For Arun Vale / proposed negotiating position · 18 January 2027

Buy a stable six-week service.

Recommend P + R: Friday physical expansion and the report waiver, £2,700 committed for all six weeks. It schedules all 120 weekly appointments, preserves physical-preference cohorts, and reserves eight optional language-video slots—four in each language. The £900 premium buys one repeated template and more booking headroom. Both packages remain conditional on approvals and individual booking acceptance. [12-A–H]

The agreement to put on the table

Ask for a fixed Friday facilities commitment, the named admin-report substitution, and the same clinical roles and windows every week. Keep Wednesday below the review trigger by holding remote appointments at 20; a 21st remote appointment is not supported by this package. [12-E,F]

All 120 are planned capacity, not accepted bookings or completed care. Neither Jo's advocacy nor an on-screen scenario change creates consent, approval or a commitment. [12-B,G,H]

Negotiating reserve

Offer T + V + R at £1,800 if the £900 premium is rejected. It preserves the same eight language-video opportunities, but needs a middle-week template, Wednesday reviews and a £900 replacement-teaching obligation after the pilot. [12-E–G]

£300 authority headroom for P + R; £1,200 for T + V + R. Headroom is not an unlisted resource offer. Neither package is signed. [12-A,F,G]

Two complete proposals • same demand, different operating burden
DecisionP + R · recommendedT + V + R · lower cash commitment
Six-week commitment£1,800: V £150 × 6 + T £900 committed now
Patient access each week87 physical / 15 telephone / 18 video in W1–2,5–6; 84 / 18 / 18 in W3–4; 8 language video throughout
ContinuityTwo templates; Wednesday language-video consultant role changes to two ST telephone appointments in middle weeks, alongside the separate 60-minute review
Weekly admin headroom1 minute in W1–2; 35 in W3–4; 41 in W5–6
Displaced work / capacityWednesday −60 practitioner minutes for teaching cover; Thursday −120 room minutes for video conversion; teaching replacement required; duplicate report suspended

Calculated from 12-B–F. Continuity here means repeatable cohort windows and clinician roles, not a promise of a named clinician or the same patients attending six times. More remote activity is not assumed to mean better care. [12-B,G]

Inspect the operating template

Select a week to see its actual resource limits. Withdraw one concession to test the unchanged appointments against the reduced package. Nothing reallocates silently.

Scenario workspace only: no records are written. Reload or reset restores P + R, W1, with no withdrawal. All figures remain proposed; the original evidence and dated position stay below.

All six weeks under the selected package / withdrawal
WeekTemplateAppointmentsRemoteAdmin used / usableResource result

Every session, every resource pool

Used / available minutes. Amber = exactly full; red = exceeded. Zero / zero is unused, unavailable capacity. Admin is checked once per week, below. [12-C–F]

SessionConsultantPractitionerNurseExam roomsVideo boothsInterpreter AInterpreter B
Appointment allocations and clinician roles

Counts are weekly slots. p = physical; t = telephone; v = video. Nurse, booking, rooms, booths and interpreters are additional to the assigned clinician. Offer T changes Wednesday W, not Tuesday T. [12-A–F]

Cohort reconciliation and mode choices
CohortDemandPlannedPhysicalTelephoneVideoWindows / roles

All rows checked against the unchanged planning register, including physical-only new, complex and preference cohorts. No unlisted combination, overtime or reclassification is used. [12-A–C]

What changes in the lower-cost middle weeks?

For W3–4 only, compared with its ordinary template: SP physical slots change from A7 / T5 / H1 / F5 to A5 / T6 / W1 / H1 / F5. ST changes from A(1 physical + 5 telephone), T1 physical, H1 physical, W5 telephone, F5 telephone to A9 telephone, W4 telephone, F5 telephone. Two Wednesday ST telephone slots use a consultant; the other two use a practitioner. All four Wednesday BV video slots use practitioners, replacing the ordinary split of one consultant and three practitioners. All remaining slots stay as listed. [calculation from 12-B–F]

That moves remote demand from 33 to 36, keeps the separate 60-minute Wednesday consultant review, and fits Thursday's additional −20 practitioner / −20 room minutes. The middle template would consume 1,090 admin minutes with onboarding, so it is not used in W1–2 (limit 1,085). Restore the ordinary template in W5. These are templates for different weekly patients, not assumed repeat attenders. [12-B,E]

