This page presents the recorded trial. The PDA MCP server ran locally; this public report does not run it. The original dated record follows.

Mapping Winter Fleet to PDA

The source register remains authoritative. Generated mappings are disposable analytical inputs.

Source meaning PDA representation attempted Boundary
One commitment with a fixed weekly service window Project task / structured scenario row A week is not a witnessed daily start/finish. Do not claim a critical path from a constructed daily order.
Vessel and person demand by week Resource-plan rows Planned days are source quantities; actual days remain absent. Availability is relative to a declared five-day capacity basis, not a measured productivity rate.
Qualification and allowed vessel constraints Source companion / reference checks Do not assume free-text notes cause native enforcement.
Opening cash, receipts, vessel costs, overhead and minimum cash Reference cash ledger; native financial tools inspected for coverage Budget, spend and estimate-at-completion are different quantities. Opening cash is not a cost budget; receipts are not negative costs.
Published W05 capacity reduction Numeric assumption baseline and later source-bound observation This tests drift retention, not whether PDA discovered the reduction. The baseline is an explicitly identified planning assumption.
Additional offered work Proposed change records and separate candidate scenarios No automatic approval, invented risk rating or retainer income. Cost impact is calculated outside PDA and attributed to the mapper.
Case-defined original obligations and nonfinancial promises Preserved source IDs and explicit reference checks Register presence alone does not prove continuing service obligations or legitimate authority.

If a platform interface cannot express a material source concept, the result is unavailable or a disclosed projection. No empty register will be described as evidence that the fleet is healthy.