Build a shed halfway up a cliff: dual category view (tasks T vs states S)

A small storage/tool shed built on a prepared terrace halfway up a steep slope/cliff, with planned access (scaffold/rope) and anchoring. Click nodes to explore the mapping.

Category T (tasks as objects, prerequisites as morphisms)

Click a task to highlight its prerequisites/dependents and the induced state/transition on the right.
PERMPERM: Permissions & stakeholder sign-off — Landowner permission / access agreement; planning/HOA checks if needed. SAFETYSAFETY: Risk assessment + method statement (RAMS) — Working-at-height risk assessment, rescue plan, PPE plan, toolbox talk prep. SURVSURV: Site survey & geotech sanity-check — Measure location, slope, drainage; basic ground/rock check for anchors & footings. DESDES: Design + bill of materials — Shed design sized for site; choose foundation/anchoring scheme; produce BOM and cut list. BOOKBOOK: Book/hire access & lifting setup — Line up scaffold/rope-access contractor, edge protection, hauling/lifting kit. ORDERORDER: Order building materials + anchors — Order timber, fixings, roofing, cladding, anchors; arrange deliveries. ACCESSACCESS: Mobilise and set up safe access — Set up scaffold/rope access, edge protection, exclusion zone, material handling plan. ANCHANCH: Install & proof-test anchors/lifelines — Install temporary/permanent anchors for fall protection and for tying-in structure. STAGESTAGE: Haul and stage materials on site — Transport materials to the cliff location (hand-carry/rope haul) and stage safely. TERRTERR: Prepare terrace + erosion control — Cut/level bench; install drainage/erosion control and any retaining elements. FOUNDFOUND: Install foundations/footings — Install piers/footings/ground screws; set posts or base; allow cure time if needed. FRAMEFRAME: Frame the shed & tie-in — Build floor/walls; fix to foundations; tie structure to anchors as designed. ROOFROOF: Roof & waterproofing — Roof framing, sheathing, membrane, flashing so the structure is weather-tight. CLADCLAD: Cladding + doors/windows — External cladding, door, any glazing/vents; weather-seal details. HANDHAND: Final inspection & handover — Snagging, safety check, clean-up, documentation/photos, handover to owner.

Category S (states as objects, inclusions as morphisms)

Click a state to see completed tasks (green) and enabled next tasks (orange) on the left.
PERM SAFETY SAFETY PERM SURV BOOK DES BOOK SURV ACCESS DES ACCESS BOOK ORDER SURV ORDER ACCESS DES BOOK ORDER ACCESS ANCH STAGE TERR FOUND FRAME ROOF CLAD HAND S0S0 (|I|=0): {} S1S1 (|I|=1): {PERM} S2S2 (|I|=1): {SAFETY} S3S3 (|I|=2): {PERM, SAFETY} S4S4 (|I|=3): {PERM, SAFETY, SURV} S5S5 (|I|=3): {PERM, SAFETY, BOOK} S6S6 (|I|=4): {PERM, SAFETY, SURV, BOOK} S7S7 (|I|=4): {PERM, SAFETY, SURV, DES} S8S8 (|I|=4): {PERM, SAFETY, BOOK, ACCESS} S9S9 (|I|=5): {PERM, SAFETY, SURV, BOOK, DES} S10S10 (|I|=5): {PERM, SAFETY, SURV, BOOK, ACCESS} S11S11 (|I|=5): {PERM, SAFETY, SURV, DES, ORDER} S12S12 (|I|=6): {PERM, SAFETY, SURV, BOOK, DES, ACCESS} S13S13 (|I|=6): {PERM, SAFETY, SURV, BOOK, DES, ORDER} S14S14 (|I|=7): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER} S15S15 (|I|=8): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH} S16S16 (|I|=9): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE} S17S17 (|I|=10): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR} S18S18 (|I|=11): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND} S19S19 (|I|=12): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME} S20S20 (|I|=13): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME, ROOF} S21S21 (|I|=14): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME, ROOF, CLAD} S22S22 (|I|=15): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME, ROOF, CLAD, HAND}

Inspector

Tips: click a task (left) or a state (right). Task click shows F(task) (a state node) and G(task) (an earliest-enabling transition edge). Toggle “all morphisms” to reveal transitive closure arrows (can get visually dense).
Nothing selected.
Explainer: what are T, S, F, and G here?