Eight language-video offers, not eight consents

Proposed allocation

Both packages reserve AV video: 2 Tuesday + 2 Thursday; BV video: 4 Wednesday. This meets Jo's requested eight opportunities and at least three in each language. The six AP and six BP physical-preference slots remain physical. The remaining two AV and two BV slots are physical. [12-B,G; calculated templates]

There are twelve patients in the video-option cohorts each week and eight video slots; four potential video options are not offered in these templates. Jo cannot allocate on behalf of patients. Do not turn this into a minimum uptake target or force the four remaining patients to accept a mode. [12-B,G,H]

Choice rule to agree with Dr Shah and Jo

Offer within the recorded language, clinical mode and session windows. Use Dr Shah's documented clinical priority first, then stated access/travel difficulty and actual available windows; use a transparent rotating tie-break among equally placed requests. Do not favour the easiest booking. These are proposed terms, not an existing priority policy. [12-G,H]

Explain the option accessibly, confirm individual acceptance and any communication support before booking. A declined video offer triggers a capacity check for a permitted physical slot, not automatic conversion. Record preferred modes not offered and any unserved request in the existing booking record / digest. Reconcile weekly opportunity and acceptance counts separately. [12-B,H]

PLANNED120 slots / 8 language-video slotsProposal in this page; eight planned offer opportunities, not offers already issued.
OFFERED & ACCEPTEDNot recordedTrack offers issued and patient acceptances as separate actual counts. Planning acceptability is not booking consent.
DELIVEREDNo delivery evidence yetAppointments delivered are a third measure; no outcomes are forecast as facts. [12-B,G,H]

Terms, concessions and approval register

The negotiation is on 18 January 2027; pilot 25 January–5 March. Dates below are proposed deadlines. No combined package or conditional offer has been accepted. Only Arun can authorise start and commitments within £3,000; only the board can authorise overspending or continuation. T + P totals £3,600 and is outside his authority; V and P cannot coexist. [12-A,F–H]

Term to acceptNamed decision ownerProposed deadline / evidence of acceptanceCurrent state
P · recommended
Friday +120 consultant, +60 nurse, +240 room minutes; −60 practitioner; original 30 booth minutes unavailable. Buy all six weeks: £2,700. Fixed facilities team; no V.
Dr Shah, Mara Finn and Arun18 Jan package selection; written six-week staffing/facilities confirmation by 20 JanConditional offer only [12-F]
R · both packages
Suspend the optional duplicate weekly narrative utilisation return. Retain an existing-data digest, max 15 minutes/week, yielding net +85 booking minutes. Include planned/offered/accepted/delivered counts, choice shortfalls, unserved requests and session workload; no second survey.
Evan Cho signs waiver; Elin Price accepts the 15-minute workflow18 Jan principle; named report and sample digest by 20 JanConditional; 1,085 usable minutes only after approval [12-F–H]
T · alternative only
Wednesday +90 consultant, −60 practitioner for teaching cover. £900 replacement teaching committed now, even though paid later. Rae to confirm content, hours, attendees and actual replacement date.
Rae Holt and ArunSign 18 Jan; dated plan by 20 Jan. Propose replacement during week commencing 8 Mar, subject to Rae's confirmation.Conditional; replacement date is a proposal [12-F,G]
V · alternative only
Thursday +120 booth / −120 room minutes; £150 × 6 = £900. Keep one facilities configuration for all six weeks; no P.
Mara Finn and ArunWritten facilities commitment by 20 JanConditional offer only [12-F,G]
Clinical arrangement
Approve exact templates, whole-appointment clinician roles, prioritisation rule and explicit Thursday vaccination loss. Preserve the 60-minute Wednesday review whenever remote count exceeds 20.
Dr Shah18 Jan selection; complete template sign-off by 20 JanProposed; no review exemption sought [12-C,E,G,H]
Booking and start
Elin validates each week including onboarding and actual accepted choices; confirm interpreters separately by language, authorised practitioners, nurse cover and recorded windows. Arun authorises the total commitment and launch only after all required acceptances.
Elin and resource managers; Arun; each patient accepts their own bookingReady-to-launch decision by noon 22 Jan, before promises depend on unsupported resourcesNot approved; consent remains individual [12-B,D,H]

Negotiation decisions to record

  1. Arun / Mara / Dr Shah: accept the £900 premium for stable P + R, or explicitly choose the more constrained T + V + R templates. No mixed P + V package.
  2. Evan / Elin: agree exactly which duplicate report stops, the 15-minute replacement, and the action if admin exceeds that allowance. No averaging spare later-week admin into onboarding.
  3. Dr Shah / Jo / Elin: endorse the choice allocation rule and honest handling of unmet preferences. Eight offers is an aspiration supported by capacity, not patient acceptance.
  4. Rae, if T selected: accept the deferred teaching obligation with a dated plan; capture £900 in the current commitment register.

