Decision memo · Eva Chen · Merefield Energy · 48 MW

Test the ground, protect access, keep full kits out.

On D1, Monday 22 March 2027, recommend G16 + R + I for £80k: approve the separable £30k investigation now, seek the board’s £50k balance on D5, and keep the D18 foundation release conditional on accepted ground findings. This buys better evidence, a drainage intervention and a controlled design boundary; it does not buy a proven saving. [19-A] [19-D] [19-E] [19-F]

Recorded position, D1: no purchases have been made and no package approval is recorded. Eva recommends; Omar accepts baseline findings; the board is needed above Omar’s cumulative £75k limit; the operator retains interface approval. All controls below are ephemeral planning scenarios. They do not authorise expenditure, certify engineering or edit evidence. Reload or Reset restores this dated recommendation. [19-E] [19-F]

The decision to take on 22 March

Commit now; stage the authority

Ask Omar to approve G16, £30k on D1. Ten field days D2–D11, then Gia’s four consecutive analysis days D12–D15, make the report usable at end D15. Preserve D16–D17 for response and Omar’s acceptance before the start-of-D18 order. These two days are decision margin, not a promise that any redesign will fit. [19-A] [19-E]

Take the whole £80k exposure to the D5 board. Request the remaining £50k as R £38k and I £12k. On approval, I uses Gia D6–D9; order R on D6 and deliver D26–D30 before D31 traffic. Ground analysis plus I uses all eight Gia-days. No room remains for P or K without replacing work or securing additional capacity. [19-A] [19-E]

Amend the baseline: separate the foundation geometry decision from unapproved interface/string-grouping and kit-label decisions. Retain D25 freeze as conditional on operator input expected D20; do not call that expectation an approval. Reject K from the current baseline: its D10 approved-interface requirement cannot be met. [19-D] [19-E]

Why this package

Two non-adjacent cobble zones and only two shallow points make copying Swift’s six selected blocks unsafe as a site-wide inference. G16 purchases broader information for £12k more than G8, with the same four analysis days; Gia must choose and document the sampling design. Six central positions are explicitly unrepresentative. Sixteen locations are still not proof for all 48 blocks. [19-C: L4] [19-D] [19-E]

The road decision rests on a surveyed low point and a single access route, not Lark’s claimed closure prevention. £70k of the £150k allowance would remain after £80k prevention, with £15k headroom to the prevention cap. None is a benefit or a validated redesign provision. [19-A] [19-D] [19-E]

Defensible alternative, before committing G16: G8 + R + I = £68k, wholly within Omar’s limit, approved D1. Field D2–D7; report end D11; I D2–D5; eight Gia-days; £82k allowance remains. It saves £12k of commitment and brings evidence four days earlier, but buys fewer observations. Choose it only if Gia can defend targeted coverage of both separated suspected zones and the wider site. Unknown findings still gate D18. [19-D] [19-E]

Planning assumption: the offers include agreeing and documenting the sampling design within their stated resources; no extra Gia-day is silently added. Gia must confirm that interpretation before mobilisation. If it is false, Eva must rebalance scope/capacity and re-run the dates. The memo does not prescribe pile positions, engineering adequacy or safety acceptance.

Interactive proposal · no approvals are created

Test cost, resource fit and the D18 gate

Choose a mutually exclusive investigation and optional commitments. Dates are intended approval dates, not recorded approvals. Work starts no earlier than the next workday. The schedule uses the fixed quoted durations, with no holidays. [19-A] [19-E]

A favourable selection is a hypothetical report, not approval. Partial release is conditional on Gia identifying evidenced, independent scope and Omar explicitly accepting it; this page never identifies safe blocks.

£80kProposed prevention commitment
£70kAllowance after proposed spend
8 / 8Gia-days requested / available
£15kHeadroom to £95k prevention cap

    D18 foundation-release instruction

    Resource-loaded route for this scenario

    Field / implementationGia engineeringFixed gateUnachievable / outside window
    Activity / ownerDays and usable outputD1 D31

    Scenario receipt: the visible selection is a temporary decision aid, stored only in this page’s memory. No order, approval, operator consent or baseline change has been issued. Source records and the original D1 position remain below. Reselection corrects the scenario; Reset or reload discards it. Invalid scenarios remain visible with their failed checks.

