Mossbank festival • circulation candidate for Ria Bell

Keep Saturday. Amend the authority before signing.

At 13:00 on Friday 9 July 2027, the headliner is held, not booked. Use today’s possible 16:00 board decision to consider the sponsor-funded deposit route. It can work, but H8 currently prohibits signing before council permission. The festival has £0 unallocated base cash; Sam must not pay the £2,000 deposit from its bank. 20-A20-B20-D20-F20-G

Recorded position • 9 July 2027, 13:00 localSaturday 18 September remains the approved date, subject to permission. Sponsor agreement unsigned by the festival; artist contract unsigned; artist deposit unpaid; council permission unissued. This position stays visible in every hypothetical view. 20-C20-E20-F20-G
Monday 12 July, 10:00Artist hold / direct deposit deadline is the first commercial cutoff; sponsor offer ends at 11:00. Aim for paired completion by 10:00. 20-F20-G
Permission: no earlier than 20 JulyReceipt of V1 was not permission. Paid tickets cannot launch on 15 July. 20-A20-E
Two real staffing gaps14:00–15:00: short one person and one lead. 16:00–18:00: short one person. Hana’s confirmation would close both. 20-H

All controls are ephemeral planning views. Nothing is sent, signed, assigned, saved as an approval or booked. Reload or reset restores the baseline.

Corrected decision and action record

“Agreed” can describe a completed submission or valid conditional resolution; it does not imply permission. Filters retain the prerequisite records of matching entries, marked dependency context. Owners act only within the authority stated.

Position as at 13:00 • proposals are explicitly separate
ReferenceStatusDecision / controlled actionOwner, timing and authorityDependencies / evidence

P4 correction log

P4 dated 6 July is a working plan, not an approval. Retain it as history, but replace these claims in the circulation version. Preserve the completed V1 submission and the original reporting deadlines; add the changed work explicitly. 20-I

P4 claim / instructionCorrect position for circulationEvidence
Sunday 19 SeptemberSaturday 18 September, subject to council permission. The draft Sunday minute was corrected at 18:20 on 8 July. Raj’s later suggestion is only a proposal. A Sunday move would need a new venue request, board date approval, availability and Sam-signed variations; the quoted £900 is not a commitment.20-A, 20-C, 20-E, 20-I
Headliner “booked”No contract or deposit. Provisional hold to Monday 10:00; H8 is valid conditional authority, not a booking. The new route needs an explicit amendment.20-D, 20-F, 20-G
£8,000 sponsorship received£0 received by festival. An authorised signed sponsor offer is not the festival’s countersigned agreement. Proposed £8,000 comprises £2,000 direct to artist plus £6,000 to festival, not £8,000 into bank.20-B, 20-G
£6,800 “total committed spend”Signed base contracts total £10,000; £3,200 paid and £6,800 still payable. Essential uncontracted quotes add £4,000 to the funding requirement, not to signed commitments.20-B
Twelve stewards confirmedTen people confirm only their stated intervals; Hana tentative, Kai no reply. Effective counts are 6 / 7 / 8 / 7, with only one lead 14:00–15:00. Ann’s control-tent duty is agreed and removes her for that hour.20-H
Route plan closedA1’s V1 submission is genuinely complete. Open successor A1R: revised route tied to council layout V2, including moved emergency entrance, due 16 July noon. Do not erase A1’s completion.20-C, 20-E
Council permission 14 JulyNo permission yet. Earliest decision 20 July, with no guarantee of approval or a decision that day. Saturday reservation is not permission.20-E
Paid tickets 15 JulyBlocked until council event permission is actually issued. Replace the launch date with this gate.20-A, 20-E
Sam to pay artist £2,000 from bank nowDo not issue payment. H8’s two conditions are unfulfilled and every pound in bank is needed for the base. The offered alternative is a sponsor-funded direct deposit after amended authority and matched agreements.20-A, 20-B, 20-D, 20-G

The bank is fully allocated to the base

Current reconciliation below is fixed. A hold is not a contract; a quotation is not a signed obligation; direct sponsor payment never passes through festival cash. 20-B20-F20-G