Owners and rights from 12-F–H; specific terms and deadlines are this proposed agreement.

Launch, monitor and contain a failure

Launch gates and weekly rhythm

Before 25 January, Elin reconciles the actual bookings against this weekly template, patient acceptance and all seven session resources; Dr Shah confirms clinical cover and prioritisation. Arun releases launch only after the selected concessions are signed. A fit in this planner does not establish those facts. [12-H]

Use the existing booking records and R digest for a short weekly review: session minutes, admin actually used, remote count, named-language support, offers / acceptances / delivery, unserved requests and preferred modes not offered. Record actual take-up rather than inventing a forecast. Elin owns the digest; Dr Shah owns clinical response; Arun decides operating changes. [12-G,H]

Approve the next week's booking mix before confirming it. Check the W3–4 vaccination reduction specifically; use the alternative's middle template only then. Pause unsupported promises if a resource disappears, consent changes, or the 15-minute digest cannot be delivered; count the exact shortfall and obtain a bounded re-agreement. No averaging and no uncosted additional data collection. [12-D–H]

Two quantified containment decisions

If P is withdrawn before agreement

Keeping the proposed roles and slots, Friday is short 120 consultant minutes, 30 nurse minutes and 120 room minutes. The six Friday SV consultant physical appointments account for exactly those deficits. Holding those six leaves a 114-slot resource-feasible subset, but that is an explicitly reduced proposal requiring Dr Shah's prioritisation and Arun's approval—not success, and not an automatic cancellation decision. Use the withdrawal control to inspect the full, invalid 120-slot plan. [12-C–F,H; calculated]

If one Wednesday BV video offer is declined: converting it to physical in the recommended plan adds 20 room minutes and 5 nurse minutes. Wednesday becomes 320 / 300 room minutes and 140 / 140 nurse minutes; clinician and interpreter minutes stay unchanged. Preserve the other 119 planned appointments, record one unresolved request, and obtain a permitted, validated alternative with that patient's acceptance. Do not promise a physical conversion or a different window. [12-B–E,H]

If a workable re-agreement cannot be approved before the booking decision, Arun must explicitly decide whether to use the existing 96 physical / 24 unserved per week service while Dr Shah determines prioritisation. That fallback is not six-week completion. Only a bounded board request may authorise more money or continuation; there is no assumed rescue resource. [12-H]

Exit after W6: all concessions expire after 5 March. Restore the original facilities and practitioner allocations, end the temporary report waiver unless separately authorised, and fulfil any already committed replacement teaching. Any continued redesign goes to the service board; unused authority is not permission to roll forward. [12-F,H]

Evidence and reproducible workings

Recorded rules 12-A–F and 12-H establish the fictional service bounds. Stakeholder position 12-G records discussion. Proposal Packages, allocation choices and deadlines are authored here. Unknown Actual patient acceptance, offer uptake, staff identities and delivery outcomes are not supplied.

How the calculation works
For each appointment: clinician minutes go to its one assigned role; nurse, admin, room, booth and the matching interpreter are separate additions. For each session with remote activity: +5 practitioner minutes. For each session with video activity: +10 weekly booking-admin minutes. W1–W2 with any remote activity: +40 weekly booking-admin minutes. More than 20 remote appointments: +60 consultant minutes in Wednesday W. Cap remote appointments at 36/week. W3–W4: Thursday H practitioner and exam capacity −20 each. Apply only the selected, non-withdrawn offers, including all mandatory negative offsets. Admin usable capacity = 1,000 + (R ? 100 − 15 : 0). Compare every session/resource cell, weekly admin, complete cohort counts, permitted combinations and six-week commitments.

The page recomputes all checks on each control change. Arrangements are fixed, verified candidate allocations, not an optimiser. A withdrawal does not remove appointments, reviews, handovers or onboarding from the demand side. Removing an offer before acceptance changes the proposed commitment; no cancellation rights or refund after signing are assumed.