    Audit of the strongest improvement claim

    “33% efficiency” is a shorter measured interval

    The newsletter compares Wren and Kestrel. The observed change is 12 to 8 on-site weeks: 4/12 = 33.3% shorter elapsed installation. Kestrel also used three crews instead of two, had dry chalk and stable design, and excludes ten preceding fabrication weeks. This is not an identified prefab efficiency effect. [19-B] [19-C: L1, L2]

    Measured on-site weeks

    Wren L1
    12 weeksKestrel L2
    8 weeks

    Two full wet-access stop weeks are inside Wren’s 12. Ten fabrication weeks are outside Kestrel’s 8.

    Crew exposure within that interval

    Wren L1
    24 crew-wkKestrel L2
    24 crew-wk

    Crude normalisation only: crew size, skill mix and labour hours are not supplied.

    Like-for-like scope is 48 MW; other conditions are not controlled [19-C: L1, L2]
    Measure and workingWren L1Kestrel L2What it can establish
    Calendar productivity: MW ÷ measured weeks48 ÷ 12 = 4 MW/week48 ÷ 8 = 6 MW/week50% higher throughput per calendar week, not 33% labour efficiency.
    Crew-weeks: crews × on-site weeks2 × 12 = 243 × 8 = 24Same crew exposure including stops.
    MW per measured crew-week48 ÷ 24 = 2.048 ÷ 24 = 2.0No observed improvement on this proxy.
    Active crew-weeks: crews × (weeks − full stops)2 × (12 − 2) = 203 × (8 − 0) = 24Stop-adjusted exposure is greater for Kestrel.
    MW per active crew-week48 ÷ 20 = 2.448 ÷ 24 = 2.0Kestrel is 16.7% lower on this proxy; this also is not a causal verdict.
    Known preceding work excluded from headlineNot supplied10 fabrication + 8 on-site = 18 weeks across these two sequential intervalsDo not compare 18 with 12 as whole-project programmes; Wren’s comparable off-site boundary is unknown.

    Credible rivals to the prefab story: extra crews, dry chalk versus wet clay, access stoppages, stable versus changing design, and off-site work omitted from the clock. Rook used the same supplier as Kestrel but paid £95k modifications plus three off-site rework weeks after a late design change; its ten on-site weeks hide that rework. Together these records support controlling design maturity, not promising a four-week saving. [19-C: L1, L2, L6]

    The 8% steel claim is a different project: Osprey’s five-project pooled order, largely supplied by others’ volume, does not isolate prefab. £50k damage occurred there; Kestrel separately excluded £70k storage/transport. Do not combine these costs or calculate a net percentage without price bases. Merefield lacks both the pooled framework and full-kit holding area. Carry zero assumed cash or programme credit into this baseline, not a claim that true benefits are zero. [19-C: L2, L5] [19-D]

    Evidence → mechanism → conditional transfer

    These are Eva’s proposed judgements. Selection badges reflect the temporary package above; they do not change the evidence or the recommendation’s reasoning.

    1. Find ground variation before ordering Selected: G16

    Evidence and rival: Swift detected redesign in tested blocks, then encountered refusal in two untested zones. The claimed £120k avoided has no priced counterfactual. The selected blocks may have been unusually informative, while wider ground differences limit transfer; Wren’s £180k foundation changes are historical context, not Merefield’s avoided cost. [19-C: L1, L4]

    Mechanism and boundary: timely, representative investigation can expose incompatible ground before an irreversible order. G16’s broader offer is preferred here because suspected zones are separated. Gia documents locations, rationale, coverage limits and residual uncertainty; neither eight nor sixteen points guarantees all blocks. [19-D] [19-E]

    Change and falsifier: Fay adds fieldwork, consecutive analysis and an evidence-acceptance gate before D18. A late report, unrepresented zone or refusal changes the order to hold or explicitly justified partial release; Gia supplies evidence, Omar accepts scope. No automatic redesign/remediation funding is included. [19-F]