Actual base position • GBP, tax ignored
ItemSigned contractual costFestival paidFuture signed paymentsEssential quote reserve
Saturday stage£6,000£2,000£4,000—
Security£2,400£1,200£1,200—
Welfare£1,600£0£1,600—
Toilets • uncontracted£0£0£0£2,400
First aid • uncontracted£0£0£0£1,600
Total£10,000£3,200£6,800£4,000
£14,000 originally received − £3,200 already paid = £10,800 current bank £10,800 bank − £6,800 unpaid signed costs − £4,000 essential quotes = £0 free base cash Total base cost, if essentials contracted at quote = £10,000 + £4,000 = £14,000

Supplier payment dates and cancellation/refund terms are not supplied. Keep the full £10,800 allocated; do not infer spare cash from missing due dates. £900 Sunday stage uplift remains an unaccepted, availability-dependent indication. No extra in-kind service is evidenced. 20-B20-I

Actual facts never change: unsigned festival sponsorship; unsigned artist contract; £0 artist deposit paid; £0 sponsorship received; permission unissued. Scenarios below are calculations, not recorded decisions.

Accounting assumptions and the refusal boundary

The £2,000 direct deposit is part of the £8,000 sponsorship and part of the £5,000 artist price: never add it to either total again. With a permitted event, full sponsorship and the quoted base, total economic funding is £22,000 against £19,000 costs, leaving £3,000 before any new cost. Festival cash receipts total £20,000 (£14,000 + £6,000), and festival-funded costs total £17,000 (£14,000 + £3,000). 20-B20-F20-G

The sponsor offers to bear the deposit loss on council refusal without recourse; the agent must acknowledge it. That specific protection does not establish all cancellation terms. The offer does not say whether the festival must return any of the remaining £6,000 on refusal or other cancellation. Sam must make that explicit in the paired documents. Until evidenced, a refusal view recognises no free sponsorship surplus; it also assumes no base refunds. This is a conservative planning assumption, not an invented refund obligation.

Coverage means people in the right role, at every interval

Six stewards are required 10:00–14:00, eight 14:00–18:00, including two qualified leads throughout. Ann, Gus and Hana are qualified. Leads count within the total, not in addition. Split at 14:00, 15:00 and 16:00 to expose the changes. 20-H

Recorded baseline: 10:00–14:00 = 6 people / 2 leads; 14:00–15:00 = 7 / 1; 15:00–16:00 = 8 / 2; 16:00–18:00 = 7 / 2. Hana and Kai contribute zero confirmed coverage.

Changing a box does not contact anyone or reassign them. Ann’s existing control-tent duty is accepted, so it cannot simply be ignored. Lee and Ria are not spare stewards; medical contractor staff cannot substitute as leads. 20-H

Proposed route for Lee: seek Hana’s explicit confirmation first; it alone closes both gaps. Proposed checkpoint: Monday 12 July 09:00. If unavailable, secure a qualified lead for 14:00–15:00 plus a steward for 16:00–18:00 (one qualified person covering 14:00–18:00 can satisfy both). Another possible route is Kai’s confirmation plus an agreed, safely covered change to Ann’s duty. Kai alone fixes headcount but leaves the lead gap. Any paid solution needs a separately funded and authorised proposal. Retain A3’s actual 14 July reporting deadline.
Proposed • not a recorded resolution

The 16:00 decision Ria can put to the board

The existing H8 resolution is valid: Ria and Sam affirmatively approved its precise conditions; Raj’s silence does not invalidate it. It authorises preparation, but neither required condition is fulfilled. The sponsor’s revised offer does not amend H8. Waiting for permission under H8 cannot meet the Monday artist hold, because permission is no earlier than 20 July. 20-A20-D20-E20-G

Proposed written amendment H9 — exact wording

“For the festival on Saturday 18 September, the board amends H8 to allow Sam Dey to sign the £8,000 sponsor agreement and the conditional £5,000 artist contract before council event permission, as a coordinated transaction, provided the final documents implement all the following terms:

