Westhaven tram extension · Brief for Ravi Sethi

Secure the extra crew. Release testing through the charter.

Order the £8,000 operator offer by noon 30 September and appoint a temporary-pack coordinator. This preserves the D9–D10 specialist booking. Seek sponsor approval to move full service from D12 to D13, Wednesday 20 October 2027—the earliest feasible date, conditional on successful testing. 13-H13-A13-G

Initial decision position: 29 September 2027. No crew order, coordinator appointment, rebooking, new test result, TTA or revised service date is recorded as approved. Existing signed evidence and the charter remain authoritative.

The decision now

Ravi can act within delegation: order the offered second qualified crew for D8–D10 (£8,000 total) and appoint the temporary test-authority pack coordinator by noon 30 September. Proposed appointee: Chen Wu, already the QA lead. The appointment remains a proposal until Ravi makes it. 13-C13-H

Benefit of the extra crew: five working days earlier and £4,000 less incremental cost than rebooking with one crew. 13-G

Sponsor decision: approve the revised advertised date. If Ravi does not buy the extra crew, also approve the £12,000 rebooking and a D18 service forecast. Neither route meets D12; no zone-by-zone passenger opening is authorised. 13-A13-H

Replace the conflicting request with the signed authority distinction. Ben’s request for final passenger acceptance before energisation conflicts with the binding charter. Retain final acceptance as the passenger-service gate and use Mara’s zone TTA as the separate test-energisation gate. Chen’s energised-and-familiarised condition for each dynamic test is retained. 13-E13-F

Ravi should record this interface agreement with Ben, Mara and Chen before D1. It implements existing authority; it does not waive a test or invent permission.

Both complete routes, calculated from the same unchanged evidence
ConsequenceOne existing crewWith offered extra crew

Costs are incremental to the existing booking; no total programme cost is supplied. The extra crew is an inseparable £8,000 offer for D8–D10, even though the crucial overlap is D9. Forecasts assume success and the required approvals; they are not promised openings. 13-G13-H

Two permissions remove the apparent cycle

Valid zone G + R + P
Accepted common P3 drawing
→Mara issues zone TTA
End of evidence day
→Ben authorises energisation
Next working day
→Familiarisation
Then zone dynamic tests
→Cross-zone test
Final assembly & joint review
→Mara’s final acceptance
Passenger service next day

Every arrow is a retained dependency. Checking completed records can be signed at day-end without adding a day; activities themselves occupy whole days and successors start the next working day. TTA permits energisation and testing only. 13-A13-F

Why these are the first feasible service dates

W2 and power input P3 become usable on D5. The separate design team produces/reviews the P3 drawing on D5, while the QA crew proves West G. P tests cannot start before D6 and the single QA crew needs two days, D6 and D7. With zone TTAs signed at those day-ends, the single power crew energises on D7 and D8. Earliest familiarisations are therefore D8 and D9. 13-A13-D13-F

The D9–D10 dynamic slot requires the first zone’s dynamic test on D9 and the second zone’s familiarisation on D9. A single operator crew cannot do both. Reversing zones does not change this bound. With two crews, that overlap is feasible; without them, the next inseparable dynamic slot is D14–D15. No split booking is allowed. 13-G

With extra crew: dynamic D9–D10 → cross-zone D11 → final assembly/review/acceptance D12 → service D13. Without: dynamic D14–D15 → cross-zone D16 → final record D17 → service D18. Even the fastest route needs D12 for the final record, so passenger service cannot start on advertised D12. 13-A13-F13-G

Preserve three signed records; do three new static tests

Applicability depends on each test family’s fingerprints, not the executable label alone. S7→S8 changes diagnostics only. Three static records carry forward; East P, West G and West P require new proving. Both dynamic tests are new campaign work. 13-B13-C

Select a test to inspect the precise transfer decision
Zone / familyTarget relevant identifiersPrior signed recordDispositionPlanned work

Critical interface agreement register

Proposed execution agreements for Ravi to close before 4 October. Authority comes from the supplied charter and delegation; future evidence and signatures remain pending. Select a handoff, or a matching activity in the day view, to inspect its gate.