    2. Protect the single heavy-delivery route Selected: R

    Evidence and rival: Lark’s zero closures with £42k reinforcement occurred in an unusually dry season with no untreated comparator. The planned five closure days were not observed avoided delay. Weather alone could explain its result. [19-C: L3]

    Mechanism and boundary: the current survey confirms a flooded low point would block heavy deliveries and there is no alternative road. Drainage/reinforcement addresses that vulnerability; neither event probability nor days saved is validated. The £38k current offer, not Lark’s nominal cost, funds R. [19-A] [19-D] [19-E]

    Change and falsifier: Leon orders by D20, plans D26–D30, records completion and access readiness before D31. If scope review cannot address the low point, the order deadline slips, or flooding/access failure remains, Leon stops relying on the delivery date and Fay resequences haulage for Omar’s decision. No substitute route is assumed.

    3. Separate stable foundations from unconfirmed kits Selected: I

    Evidence and rival: Kestrel’s early stable design and Rook’s post-order changes plausibly explain different outcomes; supplier performance or different scope could also contribute. Same supplier is useful context, not an experiment. [19-C: L2, L6]

    Mechanism and boundary: I turns the current evidence that geometry can be independent into a controlled boundary: foundations tied to accepted ground, strings/labels and associated kit tied to operator-approved interface. Four Gia-days create the split, interface register and change controls; they cannot pull operator approval forward. [19-D] [19-E]

    Change and falsifier: Gia documents dependencies; Fay installs separate freeze/release gates. If interface details or investigation contradict independence, block affected release and rebaseline through Omar. At D20, missing or changing operator detail triggers review of D25 freeze and dependent kit dates. Operator retains its approval. [19-F]

    4. Reject full-kit acceleration in this baseline Rejected: K

    Evidence and rival: newsletter timing and steel claims confound crews, weather, off-site work and pooled purchasing. A mature design and buying volume, rather than prefab itself, may drive the advantage. [19-B] [19-C: L1, L2, L5, L6]

    Mechanism and boundary: stable, approved design might allow early kit manufacture, but K demands approved interface by D10. The operator will not approve before D20; no supplier substitute relaxes it. Storage is also absent and K needs six Gia-days. Reject £55k K regardless of apparent budget headroom. [19-A] [19-D] [19-E]

    Change and falsifier: Eva can reopen K only against an explicitly revised programme with actual approved design, secure holding arrangements, a current offer and resourced engineering. D20 approval cannot retrospectively satisfy D10. No early-kit benefit enters D18.

    5. Keep the reversible label experiment as an option Not funded: P

    Evidence and rival: Rook’s rework and the present possibility of string/label change justify learning about change handling; they do not prove that a small trial scales to all kits. A neat trial may reflect controlled conditions rather than a robust process. [19-C: L6] [19-D]

    Mechanism and boundary: P could test label revisions, traceability and withdrawal of superseded versions without a full-kit commitment. It costs £8k and two Gia-days. Both proposed packages already use eight days, so P is not an uncosted extra or a replacement for operator approval. [19-E]

    Change and falsifier: if a revised package funds P, Gia records a controlled label-change exercise, mismatches and correction/retrace results; failures require process revision before use. A successful trial supports that limited process only. Eva must explicitly displace other work or secure capacity; no guaranteed programme saving is credited.

