  "cutoff": "2026-11-21",
  "triples": 95,
  "methods": {
    "literal": [
      "EJ-04",
      "HC-06"
    ],
    "mapped": [
      "AQ-08",
      "AQ-17",
      "EJ-04",
      "FV-09",
      "FV-12",
      "HC-06"
    ],
    "agenda": [
      "AQ-17",
      "FV-09"
    ]
  },
  "records": [
    {
      "id": "AQ-08",
      "lesson": "Supply a single cabinet photograph for the platform pair",
      "term": "PIDS",
      "meanings": [
        "passenger information display"
      ],
      "setting": "permanent platform installation",
      "source": "Alder Quay · early handover minute AQ-HO-08",
      "date": "2025-02-04",
      "extract": "The early review accepted one cabinet photograph for the pair. The controlled index later marked this entry superseded by AQ-17.",
      "standing": "accepted",
      "replacement": "AQ-17",
      "literal": false,
      "mapped": true,
      "decision": "superseded",
      "heading": "Use the later record",
      "reason": "The controlled index points to AQ-17 as the replacement for this entry."
    },
    {
      "id": "AQ-17",
      "lesson": "File one evidence image against each installed display ID",
      "term": "PIDS",
      "meanings": [
        "passenger information display"
      ],
      "setting": "permanent platform installation",
      "source": "Alder Quay · handover acceptance minute AQ-HO-17",
      "date": "2025-04-16",
      "extract": "The reviewer could not match a single cabinet photograph to both platform displays. The resubmission indexed a separate destination-change image under each installed asset ID. The reviewer accepted the revised pack.",
      "standing": "accepted",
      "replacement": null,
      "literal": false,
      "mapped": true,
      "decision": "agenda",
      "heading": "Put on the agenda",
      "reason": "The recorded term identifies the display, the setting matches, and the current record has accepted evidence."
    },
    {
      "id": "EJ-04",
      "lesson": "Index the portable display pack by event shift",
      "term": "passenger information display",
      "meanings": [
        "passenger information display"
      ],
      "setting": "temporary concourse installation",
      "source": "East Junction · temporary event closeout EJ-EV-04",
      "date": "2025-08-18",
      "extract": "The hired concourse units moved between shifts. An index by event and shift let the team trace each unit through the temporary deployment.",
      "standing": "accepted",
      "replacement": null,
      "literal": true,
      "mapped": true,
      "decision": "context",
      "heading": "Different setting",
      "reason": "The source concerns a temporary concourse installation. Merebridge is a permanent platform installation."
    },
    {
      "id": "FV-09",
      "lesson": "Reconcile the supplier and station identifiers in the index",
      "term": "customer information screen",
      "meanings": [
        "passenger information display"
      ],
      "setting": "permanent platform installation",
      "source": "Fen Vale · closeout record FV-CR-09",
      "date": "2025-06-03",
      "extract": "Two evidence entries were filed under the supplier serial number alone. The station librarian accepted the revised index after it listed the station asset identifier beside each serial number.",
      "standing": "accepted",
      "replacement": null,
      "literal": false,
      "mapped": true,
      "decision": "agenda",
      "heading": "Put on the agenda",
      "reason": "The recorded term identifies the display, the setting matches, and the current record has accepted evidence."
    },
    {
      "id": "FV-12",
      "lesson": "Resolve what the asset register meant by ‘screen’",
      "term": "screen",
      "meanings": [
        "passenger information display",
        "privacy screen"
      ],
      "setting": "permanent platform installation",
      "source": "Fen Vale · asset register exception FV-AR-12",
      "date": "2025-06-11",
      "extract": "The entry says only ‘screen at platform end’. No asset tag, photograph or system identifier accompanies it. The register includes both passenger displays and privacy partitions.",
      "standing": "accepted",
      "replacement": null,
      "literal": false,
      "mapped": true,
      "decision": "clarify",
      "heading": "Clarify the asset",
      "reason": "The recorded term has more than one possible meaning. Obtain an asset ID before transferring the lesson."
    },
    {
      "id": "HC-06",
      "lesson": "Check whether daylight photographs were requested",
      "term": "passenger information display",
      "meanings": [
        "passenger information display"
      ],
      "setting": "permanent platform installation",
      "source": "Harbour Cross · unsigned issue note HC-IN-06",
      "date": "2025-09-10",
      "extract": "A participant recalled a request for daylight photographs. The issue log has no decision reference or acceptance minute to support the recollection.",
      "standing": "unconfirmed",
      "replacement": null,
      "literal": true,
      "mapped": true,
      "decision": "verify",
      "heading": "Find corroboration",
      "reason": "The report matches the asset and setting. An acceptance minute or corroborating source is still needed."
    },
    {
      "id": "WB-03",
      "lesson": "Record the panel finish in the handover schedule",
      "term": "privacy screen",
      "meanings": [
        "privacy screen"
      ],
      "setting": "permanent platform installation",
      "source": "West Bank · finishes record WB-FN-03",
      "date": "2025-03-22",
      "extract": "The joinery handover schedule records the finish of the opaque partition. The finishes reviewer accepted the corrected entry.",
      "standing": "accepted",
      "replacement": null,
      "literal": false,
      "mapped": false,
      "decision": "asset",
      "heading": "Different asset",
      "reason": "The record identifies a privacy screen. Merebridge needs a passenger information display."
    }
  ]
}