  1. The sponsor pays £2,000 directly to the artist’s agent by 12 July 10:00, credited within the £8,000 sponsorship and the £5,000 artist price. No festival bank money funds this deposit.
  2. The sponsor bears that £2,000 loss if council permission is refused, without recourse to the festival, and the artist’s agent expressly acknowledges the payer and allocation of loss.
  3. The remaining £6,000 sponsorship is payable to the festival on 15 July once both agreements are signed. The documents state how that money is treated on refusal or cancellation; no undisclosed festival liability or additional non-cancellable cost is accepted.
  4. The artist’s remaining £3,000 is due only after council event permission; none is due if permission is refused. Total artist fee is capped at £5,000. Ordinary unconditional booking terms are not authorised.
  5. Sam approves matching execution/effectiveness arrangements with both counterparties, so neither the sponsor’s headliner-contract condition nor the artist’s funding arrangement is left unmatched. Dana coordinates completion within the artist deadline and before the sponsor offer expires.

If these terms cannot be completed, Sam must not commit or use the protected base cash; Dana may seek a written extension, but absent an extension the hold lapses. This amendment does not change the event date, grant council permission or authorise paid ticket sales. All other H8/governance controls remain in force.”

Adoption test: record two affirmative written approvals including Sam (Ria and Sam are available at 16:00). An agenda item, circulation, silence or one affirmative response does not adopt H9. Then Sam must sign the contracts; a board vote alone does not execute either agreement. 20-A20-G

Separate proposed base-cost approval: to avoid assuming authority that is absent from the pack, also record authority for Sam to contract toilets up to £2,400 and first aid up to £1,600 within the existing £4,000 ring-fenced base provision. Dana should secure the quoted services or written quote extensions before Monday noon. These are funded essential quotes, not already signed contracts. Board approval for additions above £1,000 and Sam’s supplier signature rules still apply. 20-A20-B

What still needs evidence, not a fresh debate

Sam and Dana need the adopted amendment, countersigned sponsor agreement, conditional artist contract, agent’s no-recourse acknowledgement, direct-deposit receipt and explicit treatment of the £6,000 on refusal. The counterparty execution mechanism and the £6,000 refusal/cancellation term are proposed completion safeguards, not terms already accepted by the agent/sponsor. If those cannot be agreed within the offer, seek extension or return a specific changed term for board consideration; do not call the route complete.

The next ten days, in dependency order

Fixed dates come from the records. Suggested internal targets are labelled proposed. This page authorises no outbound messages, bookings or payments.