    Approval, release and learning controls

    Recommended package — proposed owner commitments, not completed actions [19-A, 19-E, 19-F]
    When / accountable ownerEvidence or decision to retainTrigger → required response
    D1 · Eva / Omar£80k package submission with £30k G16 staged authorisation, £50k pending board, £70k remaining allowance. Gia’s documented sampling rationale and resource confirmation before mobilisation.If sampling cannot represent separated suspected zones or consumes extra Gia capacity, revise sampling/resource plan before relying on the quoted route; no technical certification inferred.
    D5 · Board / OmarWhole-package decision, cumulative authority and the £30k already exposed. Approval authorises R + I balance, not artificial parts of a single order.If declined or deferred, R and I remain uncommitted. Continue only the separately authorised G16. An explicit reduced G16 + R proposal (£68k cumulative) could fit Omar’s limit, but drops I and requires a revised boundary/control plan. It is not the original £68k G8 alternative or a silent switch/refund.
    D6 · Leon; D6–D9 · GiaR order receipt by D20; I dependency register, foundation/kit boundary, unresolved interface items and change approval route.No board decision means no assumed R/I start. If I cannot establish independence, hold affected foundations/kit and escalate schedule consequences to Omar.
    End D15; D16–D17 · Gia / Omar / FayReport, tested coverage, refusals, residual uncertainty; priced and timed response where needed; Omar’s recorded acceptance and Fay’s release baseline.Adverse, incomplete or late evidence: hold D18 full order. Partial release only for evidenced independent scope identified by Gia and explicitly accepted by Omar; otherwise re-date. Testing does not pay for redesign/remediation.
    D20 · Gia / operator / FayActual interface details and approval status; change impact on strings/labels and independent foundations. Recheck D25 freeze.Expected details are missing, unapproved or incompatible: keep affected kit frozen from procurement, reassess D25 and works dependencies; never replace approval with an assumption.
    D20 then D26–D30 · LeonOrder lodged on time; completion record, condition of low point and access-readiness evidence before D31.Unordered by D20, incomplete by D30 or unsuitable road: no assumed heavy-traffic readiness. Leon informs Fay; Omar decides revised access/haulage plan and exposure.
    After works · Eva with Gia / Leon / FayTrials versus later refusals by tested/untested areas; road condition, rainfall and actual closures; crew counts, active/stopped days, off-site effort, kit changes and full costs.A mismatch between tested findings and later refusals challenges sampling transfer; closures despite completed R challenge access assumptions. Keep these observations with confounders, not a new unsupported “avoided” saving.

    Control accounts: retain separate observed costs, forecast effects and approved commitments. Record discoveries against the £70k residual allowance without assuming it is sufficient. Any remediation, new engineering demand or changed programme goes back to the relevant authority; no automatic cash saving releases allowance. [19-E] [19-F]

    Dated evidence retained for review

    Supplied fictional records only. Historical nominal costs explain context; fixed current offers fund this proposal. Disclosures retain adverse evidence and uncertainty.

    19-A · D1 baseline and authority

    Director Omar Shah: 48 MW; four ground zones of twelve pile blocks each. Coastal clay, intermittent cobbles in two zones; two shallow desk-study points are insufficient to map them. One low-lying access road, no alternative.

    Foundation order released at start D18; changes require evidence by end D17. Design freeze D25; main works/haulage D31. Grid-interface details expected D20; operator will not approve earlier. Remaining risk allowance £150k. Prevention cap £95k. Omar’s cumulative delegated limit £75k; board above that available at D5. Separable investigation can be approved before balance; artificial splitting of one order forbidden.

    Gia Cole has eight engineering days flexibly within D2–D17; other demand fills remaining capacity. Quoted consecutive analysis/report periods remain consecutive. Leon Ward owns logistics; Fay Moss owns integrated plan.

    19-B · Sponsored 2026 programme newsletter
    “Prefabrication cut installation from 12 weeks to 8: a 33% efficiency gain, with an 8% steel saving. Repeat this standard. Trial piles and access roads are optional risk costs; the real lesson is to order kits early.”

    Sponsored by former delivery director. Compares L1/L2, with cost claim from L5. No further calculation attached. Treat as a claim, not a validated causal result.

    19-C · Signed close-outs and diaries, retrieved 17 March — all six cases

    Weeks are on-site installation from crew arrival to completion, including stoppages, five days/week. Crew counts stayed constant. MW is completed scope.

