Keeping construction methods open · Essai 3 · 18 November 2026
Can we recover before we know?
A route exists in every possible world. That does not yet give the team a recovery policy it can execute with the information it has.
The half-built bridge
The bridge between two peaks is partly built. Either the crane has become unavailable or the cable corridor has closed. Exactly one route remains; the team does not yet know which. A retained conversion interface makes the cable route possible. The access window is closing.
All times below are invented planning ticks. A route attempt includes a safe preflight: an unavailable lift is refused after one tick, and an unavailable cable route after two ticks, without irreversible work. A successful lift finishes in two ticks; cable work takes the selected total. Attempts cannot be interrupted. The routine status and direct check are exact and describe a disruption that remains fixed.
Change the recovery conditions
Controls recalculate immediately. This is an ephemeral calculation: nothing is saved, transmitted, or changed on a real project. Reload restores defaults.
Best common policy
All first choices
| First choice | Latest branch finish | Guaranteed by closure? |
|---|
What moved forward
Essai 2 proved reachability in a fully observed state graph. This essai distinguishes for every world, some route from one policy, working in every world. The policy can branch only after a receipt or preflight result. At the opening settings, both worlds have a route finishing by tick 3, but every admissible policy has a branch finishing at tick 4 or later. Retained hardware alone is insufficient.
Try closing at tick 4, receiving status at tick 0, or reducing cable completion to two ticks through work already completed before this decision. Each can restore a guarantee. Removing the conversion interface cannot be repaired by faster reporting. These are different interventions on time, information and physical state.
The exact boundary
With the interface retained, the earliest guaranteed finish is the minimum of: routine receipt plus the slower route; direct-check time plus the slower route; lift-first’s worst branch; and cable-first’s worst branch. The solver exposes a witness policy and every branch. This is finite-horizon robust reachability under the declared uncertainty, not an infinite-horizon viability theorem.
Derivation, assumptions, sources and verification · Executable model