  1. Friday 9 July, 13:00 — corrected circulation candidateRia owns the accurate record: use M7/D1 for Saturday, H8 for existing conditional authority, V2 as the current layout basis and this correction log to replace P4 assertions. Preparation only; this page has not circulated it. 20-C20-D20-E
  2. Friday 9 July, 16:00 — proposed H9 / essential-cost decisionsRia presents the exact amendment and separate base-cost authority. Sam participates in both written approvals; two affirmative approvals including him are required. Dana/Sam may prepare and negotiate in advance, but may sign only when the relevant authority and documentary conditions exist. 20-A20-G
  3. Monday 12 July, proposed 09:00 staffing checkpointLee checks Hana’s employer release and attendance; if absent, activates a documented qualified-cover route. This early checkpoint is proposed, while A3’s confirmed-coverage report remains due 14 July. 20-C20-H
  4. Monday 12 July, 10:00 — artist hold and deposit cutoff; 11:00 — sponsor offer expiryOnly after adopted H9 and matched terms: Sam signs both contracts; Dana coordinates with sponsor/agent for direct payment and agent acknowledgement. Proposed operational target is to complete the whole pair by 10:00, not to use the later 11:00 deadline as extra artist time. Resolve circular signing through mutually accepted paired execution. If H9 is declined or the terms/receipt fail, no booking or festival deposit: seek a written extension or let the hold lapse and retain a base-event/headliner-alternative option. Extension or alternative is not assumed. 20-F20-G
  5. Monday 12 July, 12:00 — essential quotes expireDana coordinates toilets/first aid; Sam signs only with appropriate authority, preserving £4,000 funding. If not signed by noon, obtain extensions or refreshed quotes; do not treat the old prices as indefinitely firm. Keep the base provision intact through the headliner decision. 20-A20-B
  6. Wednesday 14 July — retained A2 and A3 reporting datesSam reports sponsor agreement outcome; its original “complete by 14 July” date is too late for the live offer, so the proposed operational target above supersedes it for execution. Lee reports confirmed intervals and leads, or the exact outstanding gaps. A3 is a reporting promise, not a promise of a filled roster. 20-C
  7. Thursday 15 July — £6,000 due only if agreements are signedSam verifies actual bank receipt and records it separately from the £2,000 direct deposit. If late, escalate with sponsor/agent immediately before the earliest permission date; no protected base funds may be treated as available. The offered artist balance is triggered by permission, not by cash receipt, so late sponsorship leaves a real payment risk unless resolved. Do not silently assume a right to delay the artist balance. 20-F20-G
  8. Friday 16 July, 12:00 — revised route tied to V2 dueDana submits the revised route with the moved emergency entrance and retains submission/receipt evidence. A1 remains complete; A1R is the open successor. Receipt still does not grant permission. 20-E
  9. Tuesday 20 July — earliest council decision, not a promised decisionDana obtains the written outcome when issued. If granted, Sam checks the executed artist terms and pays the £3,000 balance when due; ticket sales can pass their permission gate. If delayed, keep ticket sales blocked and check any hold/contract implications without inventing new deadlines. If refused, no artist balance is due under the offered terms and the sponsor bears the deposit loss if the agreed acknowledgement is in place; apply the signed £6,000 treatment and review base exposure against actual contracts. 20-A20-E20-F20-G

Evidence and document control

The original fictional records are reproduced below without changing their claims. Authority comes from governance 20-A, approved minutes M7 and valid conditional H8; P4 and the corrected Sunday draft are not approved decisions. Council layout V2 replaces V1 as the layout basis for the next route submission; it does not erase the submitted V1 or issue permission.