Producer → receiver, controlled version, acceptance evidence and accountable decision
Handoff / due pointProducer → receiving authorityVersion / configurationAcceptance evidenceAccountable decision

Day-by-day resource sequence

Click an activity to open its interface agreement. Each populated resource cell is a whole-day use unless explicitly marked “end-day” or a fixed input milestone. Blanks mean no required work scheduled. Joint drawing review uses a separate design team and can overlap QA. Independent zone isolation permits the D7 overlap between energising one zone and static P proving in the other. 13-D

Selected scenario resource assignments
Day / dateInputs / designQA crewPower crewOperator crew 1Operator crew 2Test specialistsRecords / authority

All operational rows are conditional plans, not records of completed work. D1 = Monday 4 October 2027; weekdays only, no holidays. No work outside the supplied records is inserted as a blocker. 13-A

Controls and boundaries

Supplied evidence, recoverable in full

Synthetic BPB2-13 fixture only. Links throughout the page point to these unaltered source records; planning conclusions are calculations from them.

13-A — supplied record
**13-A — Planning and control, integration office, 28 September 2027.** D1 is Monday 4 October; count weekdays only, with no holidays. Activities occupy whole working days; successors start next working day. An input verified on Dn is usable from Dn+1. Authorisations that require only checking completed records may be signed at the end of the completion day and add no extra day. Advertised full service is D12. Zone-by-zone passenger service is not authorised. Full service starts the working day after the final service record is assembled and accepted. No other work beyond the records below blocks service.
13-B — supplied record
**13-B — Target configuration and equivalence rule, design authority, 28 September.** Target executable release is S8. East fingerprints: geometry E4, route logic K2, power/isolation P3. West: geometry W2, route logic K3, power/isolation P3. S8 differs from S7 only in diagnostics, so a test may transfer across those executable labels if every fingerprint relevant to its test family matches. This rule authorises evidence reuse, not undocumented configuration changes.

| Test family | Fingerprints that must match | Duration for a required new test in one zone |
|---|---|---:|
| G: geometry/position proving | Zone geometry only | 1 day |
| R: route-logic proving | Zone route logic only | 2 days |
| P: static power/isolation proving | Zone geometry AND common power/isolation drawing | 1 day |
| D: dynamic zone test | All target fingerprints; new test required for this commissioning campaign | 1 day/zone |
13-C — supplied record
**13-C — Signed existing test records, QA lead Chen Wu, 27 September.** Every record below passed and has its signed result attached in this fixture; the question is applicability, not whether “passed” means tested. No other transferable tests exist.

| Record | Zone/family | Executable and relevant evidence identifiers |
|---|---|---|
| E-G-14 | East G | S7; E4 |
| E-R-09 | East R | S7; K2 |
| E-P-07 | East P | S7; E4/P2 |
| W-G-12 | West G | S7; W1 |
| W-R-11 | West R | S7; K3 |
| W-P-05 | West P | S7; W1/P2 |
13-D — supplied record
**13-D — Input handoffs, track/power leads, 28 September.** East E4 geometry is already verified. West W2 survey is verified at end D4; it cannot be released earlier. Power as-built input P3 is ready end D4. Producing and jointly reviewing the common P3 isolation drawing occupies D5, using both verified geometries and the power input; a separate design team does this. Track lead Talia Reed, power lead Ben Cole and operator Mara Finn must accept the drawing at end D5. It defines independent zone isolation, so one zone may be live while the other undergoes de-energised work. East/West G, R and P tests use one shared QA crew, and each zone’s P test must follow that zone’s valid G and R evidence plus the accepted P3 drawing. The drawing review can run in parallel with G/R testing.
13-E — supplied record
**13-E — Conflicting interface requests, 29 September.** Ben’s work order says: “No zone energisation until Mara provides final passenger-service route acceptance.” Mara replies: “Final route acceptance follows dynamic and cross-zone testing; I will not sign it beforehand.” Chen’s request says each route must already be energised and familiarised when its own dynamic test starts. These requests are not amendments to the charter below. Ravi has not yet named the person assembling the temporary test-authority pack.
13-F — supplied record
**13-F — Joint commissioning charter, signed by all four leads, 20 September; binding.** There are two distinct permissions. A **temporary test authority (TTA)** permits energisation and testing, not passenger service. Mara may issue it for a zone at end of day once that zone has valid G/R/P evidence and the accepted common P3 drawing. Ben then authorises a one-day energisation activity on the next working day. One power commissioning crew serves the two zones; zone energisations cannot overlap. Following successful energisation, a one-day operator familiarisation is required. Dynamic testing follows familiarisation and requires the shared specialist test team plus one qualified operator crew. After both zone dynamic tests, one full-day cross-zone integration test is required. Final record assembly and joint review take one further day, using all zone/cross-zone results and the locked target configuration. Mara alone accepts the final record and authorises passenger service. This charter is the complete fictional operating rule; TTA is an authorised stage, not a safety waiver.
13-G — supplied record
**13-G — Resources/windows, programme controls, 29 September.** One QA crew performs any required G/R/P tests. One power crew performs energisation. One existing qualified operator crew can perform either familiarisation or attend one zone dynamic test on a day, never both. A second fully qualified operator crew is offered for D8–D10 for £8,000 total; it may perform familiarisation or attend dynamic testing without additional induction. All other named people are available when required. Dynamic specialists sell an inseparable two-day slot: both zones must be tested on consecutive days in either order. Existing booking D9–D10; next available D14–D15, costing an additional £12,000 if rebooked. The two bookings cannot be split to test one zone in each. Cross-zone specialists are available D11 or D16 only. Record-assembly staff are available after either window. Test success is prospective and cannot be guaranteed.
13-H — supplied record
**13-H — Authority/deadline, sponsor, 29 September.** Ravi may appoint the temporary-pack coordinator and order the second operator crew within his £10,000 delegation by noon 30 September. Rebooking at £12,000 and changing the advertised service date need sponsor approval. He cannot change fingerprints, waive tests, create passenger-service permission or command the operator to accept evidence not yet produced. A plan may propose appointments/sign-offs but must distinguish those from approvals already given.
Read the complete supplied case · BPB2-13
# BPB2-13 — Tram extension — resolve delivery interfaces