    SourceScope and resourcesObserved outcome, caveats and adverse evidence
    L1 Wren 202448 MW conventional; 2 crews; 12 on-site weeksTwo full weeks stopped by wet access; inland clay; no pretrials; refusal in one cobble band; £180k foundation changes.
    L2 Kestrel 202548 MW prefab; 3 crews; 8 on-site weeksDry chalk; no weather stoppage; design stable before order; ten off-site fabrication weeks precede and are excluded from measured interval; £70k storage/transport excluded from claimed steel saving.
    L3 Lark 202640 MW coastal clay; £42k access reinforcementZero closures; unusually dry season; planner allowed five closure days; no observed untreated comparator.
    L4 Swift 202644 MW; £26k trials in six selected blocksDetected redesign before orders there; refusals later in two untested zones. Claimed £120k avoided; no priced counterfactual survives.
    L5 Osprey 202532 MW; five-project pooled steel order8% quoted discount; £50k storage damage; other projects supplied most volume; prices do not isolate prefab effect.
    L6 Rook 202648 MW prefab; 2 crews; 10 on-site weeksDesign changed after order; £95k modifications and three off-site rework weeks before arrival, excluded from site measure; same supplier as L2.
    19-D · Current-site evidence, Gia / Leon, D1

    Two suspected cobble zones are non-adjacent: six centrally selected tests would not represent the site. Drainage survey confirms a low point preventing heavy deliveries when flooded; no validated probability or closure-duration estimate.

    Operator details may change string grouping and related kit labels; foundation geometry can be fixed independently after ground results. No five-project buying framework or secure full-kit holding area exists. These facts do not assure that any intervention eliminates delay.

    19-E · Fixed inclusive current offers and their limits
    Action / costResources and conditions
    G8 £18kEight targeted locations: six field days, then four consecutive analysis/report days with Gia all four days. Independent field crew. Fieldwork only D1–D15.
    G16 £30kSixteen distributed locations: ten field days, then four consecutive analysis/report days with Gia. Same access rule. Mutually exclusive with G8.
    R £38kFive days D26–D30; order by D20; no Gia days; finish before D31 heavy traffic.
    I £12kFour Gia-days before D17. Controlled separation of independent foundations and unconfirmed kit details; no early operator approval.
    K £55k incrementalApproved interface freeze by D10 needed for baseline, no supplier substitute relaxes it; six Gia-days by D17.
    P £8kTwo Gia-days by D17; reversible label/change-handling/traceability trial; no guaranteed saving.

    No automatic cash saving or allowance release beyond actual unspent amount. Testing/reporting quotes exclude later redesign and remediation. Discoveries require programme reassessment. Purchases have not been made.

    19-F · Decision rights and the release gate

    Eva recommends packages and baseline/control changes. Gia chooses and documents sampling; this memo must not invent technical design or safety certification. Omar accepts findings into baseline; operator retains interface approval. Inadequate evidence for D18 requires explicit hold/partial-release decision; assumptions are not ground evidence. Staged packages are permitted with visible exposure and later board decision. Triggers and evidence need named owners.

    Recover the initial dated position and model assumptions

    Original proposed D1 package, unchanged by the calculator

    G16 + R + I £80k; £30k separable G16 submitted to Omar D1; £50k balance to board D5. G16 field D2–D11, report D12–D15. I D6–D9. R ordered D6, works D26–D30. All eight Gia-days used. £70k allowance remains, £15k prevention headroom. No actual purchase or approval recorded; ground outcome pending. Alternative before commitment: G8 + R + I £68k; delegated D1; report D11; I D2–D5.

    Model boundary

    D1 is Monday 22 March 2027. D numbers count weekdays without holidays. Work of n days starting Ds ends D(s+n−1), report usable that evening. Model starts fieldwork the day after investigation approval; analysis follows fieldwork and stays consecutive. I has a strict end-before-D17 limit; P/K can use D17. Other measures begin no earlier than the day after their selected approval. All optional engineering is placed on free eligible days, with I first because its deadline is earlier. These are scheduled intentions under quoted conditions, not completion forecasts guaranteed by prior cases.

    Approval checks assess the whole selected package, not separate order fragments. The D5 board meeting is the only above-limit approval slot evidenced. Capacity of eight days is a hard total as well as a calendar restriction. Fixed costs are current; no speculative probabilities, expected savings, avoided-loss credits or contingency adequacy claims are inserted. Gia’s sampling-design resource interpretation is a disclosed assumption to verify before mobilisation.