DocumentUse nowRetain / successor
M7 • approved 7 JulyAuthoritative D1 and original A1–A3Retain; proposed tighter A2 execution target explicitly separate
H8 • valid 8 JulyCurrent conditional headliner authorityRetain unless formally amended; H9 above is only a proposal
Route V1 • sent 8 July 10:00Evidence A1 completedRetain receipt; new route tied to layout V2 required
Council layout V2 • 8 July 16:00Current emergency-entrance / route basisDana’s revised route due 16 July noon; no new version claimed as issued
Sunday draft • 8 July 18:00Superseded sentence, corrected at 18:20Use Saturday D1; Raj’s 9 July comment remains a proposal
P4 • unapproved 6 JulyHistorical working plan onlyApply explicit correction log; no silent overwrite or approval by publication
20-A — Governance, signed 6 July.
Board members Ria (chair), Sam Dey (treasurer), Raj Kent. A written resolution needs two affirmative approvals including Sam; silence is not approval. Board approval is required for event-date changes and additions above £1,000. Every supplier/sponsor contract also needs Sam's signature. Lee Moss owns volunteer assignment; Dana Fox owns supplier/permit coordination. A conditional board resolution permits preparation/negotiation but **no contract signature until its stated conditions are fulfilled**, unless the board formally amends it. Only the council issues event permission. Paid tickets cannot be sold before that permission. Publication of a plan does not approve it.
20-B — Cash and obligations, Sam,9 July 09:00.
Cash originally received £14,000, all unrestricted. Signed Saturday-stage contract £6,000, of which £2,000 paid; signed security £2,400, £1,200 paid; signed welfare £1,600, nothing paid. The current bank balance is £10,800. Essential uncontracted costs: toilets £2,400 and first-aid provision £1,600. These are firm quotes through Monday 12 July 12:00 and must remain funded. No other base cost. No borrowing, speculative ticket receipts or unconfirmed sponsorship may cover non-cancellable commitments. Plan P4 calls £6,800 “total committed spend” and counts £8,000 sponsorship as cash already received.
20-C — Approved minutes M7, Ria+Sam,7 July 17:00.
D1: retain Saturday 18 September subject to council event permission. Sunday discussed only. A1:Dana to submit route plan V1 by 8 July; A2:Sam to complete sponsor agreement by 14 July. A3:Lee to report confirmed steward names/coverage by 14 July—not a promise that all slots are filled. The board asks for a headliner option; no approval then.
20-D — Written resolution H8,8 July 12:00–12:10.
Ria: “Approve headliner addition up to £5,000, conditional on a signed £8,000 sponsor agreement and council event permission; Sam to sign only once both are evidenced.” Sam: “Agreed to precisely those conditions.” Raj has not replied. This is a valid conditional resolution under 20-A. No conditions are yet fulfilled.
20-E — Council/document trail,8–9 July.
At 8 July 10:00 Dana sent route plan V1; council acknowledged receipt. At 8 July 16:00 council issued site layout V2, moving the emergency entrance, and required a revised route tied to V2 by 16 July 12:00. Council officer Jo Vale on 9 July 09:30: “We will decide permission no earlier than 20 July. Saturday 18 September remains reserved; Sunday requires a new venue request. Acknowledgement is not permission.” Task log A1 was marked closed on 8 July 11:00. A draft minute on 8 July 18:00 says Sunday agreed; Ria corrected that sentence by email at 18:20, referring to D1. Raj's 9 July 12:50 suggestion “Sunday may still work” is a proposal, not a vote/resolution.
20-F — Artist's agent, authorised offer 9 July 10:30.
Headliner fee £5,000. A provisional hold expires Monday 12 July 10:00. Offer of a conditional contract:£2,000 non-refundable deposit by that time, with £3,000 balance due only after council permission. If council refuses, no balance is due, but the deposit is lost. No contract or deposit exists yet. The agent will accept the deposit directly from the sponsor and acknowledge which party bears the loss. Ordinary unconditional booking terms have not been agreed.
20-G — Sponsor's authorised commercial director,9 July 11:20.
“Our £8,000 offer remains conditional on a signed headliner contract. Revised route: we pay £2,000 directly to the agent as part of that £8,000, and pay the remaining £6,000 to the festival on 15 July once its sponsor agreement and conditional artist contract are signed. We bear the £2,000 deposit loss if permission is refused, without recourse to the festival; the agent must acknowledge this. This offer expires 12 July 11:00.” This is an offer signed by the sponsor, not a festival countersigned agreement. It does not change H8. Sam is available with Ria for a possible board decision at 16:00 today; no decision is pre-recorded.
20-H — Steward rule and roster, Lee,8 July 20:00.
Need six stewards continuously 10:00–14:00 and eight continuously 14:00–18:00, including two qualified leads throughout. Staff in other roles do not count simultaneously. Names/availability below are the complete evidence; “yes” confirms only the stated interval. Ann and Gus are qualified leads; Hana is also qualified; others are stewards only. Lee and Ria have other duties and are not available as spare stewards.

| Person | Available interval | Confirmed? |
|---|---|---|
| Ann |10:00–18:00 | Yes, except agreed control-tent duty 14:00–15:00 |
| Ben |10:00–14:00 | Yes |
| Cara |10:00–18:00 | Yes |
| Dev |14:00–18:00 | Yes |
| Eli |10:00–14:00 | Yes |
| Fran |14:00–18:00 | Yes |
| Gus |10:00–18:00 | Yes |
| Hana |14:00–18:00 | Tentative; employer release unconfirmed |
| Ivo |10:00–16:00 | Yes |
| Jo |14:00–18:00 | Yes |
| Kai |10:00–18:00 | No reply |
| Luz |14:00–18:00 | Yes |

Ann's control-tent assignment was agreed by Lee and Ann on 8 July; it is not an unaccepted request. Medical contractor staff cannot replace steward leads under this exercise's staffing rule.
20-I — Working plan P4, Dana,6 July; not approved.
Sunday 19 September; headline act “booked”; sponsor £8,000 received; twelve stewards confirmed for the event; route plan closed; council permission 14 July; paid tickets 15 July. Sam to “pay artist £2,000 from bank now”. Stage supplier says a Sunday move, if available, adds £900; Saturday contract has not changed. No one has instructed a Sunday variation or the artist payment.
Read the complete supplied case · BPB2-20
# BPB2-20 — Community festival — turn discussion into controlled action

Suite BPB2 v0.3-pilot; Foray 247, third essai.