Suite BPB2 v0.3-pilot; Foray 247, third essai.

### Scenario

Westhaven’s tram extension has East and West test zones, several versions of apparently satisfactory evidence and incompatible interpretations of when power may be switched on. Integration manager Ravi Sethi needs executable interface agreements before 4 October 2027. The booked specialist window is close, and the same operator crew is expected in two places. Ravi must preserve valid completed work, break a real approval deadlock through the supplied authority and expose the date and resource decisions that remain.

### Exact task prompt

Produce one usable in-browser answer page for the named practitioner, using the supplied fictional evidence. Keep observed facts, forecasts, assumptions and proposed decisions distinguishable, and cite source IDs beside material claims. No external research or real-world certification is required.

Prepare Ravi’s critical interface agreement register and integrated route to full service. Determine which existing evidence carries forward to the target configuration, identify the remaining work, resolve the apparent acceptance/energisation cycle through the authorised process, and compare the first feasible service date with and without the offered extra operator crew. Name the producer, receiving authority, version, acceptance evidence, accountable decision and due point for each critical handoff. Show a resource-feasible sequence, the implications for the advertised date and the specific decision needed now. Do not replace valid evidence unnecessarily or invent a waiver, split booking, partial service or test authority.

### Supplied records

**13-A — Planning and control, integration office, 28 September 2027.** D1 is Monday 4 October; count weekdays only, with no holidays. Activities occupy whole working days; successors start next working day. An input verified on Dn is usable from Dn+1. Authorisations that require only checking completed records may be signed at the end of the completion day and add no extra day. Advertised full service is D12. Zone-by-zone passenger service is not authorised. Full service starts the working day after the final service record is assembled and accepted. No other work beyond the records below blocks service.

**13-B — Target configuration and equivalence rule, design authority, 28 September.** Target executable release is S8. East fingerprints: geometry E4, route logic K2, power/isolation P3. West: geometry W2, route logic K3, power/isolation P3. S8 differs from S7 only in diagnostics, so a test may transfer across those executable labels if every fingerprint relevant to its test family matches. This rule authorises evidence reuse, not undocumented configuration changes.

| Test family | Fingerprints that must match | Duration for a required new test in one zone |
|---|---|---:|
| G: geometry/position proving | Zone geometry only | 1 day |
| R: route-logic proving | Zone route logic only | 2 days |
| P: static power/isolation proving | Zone geometry AND common power/isolation drawing | 1 day |
| D: dynamic zone test | All target fingerprints; new test required for this commissioning campaign | 1 day/zone |

**13-C — Signed existing test records, QA lead Chen Wu, 27 September.** Every record below passed and has its signed result attached in this fixture; the question is applicability, not whether “passed” means tested. No other transferable tests exist.

