  "activity_names": {
    "A": "Common service isolation/renewal",
    "B": "North preparation",
    "C": "South preparation",
    "D": "East preparation",
    "E": "North specialist fit-out",
    "F": "South specialist fit-out",
    "G": "East specialist fit-out",
    "H": "North objects/cases",
    "I": "South objects/cases",
    "J": "East objects/cases",
    "K": "AV/control configuration",
    "L": "Climate commissioning",
    "M": "Integrated case/alarm tests",
    "N": "Interpretation/signage",
    "O": "Accessibility/visitor-route walkthrough",
    "P": "Full integrated operating run",
    "Q": "External acceptance",
    "R": "Staff rehearsal"
  },
  "predecessors": {
    "A": [],
    "B": [
      "A"
    ],
    "C": [
      "A"
    ],
    "D": [
      "A"
    ],
    "E": [
      "B"
    ],
    "F": [
      "C"
    ],
    "G": [
      "D"
    ],
    "H": [
      "E"
    ],
    "I": [
      "F"
    ],
    "J": [
      "G"
    ],
    "K": [
      "E",
      "F"
    ],
    "L": [
      "G"
    ],
    "M": [
      "H",
      "I",
      "J",
      "K",
      "L"
    ],
    "N": [
      "E",
      "F"
    ],
    "O": [
      "N",
      "H",
      "I",
      "J"
    ],
    "P": [
      "M",
      "O"
    ],
    "Q": [
      "P"
    ],
    "R": [
      "Q"
    ]
  },
  "base_durations": {
    "A": 3,
    "B": 4,
    "C": 3,
    "D": 5,
    "E": 4,
    "F": 3,
    "G": 4,
    "H": 3,
    "I": 2,
    "J": 4,
    "K": 3,
    "L": 2,
    "M": 2,
    "N": 3,
    "O": 1,
    "P": 2,
    "Q": 2,
    "R": 1
  },
  "offers": {
    "X": 7,
    "S": 18,
    "C": 12,
    "T": 6,
    "V": 4
  },
  "options": [
    {
      "codes": "",
      "cost": 0,
      "orders_examined": 72,
      "feasible_orders": 72,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 7,
          "G": 14,
          "H": 11,
          "F": 18,
          "J": 18,
          "L": 19,
          "I": 22,
          "K": 21,
          "N": 21,
          "M": 25,
          "O": 24,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 11,
          "G": 18,
          "H": 14,
          "F": 21,
          "J": 22,
          "L": 21,
          "I": 24,
          "K": 24,
          "N": 24,
          "M": 27,
          "O": 25,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "E",
            "G",
            "F"
          ],
          [
            "H",
            "J",
            "I"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 14
    },
    {
      "codes": "V",
      "cost": 4,
      "orders_examined": 72,
      "feasible_orders": 72,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 7,
          "G": 14,
          "H": 11,
          "F": 18,
          "J": 18,
          "L": 19,
          "I": 22,
          "K": 21,
          "N": 21,
          "M": 25,
          "O": 24,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 11,
          "G": 18,
          "H": 14,
          "F": 21,
          "J": 22,
          "L": 21,
          "I": 24,
          "K": 23,
          "N": 24,
          "M": 27,
          "O": 25,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "E",
            "G",
            "F"
          ],
          [
            "H",
            "J",
            "I"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 18
    },
    {
      "codes": "T",
      "cost": 6,
      "orders_examined": 72,
      "feasible_orders": 72,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 7,
          "G": 14,
          "H": 11,
          "F": 18,
          "J": 18,
          "L": 18,
          "I": 22,
          "K": 21,
          "N": 21,
          "M": 25,
          "O": 24,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 11,
          "G": 18,
          "H": 14,
          "F": 21,
          "J": 22,
          "L": 20,
          "I": 24,
          "K": 24,
          "N": 24,
          "M": 27,
          "O": 25,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "E",
            "G",
            "F"
          ],
          [
            "H",
            "J",
            "I"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 20
    },
    {
      "codes": "TV",
      "cost": 10,
      "orders_examined": 72,
      "feasible_orders": 72,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 7,
          "G": 14,
          "H": 11,
          "F": 18,
          "J": 18,
          "L": 18,
          "I": 22,
          "K": 21,
          "N": 21,
          "M": 25,
          "O": 24,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 11,
          "G": 18,
          "H": 14,
          "F": 21,
          "J": 22,
          "L": 20,
          "I": 24,
          "K": 23,
          "N": 24,
          "M": 27,
          "O": 25,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "E",