    Read the complete supplied case · BPB2-19
    # BPB2-19 — Solar farm construction — use previous experience intelligently
    
    Suite BPB2 v0.3-pilot; Foray 247, third essai.
    
    ### Scenario
    Merefield Energy is preparing a forty-eight-megawatt solar farm on coastal clay. Project manager Eva Chen has an apparently persuasive lessons pack, but its headline savings mix crew numbers, weather, off-site effort and different design conditions. She must propose concrete plan changes on 22 March 2027 before investigation and purchasing windows close. Preventive money and engineering attention are limited. Eva needs to decide what previous experience warrants committing now, what should be tested, and which attractive lessons should not enter this baseline.
    
    ### Exact task prompt
    
    Produce one usable in-browser answer page for the named practitioner, using the supplied fictional evidence. Keep observed facts, forecasts, assumptions and proposed decisions distinguishable, and cite source IDs beside material claims. No external research or real-world certification is required.
    Prepare Eva's evidence-to-action decision memo. Select a coherent package of transferable lessons and translate them into specific funded commitments, baseline amendments and controls for this site. Audit the strongest claimed improvement rather than accepting its headline. State the mechanism and boundary conditions behind each transfer, identify a credible competing explanation, and define what observation would cause the action or plan to change. Show an executable approval/timing route and one defensible alternative package. Do not fabricate probabilities, expected savings or causal certainty; equally, do not defer every action until perfect evidence exists.
    
    ### Supplied records
    All projects and records are synthetic. Current decision is D1=Monday 22 March 2027; D numbers count weekdays, no holidays. Work ofn days starting Ds occupies Ds through D(s+n−1); its report is usable at that day's end. An order/investigation may start the workday after its approval. Currency GBP; historical nominal costs may support mechanism/context analysis but must not be treated as current quotes.
    
    **19-A — Current baseline/authority, director Omar Shah, D1.** Site 48MW, four ground zones of twelve pile blocks each. Coastal clay, intermittent cobbles in two zones; existing test coverage is two shallow desk-study points, insufficient to map the cobbles. One low-lying access road, no alternative. Foundation order is released at the **start of D18**; any change must use evidence available by end D17. Design freeze D25; main works/haulage D31. Grid-interface details are expected D20; the operator will not approve them earlier. Remaining risk allowance £150k. Up to £95k may be committed to prevention, but Omar's cumulative delegated limit is £75k; board approval above that is available at its D5 meeting. Separable investigation can be approved before the rest of a package; artificial splitting of one order is forbidden. Gia Cole has eight engineering days available, flexibly schedulable within D2–D17; other engineering demand already fills the rest of her capacity. The quoted consecutive analysis/report periods must remain consecutive. Leon Ward owns logistics; Fay Moss owns the integrated plan.
    
    **19-B — Programme newsletter, 2026, sponsored by the former delivery director.** “Prefabrication cut installation from 12 weeks to 8: a 33% efficiency gain, with an 8% steel saving. Repeat this standard. Trial piles and access roads are optional risk costs; the real lesson is to order kits early.” The article compares L1 and L2 below; its cost claim refers to L5. No further calculation is attached.
    
    **19-C — Signed close-out summaries and diaries, retrieved 17 March.** The recorded weeks cover on-site installation from crew arrival to completion, including stoppages; five days/week. Crew counts stayed constant. These are completed scope, not planned MW.
    