Original case and initial supplied position • 11–15 January 2027
# BPB2-12 — Outpatient service redesign — secure a workable agreement Suite BPB2 v0.3-pilot; Foray 247, third essai. ### Scenario Mereford Hospital needs a six-week outpatient agreement that serves weekly demand without quietly moving the burden onto patients, teaching or another department. Its aggregate capacity appears almost adequate, but appointment windows, professional skills and two interpreter languages prevent minutes being freely exchanged. Operations director Arun Vale must negotiate a package on 18 January 2027. He needs a service people can actually operate, including the difficult middle weeks, with explicit concessions, patient-choice conditions and a bounded fallback if bookings change. ### Exact task prompt Produce one usable in-browser answer page for the named practitioner, using the supplied fictional evidence. Keep observed facts, forecasts, assumptions and proposed decisions distinguishable, and cite source IDs beside material claims. No external research or real-world certification is required. Prepare Arun's proposed operating agreement and negotiation brief. Give two complete, feasible arrangements covering all six weeks: session/cohort/mode allocations, clinician roles, every concession, overhead and total commitment. Recommend one, explaining patient access, staff continuity, displaced work and the practical cost of the alternative. Address the language-video request without turning advocacy into consent or a mandatory quota. Show whose approval is needed, the terms you would ask them to accept, launch/monitoring conditions and one quantified booking/resource contingency. A weekly capacity total, an unsolved optimisation model or blanket escalation is insufficient. Do not change clinical classifications or promise appointments outside recorded availability. ### Supplied records **12-A — Scope and calendar, Arun, 14 January 2027.** Pilot 25 January–5 March: W1=25 January, W2=1 February, W3=8 February, W4=15 February, W5=22 February, W6=1 March. Demand 120 appointments each week; no backlog. Each appointment must fit wholly in one allowed session that week. Sessions: M=Monday AM; A=Monday PM; T=Tuesday PM; W=Wednesday AM; H=Thursday PM; F=Friday AM. Minutes cannot transfer between sessions. Within one session, the listed totals are sufficient: no additional timing/order restrictions are hidden. No overtime, group visits, unlisted staff or clinical reclassification. Arun may authorise at most £3,000 total pilot commitments; continuing beyond six weeks requires the service board. All rules are fictional service rules. **12-B — Planning register, Dr Imani Shah, 14 January.** p=physical, t=telephone, v=video. Listed modes/windows are clinically permitted and recorded as acceptable for planning; none is consent to a particular booking. Counts are the weekly demand profile; do not assume that a patient must attend six times. Unlisted combinations are unavailable. | Cohort | Count | Permitted mode: sessions | |---|---:|---| | N1, new assessments | 12 | p:M,A | | N2, new assessments | 12 | p:T,H | | C1, complex follow-ups | 12 | p:W | | C2, complex follow-ups | 12 | p:A,F | | SP, stable physical preference | 18 | p:A,T,W,H,F | | ST, stable telephone option | 18 | p:A,T,H,F; t:A,W,F | | SV, stable video option | 12 | p:T,H,F; v:T,H | | AP, language A physical preference | 6 | p:T,H | | AV, language A video option | 6 | p:T,H; v:T,H | | BP, language B physical preference | 6 | p:W,F | | BV, language B video option | 6 | p:W,F; v:W,F | **12-C — Clinical/resource protocol, 14 January.** N/C appointments require a consultant. S/language appointments may use either a consultant or an authorised practitioner; assign one role for the whole appointment. Practitioners cannot cover N/C or the consultant review. Nurse time is additional, not a substitute clinician. Language A and B interpreters cannot substitute for each other. All per-appointment times below are minutes, including ordinary documentation. No telephone language appointments are allowed. | Type/mode | Assigned clinician | Nurse | Booking admin | Exam room | Video booth | Relevant interpreter | |---|---:|---:|---:|---:|---:|---:| | N p | 30 | 10 | 8 | 30 | 0 | 0 | | C p | 20 | 10 | 8 | 20 | 0 | 0 | | Any S p | 20 | 5 | 6 | 20 | 0 | 0 | | S t | 15 | 0 | 8 | 0 | 0 | 0 | | S v | 15 | 0 | 10 | 0 | 15 | 0 | | Any language p | 20 | 5 | 10 | 20 | 0 | 20 | | Any language v | 20 | 0 | 14 | 0 | 20 | 20 | **12-D — Guaranteed session resources, managers, 14 January.** Separate pools, minutes/session; unused rooms cannot provide staff. Weekly booking-admin capacity is 1,000 minutes, freely schedulable within that week; it is not a separate allowance per session. | Session | Consultant | Practitioner | Nurse | Exam rooms | Video booths | Interpreter A | Interpreter B | |---|---:|---:|---:|---:|---:|---:|---:| | M | 300 | 0 | 100 | 300 | 0 | 0 | 0 | | A | 180 | 240 | 120 | 360 | 0 | 0 | 0 | | T | 180 | 300 | 120 | 420 | 60 | 120 | 0 | | W | 240 | 240 | 140 | 300 | 90 | 0 | 120 | | H | 180 | 300 | 120 | 420 | 60 | 120 | 0 | | F | 120 | 300 | 120 | 360 | 30 | 0 | 120 | **12-E — Pilot requirements and exceptions, clinical/operations leads, 15 January.