            "G",
            "F"
          ],
          [
            "H",
            "J",
            "I"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 24
    },
    {
      "codes": "C",
      "cost": 12,
      "orders_examined": 288,
      "feasible_orders": 134,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "G": 8,
          "F": 14,
          "J": 14,
          "L": 12,
          "E": 17,
          "I": 17,
          "H": 21,
          "K": 21,
          "N": 21,
          "M": 25,
          "O": 24,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "G": 12,
          "F": 17,
          "J": 18,
          "L": 14,
          "E": 21,
          "I": 19,
          "H": 24,
          "K": 24,
          "N": 24,
          "M": 27,
          "O": 25,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "G",
            "F",
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 26
    },
    {
      "codes": "CV",
      "cost": 16,
      "orders_examined": 288,
      "feasible_orders": 134,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "G": 8,
          "F": 14,
          "J": 14,
          "L": 12,
          "E": 17,
          "I": 17,
          "H": 21,
          "K": 21,
          "N": 21,
          "M": 25,
          "O": 24,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "G": 12,
          "F": 17,
          "J": 18,
          "L": 14,
          "E": 21,
          "I": 19,
          "H": 24,
          "K": 23,
          "N": 24,
          "M": 27,
          "O": 25,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "G",
            "F",
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 30
    },
    {
      "codes": "CT",
      "cost": 18,
      "orders_examined": 288,
      "feasible_orders": 134,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "G": 8,
          "F": 14,
          "J": 14,
          "L": 12,
          "E": 17,
          "I": 17,
          "H": 21,
          "K": 21,
          "N": 21,
          "M": 25,
          "O": 24,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "G": 12,
          "F": 17,
          "J": 18,
          "L": 14,
          "E": 21,
          "I": 19,
          "H": 24,
          "K": 24,
          "N": 24,
          "M": 27,
          "O": 25,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "G",
            "F",
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 32
    },
    {
      "codes": "CTV",
      "cost": 22,
      "orders_examined": 288,
      "feasible_orders": 134,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "G": 8,
          "F": 14,
          "J": 14,
          "L": 12,
          "E": 17,
          "I": 17,
          "H": 21,
          "K": 21,
          "N": 21,
          "M": 25,
          "O": 24,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "G": 12,
          "F": 17,
          "J": 18,
          "L": 14,
          "E": 21,
          "I": 19,
          "H": 24,
          "K": 23,
          "N": 24,
          "M": 27,
          "O": 25,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "G",
            "F",
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 36
    },
    {
      "codes": "S",
      "cost": 18,
      "orders_examined": 288,
      "feasible_orders": 216,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 8,
          "F": 6,
          "G": 12,
          "I": 9,
          "K": 12,
          "N": 12,
          "H": 12,
          "L": 19,
          "J": 16,
          "M": 21,
          "O": 20,
          "P": 25,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 12,
          "F": 9,
          "G": 16,
          "I": 11,
          "K": 15,
          "N": 15,
          "H": 15,
          "L": 21,
          "J": 20,
          "M": 23,
          "O": 21,
          "P": 27,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F"
          ],
          [
            "E",
            "G"
          ],
          [
            "I",
            "H",
            "J"
          ],
          [
            "K",
            "L"
          ]
        ],
        "P_finish": 27,
        "Q_start": 27,
        "opening": 30,
        "margin": 0
      },
      "holding_cost": 0,
      "total_cost": 18
    },
    {
      "codes": "SV",
      "cost": 22,
      "orders_examined": 288,
      "feasible_orders": 216,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 8,
          "F": 6,
          "G": 12,
          "I": 9,
          "K": 12,
          "N": 12,
          "H": 12,
          "L": 19,
          "J": 16,
          "M": 21,
          "O": 20,
          "P": 25,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 12,
          "F": 9,
          "G": 16,
          "I": 11,
          "K": 14,
          "N": 15,
          "H": 15,
          "L": 21,
