Foray 285 — Testing an open-source project analytics platform

Can an open-source PDA platform make project-delivery analysis more useful and dependable than a straightforward table or calculation?

PW-285 · FORAY-285-PDA-PLATFORM · Established 7 November 2026.

The first essai applies antnewman/pda-platform to the existing fictional Winter Fleet case. This is a separate enquiry from Foray 450, which created and used the case to explore organisational change. No change to that enquiry or its retained results is implied.

Ends

Establish which delivery jobs PDA can perform accurately, which it makes easier, and where its data model or implementation prevents a useful answer. The desired result is a practical basis for adopting selected capabilities, improving a bounded integration, or declining to use the platform. Tool counts, attractive reports and technical execution alone do not establish that end.

The wider enquiry includes reliable arithmetic, preservation of project meaning, visible unknowns, correction and repeat use, and the amount of preparation needed. Practical benefit and human time savings require a later observed user trial; this essai does not invent those measurements.

Ways

  1. Start with an existing management problem and frozen source data. State the questions and comparison before the PDA run.
  2. Pin the open-source version and use its real MCP interface locally. Preserve native failures. Any diagnostic adapter must be identified and must not repair the analytical answer invisibly.
  3. Translate only source-supported facts. Record what the translation preserves, loses and leaves unsupported.
  4. Compare returned results with transparent reference calculations and existing case checks. Credit calculations to the component that actually made them.
  5. Introduce an existing case change; inspect whether the changed answer remains faithful. Check save, retrieve, correction and restart where the chosen MCP tools support them.
  6. Leave a readable worked result, exact calls, source hashes and reproduction instructions. The broader foray stays open beyond one case.

Means

Essai 01

Prospective protocol · Mapping contract

The first question is whether the existing commitments and an offered expansion fit the available boats, qualified crews and cash. Detailed results will name native outputs, diagnostic outputs, ordinary calculations and unavailable capabilities separately.