nuno Sempere’s third example illustrates averaging marginal contributions over orders, the Shapley value. Applying it to a step in cost determines the fractions used here. Sempere, Shapley values, 2019

Python replay · Saved results