          "J": 20,
          "M": 23,
          "O": 21,
          "P": 27,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F"
          ],
          [
            "E",
            "G"
          ],
          [
            "I",
            "H",
            "J"
          ],
          [
            "K",
            "L"
          ]
        ],
        "P_finish": 27,
        "Q_start": 27,
        "opening": 30,
        "margin": 0
      },
      "holding_cost": 0,
      "total_cost": 22
    },
    {
      "codes": "ST",
      "cost": 24,
      "orders_examined": 288,
      "feasible_orders": 216,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 8,
          "F": 6,
          "G": 12,
          "I": 9,
          "K": 12,
          "N": 12,
          "H": 12,
          "L": 16,
          "J": 16,
          "M": 20,
          "O": 20,
          "P": 22,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 12,
          "F": 9,
          "G": 16,
          "I": 11,
          "K": 15,
          "N": 15,
          "H": 15,
          "L": 18,
          "J": 20,
          "M": 22,
          "O": 21,
          "P": 24,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F"
          ],
          [
            "E",
            "G"
          ],
          [
            "I",
            "H",
            "J"
          ],
          [
            "K",
            "L"
          ]
        ],
        "P_finish": 24,
        "Q_start": 27,
        "opening": 30,
        "margin": 3
      },
      "holding_cost": 0,
      "total_cost": 24
    },
    {
      "codes": "STV",
      "cost": 28,
      "orders_examined": 288,
      "feasible_orders": 216,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 8,
          "F": 6,
          "G": 12,
          "I": 9,
          "K": 12,
          "N": 12,
          "H": 12,
          "L": 16,
          "J": 16,
          "M": 20,
          "O": 20,
          "P": 22,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 12,
          "F": 9,
          "G": 16,
          "I": 11,
          "K": 14,
          "N": 15,
          "H": 15,
          "L": 18,
          "J": 20,
          "M": 22,
          "O": 21,
          "P": 24,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F"
          ],
          [
            "E",
            "G"
          ],
          [
            "I",
            "H",
            "J"
          ],
          [
            "K",
            "L"
          ]
        ],
        "P_finish": 24,
        "Q_start": 27,
        "opening": 30,
        "margin": 3
      },
      "holding_cost": 0,
      "total_cost": 28
    },
    {
      "codes": "SC",
      "cost": 30,
      "orders_examined": 1152,
      "feasible_orders": 542,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 7,
          "F": 8,
          "G": 11,
          "H": 11,
          "K": 11,
          "N": 11,
          "I": 16,
          "J": 15,
          "L": 15,
          "M": 19,
          "O": 19,
          "P": 21,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 11,
          "F": 11,
          "G": 15,
          "H": 14,
          "K": 14,
          "N": 14,
          "I": 18,
          "J": 19,
          "L": 17,
          "M": 21,
          "O": 20,
          "P": 23,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S1"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "E"
          ],
          [
            "F",
            "G"
          ],
          [
            "H",
            "I"
          ],
          [
            "J"
          ],
          [
            "K",
            "L"
          ]
        ],
        "P_finish": 23,
        "Q_start": 27,
        "opening": 30,
        "margin": 4
      },
      "holding_cost": 0,
      "total_cost": 30
    },
    {
      "codes": "SCV",
      "cost": 34,
      "orders_examined": 1152,
      "feasible_orders": 542,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 7,
          "F": 8,
          "G": 11,
          "H": 11,
          "K": 11,
          "N": 11,
          "I": 16,
          "J": 15,
          "L": 15,
          "M": 19,
          "O": 19,
          "P": 21,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 11,
          "F": 11,
          "G": 15,
          "H": 14,
          "K": 13,
          "N": 14,
          "I": 18,
          "J": 19,
          "L": 17,
          "M": 21,
          "O": 20,
          "P": 23,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S1"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "E"
          ],
          [
            "F",
            "G"
          ],
          [
            "H",
            "I"
          ],
          [
            "J"
          ],
          [
            "K",
            "L"
          ]
        ],