** Each session containing any remote appointment consumes an additional five practitioner minutes for remote handover, even when its appointments use consultants. Each session containing video also adds ten booking-admin minutes. In W1–W2, any remote activity adds a further 40 booking minutes per week for onboarding. Above 20 remote appointments in a week, a 60-minute consultant review must occur in session W; no alternative reviewer/session is available. Review consumes capacity even if cases run smoothly. Maximum 36 remote/week. In W3–W4 only, a previously committed vaccination service reduces H's practitioner and examination-room capacity by 20 minutes each. Other resources are unchanged. Apply these reductions as well as concession effects; they are not spare weekly capacity elsewhere. **12-F — Conditional six-week offers, 15 January.** None has been accepted. Offer codes are separate from session codes: teaching offer T changes Wednesday session W, not Tuesday session T. Capacities below are weekly/session effects. T, V, P must be bought for all six weeks; no selected-week purchases. R has no cash charge. Offsets are mandatory; do not keep the original capacity as well. | Offer | Effect and total commitment | Required sign-off | |---|---|---| | T, teaching redeployment | W:+90 consultant minutes, but −60 practitioner minutes for teaching cover; replacement teaching £900 after pilot, committed now | Education lead Rae Holt and Arun; dated replacement-teaching plan | | R, report waiver | Suspend the duplicate weekly narrative utilisation return, releasing 100 admin minutes/week; replacement digest uses 15, so net +85 | Finance lead Evan Cho; identify suspended optional report and digest | | V, video conversion | H:+120 booth minutes but −120 examination-room minutes; £150/week=£900 | Estates lead Mara Finn and Arun | | P, physical-session expansion | F:+120 consultant,+60 nurse,+240 examination-room minutes; −60 practitioner minutes for supervision; F's original 30 booth minutes become unavailable; £450/week=£2,700 | Dr Shah, Mara and Arun | V and P use the same temporary facilities team and cannot coexist. T and P are technically compatible, but their combined £3,600 exceeds Arun's authority. Later payment does not remove T from the cap. There are no other interactions or charges. **12-G — Stakeholder positions, 15 January; discussion, not agreement.** Dr Shah wants continuity, the specified review, and an explicit response to lost capacity. Elin Price, administration manager, will not support a plan that works only by averaging onboarding with later weeks. Jo Mercer, patient representative, asks for eight language-supported video offers/week, including at least three in each language: travel is burdensome, but some patients prefer physical contact. This is an advocacy request, not a quota or patient consent. Explain any shortfall and the allocation principle; do not describe more remote activity as automatically better care. Rae wants teaching replaced and dated. Evan will consider R only if the replacement digest retains weekly appointment/choice/workload information. Mara wants one stable facilities commitment. Arun wants all 120 served within authority, and accepts that a more predictable arrangement might justify a premium. No combined package is signed. **12-H — Decision and delivery rights, signed service charter, 11 January.** Dr Shah approves the clinical arrangement and any clinical prioritisation; Elin accepts booking feasibility; each concession needs its listed sign-offs; Arun authorises expenditure/start. Individual booking acceptance belongs to the patient; Jo cannot bind a cohort. Propose specific agreement terms, owners and deadlines, distinguishing proposals from commitments. Use existing records/digest for proportionate weekly review; any additional collection burden must fit capacity. Report unserved requests and preferred modes not offered, with a transparent allocation rule instead of silently prioritising the easiest patients. Temporary concessions expire after W6. The service board alone approves overspending or continuation. If take-up/resources fail, stop unsupported booking promises, quantify the deficit and seek a bounded decision; do not force a different mode. Existing service provides 96 physical appointments/week, leaving 24 unserved; this is a fallback requiring an explicit decision, not successful delivery. ### Browser deliverable and completion conditions A proposed agreement with two inspectable session templates (and week-specific variations where needed), a commitment/approval register and negotiation decisions. Required controls are arrangement and week selection, plus withdrawal of one explicitly selected concession as a bounded resource contingency. Recompute that change's affected capacities, overheads, cost and session/resource breaches; show an invalidated arrangement honestly rather than silently reallocating patients. All displayed base arrangements must respect cohort totals, allowed session/mode/role combinations, all seven session resource pools, weekly admin, overheads, exceptions and six-week cost. A green weekly total is insufficient. Arbitrary cohort/session/role editing and automatic re-optimisation are optional extensions. Record offered/accepted/delivered status separately; a toggle cannot grant consent. Preserve the initial proposal and include a clear return to the gallery. The page must work in the supplied browser/runtime; a download button or file preview alone is insufficient. Include a clear “Return to gallery” link using the shared shell route, or ../index.html if no route is supplied. Required controls must change the dependent results, not just their appearance. Original evidence and the initial dated position must remain recoverable; hypothetical changes do not create approvals or alter source records. Optional exports are secondary.
Validation scope and limits