    | Source | Scope/method/resources | Observed outcome and conditions |
    |---|---|---|
    | L1 Wren 2024 | 48MW conventional;2 crews;12 on-site weeks | Two full weeks stopped by wet access; inland clay; no pretrials; refusal problems concentrated in one cobble band; foundation changes cost £180k |
    | L2 Kestrel 2025 | 48MW prefabricated;3 crews;8 on-site weeks | Chalk, dry; no weather stoppage; design stable before kit order; ten off-site fabrication weeks precede the measured interval and are excluded; storage/transport cost £70k excluded from the claimed steel saving |
    | L3 Lark 2026 | 40MW coastal clay; access reinforcement £42k | Zero access closures; unusually dry season; planner had allowed five closure days, but no observed untreated comparator exists |
    | L4 Swift 2026 | 44MW; trial piles £26k in six selected blocks | Detected redesign before orders in those blocks; refusal later occurred in two untested zones. Director claimed £120k “avoided”; no priced counterfactual survives |
    | L5 Osprey 2025 | 32MW; five-project pooled steel order |8% quoted steel discount, but £50k storage damage; other projects provided most purchasing volume; contract prices do not isolate a prefab effect |
    | L6 Rook 2026 | 48MW prefabricated;2 crews;10 on-site weeks | Design changed after kit order;£95k modification plus three weeks off-site rework before crew arrival, excluded from on-site measure; same supplier as L2 |
    
    **19-D — New-site evidence, Gia/Leon, D1.** The two suspected cobble zones are non-adjacent, so six centrally selected test positions would not represent the site. The road's drainage survey confirms a low point that would prevent heavy deliveries when flooded; no probability or closure duration estimate is validated. Operator interface details may change string grouping and associated kit labels, but foundation geometry can be fixed independently after ground results. The project has neither a five-project buying framework nor a secure full-kit holding area. These are current facts, not an assurance that any intervention eliminates delay.
    
    **19-E — Fixed current offers, D1; all costs fully inclusive.**
    
    | Action | Cost | Duration, resources and limits |
    |---|---:|---|
    | G8: eight targeted trial locations |£18k | Six workdays fieldwork then four analysis/report days; Gia required for all four analysis days; field crew independent. Land access allows fieldwork only D1–D15 |
    | G16: sixteen distributed trial locations |£30k | Ten fieldwork days then four analysis/report days; same Gia requirement and access rule; mutually exclusive with G8 |
    | R: road drainage/reinforcement |£38k | Five workdays, can be done D26–D30 if ordered by D20; no Gia days; must finish before D31 heavy traffic |
    | I: interface/kit boundary workshop and controlled design split |£12k | Four Gia-days before D17; does not obtain early operator approval. Produces a controlled separation of independent foundations from unconfirmed kit details |
    | K: full-kit procurement/storage/expediting |£55k incremental | Needs approved interface freeze by D10 to meet baseline; no supplier substitute can relax this. Also needs six Gia-days by D17 |
    | P: small reversible kit-label trial |£8k | Two Gia-days by D17; can test change-handling and traceability without committing full kits; no guaranteed programme saving |
    
    No action earns an automatic cash saving or releases risk allowance beyond the amount actually unspent. The groundwork quotes cover testing/reporting, not subsequent redesign or remediation. Programme effects of discoveries must be reassessed. Purchases have not been made.
    
    **19-F — Controls and decision rights, Omar, D1.** Eva may recommend the package and propose baseline/control changes. Gia must choose and document the sampling design; do not invent technical design or safety certification. Omar accepts findings into the project baseline; the operator retains interface approval. If ground results cannot support the D18 order, an explicit hold/partial-release decision is needed; assumptions are not accepted ground evidence. A staged package is permitted, with exposure and the later board decision visible. Keep a named owner for each trigger and evidence item.
    
    ### Browser deliverable and completion conditions
    Produce a navigable decision memo linking each selected/rejected lesson to source evidence, competing explanations, the current-site mechanism and a specific baseline/control change. Show budget, engineering-capacity and approval/deadline implications for recommended and alternative packages. Selecting G8/G16 and optional measures must update those checks; source disclosures must retain adverse evidence, not just the favourable quotation. The practitioner should be able to see exactly what is authorised/proposed now and what happens if investigation results are unfavourable or late.
    
    The page must work in the supplied browser/runtime; a download button or file preview alone is insufficient. Include a clear “Return to gallery” link using the shared shell route, or ../index.html if no route is supplied. Required controls must change the dependent results, not just their appearance. Original evidence and the initial dated position must remain recoverable; hypothetical changes do not create approvals or alter source records. Optional exports are secondary.