        "P_finish": 23,
        "Q_start": 27,
        "opening": 30,
        "margin": 4
      },
      "holding_cost": 0,
      "total_cost": 34
    },
    {
      "codes": "SCT",
      "cost": 36,
      "orders_examined": 1152,
      "feasible_orders": 542,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 7,
          "G": 8,
          "F": 12,
          "H": 11,
          "J": 14,
          "L": 12,
          "I": 16,
          "K": 15,
          "N": 15,
          "M": 18,
          "O": 18,
          "P": 20,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 11,
          "G": 12,
          "F": 15,
          "H": 14,
          "J": 18,
          "L": 14,
          "I": 18,
          "K": 18,
          "N": 18,
          "M": 20,
          "O": 19,
          "P": 22,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S1"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "E"
          ],
          [
            "G",
            "F"
          ],
          [
            "H",
            "I"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 22,
        "Q_start": 27,
        "opening": 30,
        "margin": 5
      },
      "holding_cost": 0,
      "total_cost": 36
    },
    {
      "codes": "SCTV",
      "cost": 40,
      "orders_examined": 1152,
      "feasible_orders": 542,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 7,
          "G": 8,
          "F": 12,
          "H": 11,
          "J": 14,
          "L": 12,
          "I": 16,
          "K": 15,
          "N": 15,
          "M": 18,
          "O": 18,
          "P": 20,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 11,
          "G": 12,
          "F": 15,
          "H": 14,
          "J": 18,
          "L": 14,
          "I": 18,
          "K": 17,
          "N": 18,
          "M": 20,
          "O": 19,
          "P": 22,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S1"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 4,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "E"
          ],
          [
            "G",
            "F"
          ],
          [
            "H",
            "I"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 22,
        "Q_start": 27,
        "opening": 30,
        "margin": 5
      },
      "holding_cost": 0,
      "total_cost": 40
    },
    {
      "codes": "X",
      "cost": 7,
      "orders_examined": 72,
      "feasible_orders": 72,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 9,
          "I": 9,
          "E": 14,
          "J": 16,
          "L": 12,
          "H": 20,
          "K": 19,
          "N": 18,
          "M": 25,
          "O": 23,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 12,
          "I": 11,
          "E": 18,
          "J": 20,
          "L": 14,
          "H": 23,
          "K": 22,
          "N": 21,
          "M": 27,
          "O": 24,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G",
            "E"
          ],
          [
            "I",
            "J",
            "H"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 21
    },
    {
      "codes": "XV",
      "cost": 11,
      "orders_examined": 72,
      "feasible_orders": 72,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 9,
          "I": 9,
          "E": 14,
          "J": 16,
          "L": 12,
          "H": 20,
          "K": 19,
          "N": 18,
          "M": 25,
          "O": 23,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 12,
          "I": 11,
          "E": 18,
          "J": 20,
          "L": 14,
          "H": 23,
          "K": 21,
          "N": 21,
          "M": 27,
          "O": 24,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G",
            "E"
          ],
          [
            "I",
            "J",
            "H"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 25
    },
    {
      "codes": "XT",
      "cost": 13,
      "orders_examined": 72,
      "feasible_orders": 72,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 9,
          "I": 9,
          "E": 14,
          "J": 16,
          "L": 12,
          "H": 20,
          "K": 18,
          "N": 18,
          "M": 25,
          "O": 23,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 12,
          "I": 11,
          "E": 18,
          "J": 20,
          "L": 14,
          "H": 23,
          "K": 21,
          "N": 21,
          "M": 27,
          "O": 24,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G",
            "E"
          ],
          [
            "I",
            "J",
            "H"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 27
    },
    {
      "codes": "XTV",
      "cost": 17,
      "orders_examined": 72,
      "feasible_orders": 72,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 9,