### Scenario
Mossbank's festival committee has a plan that confuses conditional decisions, contracts, cash and volunteer names. At 13:00 on Friday 9 July 2027 chair Ria Bell must circulate an accurate record for that afternoon's call. New sponsorship terms may unlock a headline act, but the original authorisation does not cover the proposed route and several Monday deadlines interact. The volunteer roster looks full until actual intervals and roles are checked. Ria needs a controlled near-term plan that people can act on without inventing commitments.

### Exact task prompt

Produce one usable in-browser answer page for the named practitioner, using the supplied fictional evidence. Keep observed facts, forecasts, assumptions and proposed decisions distinguishable, and cite source IDs beside material claims. No external research or real-world certification is required.
Produce Ria's corrected decision/action record and near-term plan as at 13:00 on 9 July. Reconcile the current authority, event date, commercial commitments, available/conditional money, document versions and steward coverage. Preserve completed work while reopening or superseding what later evidence changes. Show the viable next-decision route, its dependencies/deadlines and the exact proposed board decision needed; do not write that it has occurred. Distinguish contractual cost, cash already paid, future payments, holds and in-kind/direct payments. Resolve what the records permit and make the remaining uncertainties actionable, rather than referring every inconsistency back to the committee.

### Supplied records
All dates 2027, all times local. Event is planned for September. Money GBP; tax ignored. No outbound messages or bookings are authorised by this task.

**20-A — Governance, signed 6 July.** Board members Ria (chair), Sam Dey (treasurer), Raj Kent. A written resolution needs two affirmative approvals including Sam; silence is not approval. Board approval is required for event-date changes and additions above £1,000. Every supplier/sponsor contract also needs Sam's signature. Lee Moss owns volunteer assignment; Dana Fox owns supplier/permit coordination. A conditional board resolution permits preparation/negotiation but **no contract signature until its stated conditions are fulfilled**, unless the board formally amends it. Only the council issues event permission. Paid tickets cannot be sold before that permission. Publication of a plan does not approve it.

**20-B — Cash and obligations, Sam,9 July 09:00.** Cash originally received £14,000, all unrestricted. Signed Saturday-stage contract £6,000, of which £2,000 paid; signed security £2,400, £1,200 paid; signed welfare £1,600, nothing paid. The current bank balance is £10,800. Essential uncontracted costs: toilets £2,400 and first-aid provision £1,600. These are firm quotes through Monday 12 July 12:00 and must remain funded. No other base cost. No borrowing, speculative ticket receipts or unconfirmed sponsorship may cover non-cancellable commitments. Plan P4 calls £6,800 “total committed spend” and counts £8,000 sponsorship as cash already received.

**20-C — Approved minutes M7, Ria+Sam,7 July 17:00.** D1: retain Saturday 18 September subject to council event permission. Sunday discussed only. A1:Dana to submit route plan V1 by 8 July; A2:Sam to complete sponsor agreement by 14 July. A3:Lee to report confirmed steward names/coverage by 14 July—not a promise that all slots are filled. The board asks for a headliner option; no approval then.

**20-D — Written resolution H8,8 July 12:00–12:10.** Ria: “Approve headliner addition up to £5,000, conditional on a signed £8,000 sponsor agreement and council event permission; Sam to sign only once both are evidenced.” Sam: “Agreed to precisely those conditions.” Raj has not replied. This is a valid conditional resolution under 20-A. No conditions are yet fulfilled.