T is a thin category built from an acyclic prerequisite relation (a poset): objects are tasks, and there is a unique morphism x→y iff x ≤ y (“x is a prerequisite of y”).

S is the thin category of down-closed completion states (aka ideals/downsets): objects are sets of completed tasks that respect prerequisites; morphisms are inclusions I⊆J.

These states record completed tasks under precedence. For the additional question of who can work at the same time, Same work, different piles retains crew bundles, durations and resource availability. A downset here is not a full resource-and-time project state.

F: T→S sends each task x to its principal ideal ↓x: the minimal completed-state that “entails x”.

G: T→Arr(S) sends each task to an arrow-object (a transition) in the arrow category: pre(x) → pre(x)∪{x}, where pre(x)=↓x\{x}.

This is why we don’t need a 2-functor to map “tasks as objects” to “tasks as transitions”: we keep it well-typed by targeting Arr(S).

Project data: tasks (E) and cover prerequisites

Task set E (objects of T):

  • PERM: Permissions & stakeholder sign-off — Landowner permission / access agreement; planning/HOA checks if needed.
  • SAFETY: Risk assessment + method statement (RAMS) — Working-at-height risk assessment, rescue plan, PPE plan, toolbox talk prep.
  • SURV: Site survey & geotech sanity-check — Measure location, slope, drainage; basic ground/rock check for anchors & footings.
  • DES: Design + bill of materials — Shed design sized for site; choose foundation/anchoring scheme; produce BOM and cut list.
  • BOOK: Book/hire access & lifting setup — Line up scaffold/rope-access contractor, edge protection, hauling/lifting kit.
  • ORDER: Order building materials + anchors — Order timber, fixings, roofing, cladding, anchors; arrange deliveries.
  • ACCESS: Mobilise and set up safe access — Set up scaffold/rope access, edge protection, exclusion zone, material handling plan.
  • ANCH: Install & proof-test anchors/lifelines — Install temporary/permanent anchors for fall protection and for tying-in structure.
  • STAGE: Haul and stage materials on site — Transport materials to the cliff location (hand-carry/rope haul) and stage safely.
  • TERR: Prepare terrace + erosion control — Cut/level bench; install drainage/erosion control and any retaining elements.
  • FOUND: Install foundations/footings — Install piers/footings/ground screws; set posts or base; allow cure time if needed.
  • FRAME: Frame the shed & tie-in — Build floor/walls; fix to foundations; tie structure to anchors as designed.
  • ROOF: Roof & waterproofing — Roof framing, sheathing, membrane, flashing so the structure is weather-tight.
  • CLAD: Cladding + doors/windows — External cladding, door, any glazing/vents; weather-seal details.
  • HAND: Final inspection & handover — Snagging, safety check, clean-up, documentation/photos, handover to owner.

Cover relations (Hasse edges; the transitive closure gives all morphisms in T):

  • PERM ≤ SURV (precedes)
  • SAFETY ≤ SURV (precedes)
  • SURV ≤ DES (precedes)
  • PERM ≤ BOOK (precedes)
  • SAFETY ≤ BOOK (precedes)
  • DES ≤ ORDER (precedes)
  • BOOK ≤ ACCESS (precedes)
  • PERM ≤ ACCESS (precedes)
  • SAFETY ≤ ACCESS (precedes)
  • DES ≤ ANCH (precedes)
  • ACCESS ≤ ANCH (precedes)
  • ORDER ≤ ANCH (precedes)
  • ORDER ≤ STAGE (precedes)
  • ACCESS ≤ STAGE (precedes)
  • ANCH ≤ STAGE (precedes)
  • DES ≤ TERR (precedes)
  • STAGE ≤ TERR (precedes)
  • DES ≤ FOUND (precedes)
  • TERR ≤ FOUND (precedes)
  • STAGE ≤ FOUND (precedes)
  • FOUND ≤ FRAME (precedes)
  • FRAME ≤ ROOF (precedes)
  • ROOF ≤ CLAD (precedes)
  • CLAD ≤ HAND (precedes)
Project data: all states (objects of S)

Each state is a down-closed set of completed tasks. There are 23 states for this dependency structure.