          "I": 9,
          "E": 14,
          "J": 16,
          "L": 12,
          "H": 20,
          "K": 18,
          "N": 18,
          "M": 25,
          "O": 23,
          "P": 27,
          "Q": 34,
          "R": 36
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 12,
          "I": 11,
          "E": 18,
          "J": 20,
          "L": 14,
          "H": 23,
          "K": 20,
          "N": 21,
          "M": 27,
          "O": 24,
          "P": 29,
          "Q": 36,
          "R": 37
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G",
            "E"
          ],
          [
            "I",
            "J",
            "H"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 29,
        "Q_start": 34,
        "opening": 37,
        "margin": 5
      },
      "holding_cost": 14,
      "total_cost": 31
    },
    {
      "codes": "XC",
      "cost": 19,
      "orders_examined": 288,
      "feasible_orders": 150,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 9,
          "I": 9,
          "E": 14,
          "J": 14,
          "L": 12,
          "H": 18,
          "K": 19,
          "N": 18,
          "M": 22,
          "O": 21,
          "P": 25,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 12,
          "I": 11,
          "E": 18,
          "J": 18,
          "L": 14,
          "H": 21,
          "K": 22,
          "N": 21,
          "M": 24,
          "O": 22,
          "P": 27,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G",
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 27,
        "Q_start": 27,
        "opening": 30,
        "margin": 0
      },
      "holding_cost": 0,
      "total_cost": 19
    },
    {
      "codes": "XCV",
      "cost": 23,
      "orders_examined": 288,
      "feasible_orders": 150,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 9,
          "I": 9,
          "E": 14,
          "J": 14,
          "L": 12,
          "H": 18,
          "K": 19,
          "N": 18,
          "M": 21,
          "O": 21,
          "P": 25,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 12,
          "I": 11,
          "E": 18,
          "J": 18,
          "L": 14,
          "H": 21,
          "K": 21,
          "N": 21,
          "M": 23,
          "O": 22,
          "P": 27,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G",
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 27,
        "Q_start": 27,
        "opening": 30,
        "margin": 0
      },
      "holding_cost": 0,
      "total_cost": 23
    },
    {
      "codes": "XCT",
      "cost": 25,
      "orders_examined": 288,
      "feasible_orders": 150,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 9,
          "I": 9,
          "E": 14,
          "J": 14,
          "L": 12,
          "H": 18,
          "K": 18,
          "N": 18,
          "M": 21,
          "O": 21,
          "P": 25,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 12,
          "I": 11,
          "E": 18,
          "J": 18,
          "L": 14,
          "H": 21,
          "K": 21,
          "N": 21,
          "M": 23,
          "O": 22,
          "P": 27,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G",
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 27,
        "Q_start": 27,
        "opening": 30,
        "margin": 0
      },
      "holding_cost": 0,
      "total_cost": 25
    },
    {
      "codes": "XCTV",
      "cost": 29,
      "orders_examined": 288,
      "feasible_orders": 150,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 9,
          "I": 9,
          "E": 14,
          "J": 14,
          "L": 12,
          "H": 18,
          "K": 18,
          "N": 18,
          "M": 21,
          "O": 21,
          "P": 25,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 12,
          "I": 11,
          "E": 18,
          "J": 18,
          "L": 14,
          "H": 21,
          "K": 20,
          "N": 21,
          "M": 23,
          "O": 22,
          "P": 27,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S0"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G",
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 27,
        "Q_start": 27,
        "opening": 30,
        "margin": 0
      },
      "holding_cost": 0,
      "total_cost": 29
    },
    {
      "codes": "XS",
      "cost": 25,
      "orders_examined": 288,
      "feasible_orders": 216,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 8,
          "F": 6,
          "G": 9,
          "I": 9,
          "N": 12,
          "H": 12,
          "L": 12,
          "J": 16,
          "K": 14,
          "M": 20,
          "O": 20,
          "P": 22,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 12,
          "F": 9,
          "G": 12,