| Record | Zone/family | Executable and relevant evidence identifiers |
|---|---|---|
| E-G-14 | East G | S7; E4 |
| E-R-09 | East R | S7; K2 |
| E-P-07 | East P | S7; E4/P2 |
| W-G-12 | West G | S7; W1 |
| W-R-11 | West R | S7; K3 |
| W-P-05 | West P | S7; W1/P2 |

**13-D — Input handoffs, track/power leads, 28 September.** East E4 geometry is already verified. West W2 survey is verified at end D4; it cannot be released earlier. Power as-built input P3 is ready end D4. Producing and jointly reviewing the common P3 isolation drawing occupies D5, using both verified geometries and the power input; a separate design team does this. Track lead Talia Reed, power lead Ben Cole and operator Mara Finn must accept the drawing at end D5. It defines independent zone isolation, so one zone may be live while the other undergoes de-energised work. East/West G, R and P tests use one shared QA crew, and each zone’s P test must follow that zone’s valid G and R evidence plus the accepted P3 drawing. The drawing review can run in parallel with G/R testing.

**13-E — Conflicting interface requests, 29 September.** Ben’s work order says: “No zone energisation until Mara provides final passenger-service route acceptance.” Mara replies: “Final route acceptance follows dynamic and cross-zone testing; I will not sign it beforehand.” Chen’s request says each route must already be energised and familiarised when its own dynamic test starts. These requests are not amendments to the charter below. Ravi has not yet named the person assembling the temporary test-authority pack.

**13-F — Joint commissioning charter, signed by all four leads, 20 September; binding.** There are two distinct permissions. A **temporary test authority (TTA)** permits energisation and testing, not passenger service. Mara may issue it for a zone at end of day once that zone has valid G/R/P evidence and the accepted common P3 drawing. Ben then authorises a one-day energisation activity on the next working day. One power commissioning crew serves the two zones; zone energisations cannot overlap. Following successful energisation, a one-day operator familiarisation is required. Dynamic testing follows familiarisation and requires the shared specialist test team plus one qualified operator crew. After both zone dynamic tests, one full-day cross-zone integration test is required. Final record assembly and joint review take one further day, using all zone/cross-zone results and the locked target configuration. Mara alone accepts the final record and authorises passenger service. This charter is the complete fictional operating rule; TTA is an authorised stage, not a safety waiver.

**13-G — Resources/windows, programme controls, 29 September.** One QA crew performs any required G/R/P tests. One power crew performs energisation. One existing qualified operator crew can perform either familiarisation or attend one zone dynamic test on a day, never both. A second fully qualified operator crew is offered for D8–D10 for £8,000 total; it may perform familiarisation or attend dynamic testing without additional induction. All other named people are available when required. Dynamic specialists sell an inseparable two-day slot: both zones must be tested on consecutive days in either order. Existing booking D9–D10; next available D14–D15, costing an additional £12,000 if rebooked. The two bookings cannot be split to test one zone in each. Cross-zone specialists are available D11 or D16 only. Record-assembly staff are available after either window. Test success is prospective and cannot be guaranteed.

**13-H — Authority/deadline, sponsor, 29 September.** Ravi may appoint the temporary-pack coordinator and order the second operator crew within his £10,000 delegation by noon 30 September. Rebooking at £12,000 and changing the advertised service date need sponsor approval. He cannot change fingerprints, waive tests, create passenger-service permission or command the operator to accept evidence not yet produced. A plan may propose appointments/sign-offs but must distinguish those from approvals already given.

### Browser deliverable and completion conditions

Provide an interface register linked to a day-by-day resource view, an evidence-carryover table and a concise decision. Selecting a test must show the target identifiers, prior record and reuse/retest reason; selecting an interface must show its actual authority and acceptance evidence. Switching the extra operator crew on/off must recalculate a feasible sequence, the booked-window consequence, service date and additional cost. An apparent cycle must disappear only through the authorised TTA distinction, not by deleting an acceptance condition.

The page must work in the supplied browser/runtime; a download button or file preview alone is insufficient. Include a clear “Return to gallery” link using the shared shell route, or ../index.html if no route is supplied. Required controls must change the dependent results, not just their appearance. Original evidence and the initial dated position must remain recoverable; hypothetical changes do not create approvals or alter source records. Optional exports are secondary.