  • S0 (|I|=0): {}
  • S1 (|I|=1): {PERM}
  • S2 (|I|=1): {SAFETY}
  • S3 (|I|=2): {PERM, SAFETY}
  • S4 (|I|=3): {PERM, SAFETY, SURV}
  • S5 (|I|=3): {PERM, SAFETY, BOOK}
  • S6 (|I|=4): {PERM, SAFETY, SURV, BOOK}
  • S7 (|I|=4): {PERM, SAFETY, SURV, DES}
  • S8 (|I|=4): {PERM, SAFETY, BOOK, ACCESS}
  • S9 (|I|=5): {PERM, SAFETY, SURV, BOOK, DES}
  • S10 (|I|=5): {PERM, SAFETY, SURV, BOOK, ACCESS}
  • S11 (|I|=5): {PERM, SAFETY, SURV, DES, ORDER}
  • S12 (|I|=6): {PERM, SAFETY, SURV, BOOK, DES, ACCESS}
  • S13 (|I|=6): {PERM, SAFETY, SURV, BOOK, DES, ORDER}
  • S14 (|I|=7): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER}
  • S15 (|I|=8): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH}
  • S16 (|I|=9): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE}
  • S17 (|I|=10): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR}
  • S18 (|I|=11): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND}
  • S19 (|I|=12): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME}
  • S20 (|I|=13): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME, ROOF}
  • S21 (|I|=14): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME, ROOF, CLAD}
  • S22 (|I|=15): {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME, ROOF, CLAD, HAND}
Functor tables: F and G on this scenario

F maps each task to its principal-ideal state:

  • F(PERM) = S1 = ↓PERM = {PERM}
  • F(SAFETY) = S2 = ↓SAFETY = {SAFETY}
  • F(SURV) = S4 = ↓SURV = {PERM, SAFETY, SURV}
  • F(DES) = S7 = ↓DES = {PERM, SAFETY, SURV, DES}
  • F(BOOK) = S5 = ↓BOOK = {PERM, SAFETY, BOOK}
  • F(ORDER) = S11 = ↓ORDER = {PERM, SAFETY, SURV, DES, ORDER}
  • F(ACCESS) = S8 = ↓ACCESS = {PERM, SAFETY, BOOK, ACCESS}
  • F(ANCH) = S15 = ↓ANCH = {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH}
  • F(STAGE) = S16 = ↓STAGE = {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE}
  • F(TERR) = S17 = ↓TERR = {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR}
  • F(FOUND) = S18 = ↓FOUND = {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND}
  • F(FRAME) = S19 = ↓FRAME = {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME}
  • F(ROOF) = S20 = ↓ROOF = {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME, ROOF}
  • F(CLAD) = S21 = ↓CLAD = {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME, ROOF, CLAD}
  • F(HAND) = S22 = ↓HAND = {PERM, SAFETY, SURV, BOOK, DES, ACCESS, ORDER, ANCH, STAGE, TERR, FOUND, FRAME, ROOF, CLAD, HAND}

G maps each task to its canonical “add-that-task-when-just-enabled” transition (as an object in Arr(S)):

  • G(PERM): S0 → S1 (adds PERM)
  • G(SAFETY): S0 → S2 (adds SAFETY)
  • G(SURV): S3 → S4 (adds SURV)
  • G(DES): S4 → S7 (adds DES)
  • G(BOOK): S3 → S5 (adds BOOK)
  • G(ORDER): S7 → S11 (adds ORDER)
  • G(ACCESS): S5 → S8 (adds ACCESS)
  • G(ANCH): S14 → S15 (adds ANCH)
  • G(STAGE): S15 → S16 (adds STAGE)
  • G(TERR): S16 → S17 (adds TERR)
  • G(FOUND): S17 → S18 (adds FOUND)
  • G(FRAME): S18 → S19 (adds FRAME)
  • G(ROOF): S19 → S20 (adds ROOF)
  • G(CLAD): S20 → S21 (adds CLAD)
  • G(HAND): S21 → S22 (adds HAND)