          "I": 11,
          "N": 15,
          "H": 15,
          "L": 14,
          "J": 20,
          "K": 17,
          "M": 22,
          "O": 21,
          "P": 24,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G"
          ],
          [
            "E"
          ],
          [
            "I",
            "H",
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 24,
        "Q_start": 27,
        "opening": 30,
        "margin": 3
      },
      "holding_cost": 0,
      "total_cost": 25
    },
    {
      "codes": "XSV",
      "cost": 29,
      "orders_examined": 288,
      "feasible_orders": 216,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 8,
          "E": 11,
          "I": 9,
          "L": 11,
          "J": 11,
          "K": 15,
          "N": 15,
          "H": 16,
          "M": 19,
          "O": 19,
          "P": 21,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 11,
          "E": 15,
          "I": 11,
          "L": 13,
          "J": 15,
          "K": 17,
          "N": 18,
          "H": 19,
          "M": 21,
          "O": 20,
          "P": 23,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F"
          ],
          [
            "G",
            "E"
          ],
          [
            "I",
            "J",
            "H"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 23,
        "Q_start": 27,
        "opening": 30,
        "margin": 4
      },
      "holding_cost": 0,
      "total_cost": 29
    },
    {
      "codes": "XST",
      "cost": 31,
      "orders_examined": 288,
      "feasible_orders": 216,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 8,
          "E": 11,
          "I": 9,
          "L": 11,
          "J": 11,
          "K": 15,
          "N": 15,
          "H": 16,
          "M": 19,
          "O": 19,
          "P": 21,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 11,
          "E": 15,
          "I": 11,
          "L": 13,
          "J": 15,
          "K": 18,
          "N": 18,
          "H": 19,
          "M": 21,
          "O": 20,
          "P": 23,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F"
          ],
          [
            "G",
            "E"
          ],
          [
            "I",
            "J",
            "H"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 23,
        "Q_start": 27,
        "opening": 30,
        "margin": 4
      },
      "holding_cost": 0,
      "total_cost": 31
    },
    {
      "codes": "XSTV",
      "cost": 35,
      "orders_examined": 288,
      "feasible_orders": 216,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "F": 6,
          "G": 8,
          "E": 11,
          "I": 9,
          "L": 11,
          "J": 11,
          "K": 15,
          "N": 15,
          "H": 16,
          "M": 19,
          "O": 19,
          "P": 21,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "F": 9,
          "G": 11,
          "E": 15,
          "I": 11,
          "L": 13,
          "J": 15,
          "K": 17,
          "N": 18,
          "H": 19,
          "M": 21,
          "O": 20,
          "P": 23,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S1"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C0"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F"
          ],
          [
            "G",
            "E"
          ],
          [
            "I",
            "J",
            "H"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 23,
        "Q_start": 27,
        "opening": 30,
        "margin": 4
      },
      "holding_cost": 0,
      "total_cost": 35
    },
    {
      "codes": "XSC",
      "cost": 37,
      "orders_examined": 1152,
      "feasible_orders": 566,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 8,
          "F": 6,
          "G": 9,
          "I": 9,
          "N": 12,
          "H": 12,
          "J": 14,
          "L": 12,
          "K": 14,
          "O": 18,
          "M": 19,
          "P": 21,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 12,
          "F": 9,
          "G": 12,
          "I": 11,
          "N": 15,
          "H": 15,
          "J": 18,
          "L": 14,
          "K": 17,
          "O": 19,
          "M": 21,
          "P": 23,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G"
          ],
          [
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 23,
        "Q_start": 27,
        "opening": 30,
        "margin": 4
      },
      "holding_cost": 0,
      "total_cost": 37
    },
    {
      "codes": "XSCV",
      "cost": 41,
      "orders_examined": 1152,
      "feasible_orders": 566,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 8,
          "F": 6,
          "G": 9,
          "I": 9,
          "K": 12,
          "N": 12,