**20-E — Council/document trail,8–9 July.** At 8 July 10:00 Dana sent route plan V1; council acknowledged receipt. At 8 July 16:00 council issued site layout V2, moving the emergency entrance, and required a revised route tied to V2 by 16 July 12:00. Council officer Jo Vale on 9 July 09:30: “We will decide permission no earlier than 20 July. Saturday 18 September remains reserved; Sunday requires a new venue request. Acknowledgement is not permission.” Task log A1 was marked closed on 8 July 11:00. A draft minute on 8 July 18:00 says Sunday agreed; Ria corrected that sentence by email at 18:20, referring to D1. Raj's 9 July 12:50 suggestion “Sunday may still work” is a proposal, not a vote/resolution.

**20-F — Artist's agent, authorised offer 9 July 10:30.** Headliner fee £5,000. A provisional hold expires Monday 12 July 10:00. Offer of a conditional contract:£2,000 non-refundable deposit by that time, with £3,000 balance due only after council permission. If council refuses, no balance is due, but the deposit is lost. No contract or deposit exists yet. The agent will accept the deposit directly from the sponsor and acknowledge which party bears the loss. Ordinary unconditional booking terms have not been agreed.

**20-G — Sponsor's authorised commercial director,9 July 11:20.** “Our £8,000 offer remains conditional on a signed headliner contract. Revised route: we pay £2,000 directly to the agent as part of that £8,000, and pay the remaining £6,000 to the festival on 15 July once its sponsor agreement and conditional artist contract are signed. We bear the £2,000 deposit loss if permission is refused, without recourse to the festival; the agent must acknowledge this. This offer expires 12 July 11:00.” This is an offer signed by the sponsor, not a festival countersigned agreement. It does not change H8. Sam is available with Ria for a possible board decision at 16:00 today; no decision is pre-recorded.

**20-H — Steward rule and roster, Lee,8 July 20:00.** Need six stewards continuously 10:00–14:00 and eight continuously 14:00–18:00, including two qualified leads throughout. Staff in other roles do not count simultaneously. Names/availability below are the complete evidence; “yes” confirms only the stated interval. Ann and Gus are qualified leads; Hana is also qualified; others are stewards only. Lee and Ria have other duties and are not available as spare stewards.

| Person | Available interval | Confirmed? |
|---|---|---|
| Ann |10:00–18:00 | Yes, except agreed control-tent duty 14:00–15:00 |
| Ben |10:00–14:00 | Yes |
| Cara |10:00–18:00 | Yes |
| Dev |14:00–18:00 | Yes |
| Eli |10:00–14:00 | Yes |
| Fran |14:00–18:00 | Yes |
| Gus |10:00–18:00 | Yes |
| Hana |14:00–18:00 | Tentative; employer release unconfirmed |
| Ivo |10:00–16:00 | Yes |
| Jo |14:00–18:00 | Yes |
| Kai |10:00–18:00 | No reply |
| Luz |14:00–18:00 | Yes |

Ann's control-tent assignment was agreed by Lee and Ann on 8 July; it is not an unaccepted request. Medical contractor staff cannot replace steward leads under this exercise's staffing rule.

**20-I — Working plan P4, Dana,6 July; not approved.** Sunday 19 September; headline act “booked”; sponsor £8,000 received; twelve stewards confirmed for the event; route plan closed; council permission 14 July; paid tickets 15 July. Sam to “pay artist £2,000 from bank now”. Stage supplier says a Sunday move, if available, adds £900; Saturday contract has not changed. No one has instructed a Sunday variation or the artist payment.

### Browser deliverable and completion conditions
Provide a current-status summary, source-linked decision/action register, explicit P4 correction log, cash/commitment bridge and a short dependency-based plan through 20 July. Show coverage by time interval and role, not name count. Filter by “agreed”, “conditional”, “proposed”, “awaiting evidence” and “superseded/reopened”; filtering must preserve the relevant dependencies. Any hypothetical sponsorship-route view must keep the actual unsigned state visible. Proposed new actions/deadlines need clear labels, owners and authority.

The page must work in the supplied browser/runtime; a download button or file preview alone is insufficient. Include a clear “Return to gallery” link using the shared shell route, or ../index.html if no route is supplied. Required controls must change the dependent results, not just their appearance. Original evidence and the initial dated position must remain recoverable; hypothetical changes do not create approvals or alter source records. Optional exports are secondary.