Compare three authored task sequences, marking tables and WBS hierarchies against a mountain-shed Petri-net diagram. The tabs select fixed examples; this page does not generate or replay-check their histories.
This Petri net is deliberately “elementary”: it encodes *physical* precedence and key design choices (foundation type, wall method, interior scope), leaving durations/resources as a second layer. In Petri-net terms, a schedule option is a firing sequence from the initial marking to a completed marking; reachability is exactly “can we get from one marking to another by firing tasks?”. See Open Petri Nets.
Background: Petri nets can be treated compositionally and are closely tied to (strict) symmetric/commutative monoidal categories; places/transitions present generators and morphisms, and reachability is about morphisms between markings. See Baez and Master, Open Petri Nets.
For generated histories with token-supply and ordering checks, try the later marking-to-plan lab. Its model and checks are separate from these three authored examples.
Click a schedule option to (a) highlight the chosen branches in the Petri net, (b) see the firing sequence and markings, and (c) see the corresponding authored elementary WBS path. The three options differ by foundation type, wall method, and/or interior scope + ordering.
| Step | Firing event (transition = task) | Resulting marking (tokens = state) |
|---|---|---|
| 0 | Initial marking M0 | Start |
| 1 | Fire tA_design: Design & scope | Design complete → permit package ready Design complete → procurement package ready |
| 2 | Fire tB_permit: Permits/approvals | Design complete → procurement package ready Permits/approvals complete |
| 3 | Fire tC_procure: Procure & logistics | Permits/approvals complete Materials/logistics ready to mobilize Prefabrication option token |
| 4 | Fire tH0_skip_panels: Skip prefab option | Permits/approvals complete Materials/logistics ready to mobilize |
| 5 | Fire tD_mobilize: Mobilize to site | Permits/approvals complete Crew/tools/materials mobilized to mountain site |
| 6 | Fire tE_siteprep: Site prep & layout | Site prepped & layout staked |
| 7 | Fire tF1_concrete: Foundation: concrete piers | Foundation complete |
| 8 | Fire tG_floor: Build floor system | Floor system/deck complete |
| 9 | Fire tH1_stick_frame: Frame walls (stick-built) | Walls erected & braced |
| 10 | Fire tI_roof: Frame & install roof (dry-in) | Roof dried-in (weather-tight roof) |
| 11 | Fire tJ1_shell: Wrap shell & temp close | Shell weatherproof → interior can start Shell weatherproof → exterior finish can start |
| 12 | Fire tJ2_exterior: Final exterior (windows/doors/siding) | Shell weatherproof → interior can start Exterior complete (windows/doors/siding) |
| 13 | Fire tK1_interior_std: Interior fit-out (standard) | Exterior complete (windows/doors/siding) Interior fit-out complete |
| 14 | Fire tJoin_ready: Integrate & ready for closeout | Ready for closeout/inspection |
| 15 | Fire tM_close: Final inspection & cleanup | Project complete |
| Step | Firing event (transition = task) | Resulting marking (tokens = state) |
|---|---|---|
| 0 | Initial marking M0 | Start |
| 1 | Fire tA_design: Design & scope | Design complete → permit package ready Design complete → procurement package ready |
| 2 | Fire tC_procure: Procure & logistics | Design complete → permit package ready Materials/logistics ready to mobilize Prefabrication option token |
| 3 | Fire tH0_panel_fab: Offsite fab wall panels | Design complete → permit package ready Materials/logistics ready to mobilize Prefab wall panels fabricated |
| 4 | Fire tB_permit: Permits/approvals | Materials/logistics ready to mobilize Prefab wall panels fabricated Permits/approvals complete |
| 5 | Fire tD_mobilize: Mobilize to site | Prefab wall panels fabricated Permits/approvals complete Crew/tools/materials mobilized to mountain site |
| 6 | Fire tE_siteprep: Site prep & layout | Prefab wall panels fabricated Site prepped & layout staked |
| 7 | Fire tF2_skid: Foundation: skid/gravel | Prefab wall panels fabricated Foundation complete |
| 8 | Fire tG_floor: Build floor system | Prefab wall panels fabricated Floor system/deck complete |
| 9 | Fire tH2_install_panels: Install prefab wall panels | Walls erected & braced |
| 10 | Fire tI_roof: Frame & install roof (dry-in) | Roof dried-in (weather-tight roof) |
| 11 | Fire tJ1_shell: Wrap shell & temp close | Shell weatherproof → interior can start Shell weatherproof → exterior finish can start |
| 12 | Fire tK1_interior_std: Interior fit-out (standard) | Shell weatherproof → exterior finish can start Interior fit-out complete |
| 13 | Fire tJ2_exterior: Final exterior (windows/doors/siding) | Interior fit-out complete Exterior complete (windows/doors/siding) |
| 14 | Fire tJoin_ready: Integrate & ready for closeout | Ready for closeout/inspection |
| 15 | Fire tM_close: Final inspection & cleanup | Project complete |
| Step | Firing event (transition = task) | Resulting marking (tokens = state) |
|---|---|---|
| 0 | Initial marking M0 | Start |
| 1 | Fire tA_design: Design & scope | Design complete → permit package ready Design complete → procurement package ready |
| 2 | Fire tB_permit: Permits/approvals | Design complete → procurement package ready Permits/approvals complete |
| 3 | Fire tC_procure: Procure & logistics | Permits/approvals complete Materials/logistics ready to mobilize Prefabrication option token |
| 4 | Fire tH0_skip_panels: Skip prefab option | Permits/approvals complete Materials/logistics ready to mobilize |
| 5 | Fire tD_mobilize: Mobilize to site | Permits/approvals complete Crew/tools/materials mobilized to mountain site |
| 6 | Fire tE_siteprep: Site prep & layout | Site prepped & layout staked |
| 7 | Fire tF3_helical: Foundation: helical piers | Foundation complete |
| 8 | Fire tG_floor: Build floor system | Floor system/deck complete |
| 9 | Fire tH1_stick_frame: Frame walls (stick-built) | Walls erected & braced |
| 10 | Fire tI_roof: Frame & install roof (dry-in) | Roof dried-in (weather-tight roof) |
| 11 | Fire tJ1_shell: Wrap shell & temp close | Shell weatherproof → interior can start Shell weatherproof → exterior finish can start |
| 12 | Fire tK2_interior_min: Interior fit-out (minimal) | Shell weatherproof → exterior finish can start Interior fit-out complete |
| 13 | Fire tJ2_exterior: Final exterior (windows/doors/siding) | Interior fit-out complete Exterior complete (windows/doors/siding) |
| 14 | Fire tJoin_ready: Integrate & ready for closeout | Ready for closeout/inspection |
| 15 | Fire tM_close: Final inspection & cleanup | Project complete |
Note: The Petri net defines the allowed task orderings (what can happen when). Start times/durations/resources can be added as a separate “timing” layer—e.g., PERT-style constraints. See Project Scheduling and Copresheaves.
Your project rationale is that a Petri net can be treated as a generative specification for (a strict/commutative) symmetric monoidal category, and that schedule/WBS variants come from different reachable markings and firing sequences.
For executable compositional tooling, see AlgebraicJulia’s graph-rewriting and wiring-diagram example. Functorial Data Migration describes mappings of data between schemas; applying it to plans would require an explicit schema mapping.
Related open-system ideas appear in Compositional Modeling with Stock and Flow Diagrams, a possible direction for adding resource and consumption dynamics.