          "H": 12,
          "J": 14,
          "L": 14,
          "M": 19,
          "O": 18,
          "P": 21,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 12,
          "F": 9,
          "G": 12,
          "I": 11,
          "K": 14,
          "N": 15,
          "H": 15,
          "J": 18,
          "L": 16,
          "M": 21,
          "O": 19,
          "P": 23,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G"
          ],
          [
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "K",
            "L"
          ]
        ],
        "P_finish": 23,
        "Q_start": 27,
        "opening": 30,
        "margin": 4
      },
      "holding_cost": 0,
      "total_cost": 41
    },
    {
      "codes": "XSCT",
      "cost": 43,
      "orders_examined": 1152,
      "feasible_orders": 566,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 8,
          "F": 6,
          "G": 9,
          "I": 9,
          "N": 12,
          "H": 12,
          "J": 14,
          "L": 12,
          "K": 14,
          "O": 18,
          "M": 18,
          "P": 20,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 12,
          "F": 9,
          "G": 12,
          "I": 11,
          "N": 15,
          "H": 15,
          "J": 18,
          "L": 14,
          "K": 17,
          "O": 19,
          "M": 20,
          "P": 22,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 3,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G"
          ],
          [
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "L",
            "K"
          ]
        ],
        "P_finish": 22,
        "Q_start": 27,
        "opening": 30,
        "margin": 5
      },
      "holding_cost": 0,
      "total_cost": 43
    },
    {
      "codes": "XSCTV",
      "cost": 47,
      "orders_examined": 1152,
      "feasible_orders": 566,
      "schedule": {
        "starts": {
          "A": 0,
          "B": 3,
          "C": 3,
          "D": 3,
          "E": 8,
          "F": 6,
          "G": 9,
          "I": 9,
          "K": 12,
          "N": 12,
          "H": 12,
          "J": 14,
          "L": 14,
          "M": 18,
          "O": 18,
          "P": 20,
          "Q": 27,
          "R": 29
        },
        "finishes": {
          "A": 3,
          "B": 7,
          "C": 6,
          "D": 8,
          "E": 12,
          "F": 9,
          "G": 12,
          "I": 11,
          "K": 14,
          "N": 15,
          "H": 15,
          "J": 18,
          "L": 16,
          "M": 20,
          "O": 19,
          "P": 22,
          "Q": 29,
          "R": 30
        },
        "resources": {
          "A": [
            "Services"
          ],
          "B": [
            "North preparation"
          ],
          "C": [
            "South preparation"
          ],
          "D": [
            "East preparation"
          ],
          "E": [
            "S1"
          ],
          "F": [
            "S0"
          ],
          "G": [
            "S0"
          ],
          "H": [
            "C0"
          ],
          "I": [
            "C0"
          ],
          "J": [
            "C1"
          ],
          "K": [
            "T"
          ],
          "L": [
            "T"
          ],
          "M": [
            "C0",
            "T"
          ],
          "N": [
            "Interpretation"
          ],
          "O": [
            "Operations"
          ],
          "P": [
            "C0",
            "T"
          ],
          "Q": [
            "Acceptance"
          ],
          "R": [
            "Operations"
          ]
        },
        "durations": {
          "A": 3,
          "B": 4,
          "C": 3,
          "D": 5,
          "E": 4,
          "F": 3,
          "G": 3,
          "H": 3,
          "I": 2,
          "J": 4,
          "K": 2,
          "L": 2,
          "M": 2,
          "N": 3,
          "O": 1,
          "P": 2,
          "Q": 2,
          "R": 1
        },
        "resource_orders": [
          [
            "F",
            "G"
          ],
          [
            "E"
          ],
          [
            "I",
            "H"
          ],
          [
            "J"
          ],
          [
            "K",
            "L"
          ]
        ],
        "P_finish": 22,
        "Q_start": 27,
        "opening": 30,
        "margin": 5
      },
      "holding_cost": 0,
      "total_cost": 47
    }
  ],
  "method": "Exhaustive assignments and resource orders; earliest calendar-feasible placement for each order; minimize P finish, then total start boundaries.",
  "elapsed_seconds": 0.58625375,
  "validation": "All 32 retained schedules independently checked for calendars, durations, precedence, fixed Q slots and resource non-overlap."
}