Local arithmetic and DOM self-checks accompany this first-attempt proposal. The checks cover twelve baseline week/package combinations and the withdrawal behaviour. They are authored checks, not independent validation, clinical certification, a tested booking system or evidence of actual acceptance. Browser rendering is checked separately by the coordinator. No external sources are used. The initial recommendation remains P + R regardless of hypothetical control settings.

Read the complete supplied case · BPB2-12
# BPB2-12 — Outpatient service redesign — secure a workable agreement

Suite BPB2 v0.3-pilot; Foray 247, third essai.

### Scenario

Mereford Hospital needs a six-week outpatient agreement that serves weekly demand without quietly moving the burden onto patients, teaching or another department. Its aggregate capacity appears almost adequate, but appointment windows, professional skills and two interpreter languages prevent minutes being freely exchanged. Operations director Arun Vale must negotiate a package on 18 January 2027. He needs a service people can actually operate, including the difficult middle weeks, with explicit concessions, patient-choice conditions and a bounded fallback if bookings change.

### Exact task prompt

Produce one usable in-browser answer page for the named practitioner, using the supplied fictional evidence. Keep observed facts, forecasts, assumptions and proposed decisions distinguishable, and cite source IDs beside material claims. No external research or real-world certification is required.

Prepare Arun's proposed operating agreement and negotiation brief. Give two complete, feasible arrangements covering all six weeks: session/cohort/mode allocations, clinician roles, every concession, overhead and total commitment. Recommend one, explaining patient access, staff continuity, displaced work and the practical cost of the alternative. Address the language-video request without turning advocacy into consent or a mandatory quota. Show whose approval is needed, the terms you would ask them to accept, launch/monitoring conditions and one quantified booking/resource contingency. A weekly capacity total, an unsolved optimisation model or blanket escalation is insufficient. Do not change clinical classifications or promise appointments outside recorded availability.

### Supplied records

**12-A — Scope and calendar, Arun, 14 January 2027.** Pilot 25 January–5 March: W1=25 January, W2=1 February, W3=8 February, W4=15 February, W5=22 February, W6=1 March. Demand 120 appointments each week; no backlog. Each appointment must fit wholly in one allowed session that week. Sessions: M=Monday AM; A=Monday PM; T=Tuesday PM; W=Wednesday AM; H=Thursday PM; F=Friday AM. Minutes cannot transfer between sessions. Within one session, the listed totals are sufficient: no additional timing/order restrictions are hidden. No overtime, group visits, unlisted staff or clinical reclassification. Arun may authorise at most £3,000 total pilot commitments; continuing beyond six weeks requires the service board. All rules are fictional service rules.

**12-B — Planning register, Dr Imani Shah, 14 January.** p=physical, t=telephone, v=video. Listed modes/windows are clinically permitted and recorded as acceptable for planning; none is consent to a particular booking. Counts are the weekly demand profile; do not assume that a patient must attend six times. Unlisted combinations are unavailable.

| Cohort | Count | Permitted mode: sessions |
|---|---:|---|
| N1, new assessments | 12 | p:M,A |
| N2, new assessments | 12 | p:T,H |
| C1, complex follow-ups | 12 | p:W |
| C2, complex follow-ups | 12 | p:A,F |
| SP, stable physical preference | 18 | p:A,T,W,H,F |
| ST, stable telephone option | 18 | p:A,T,H,F; t:A,W,F |
| SV, stable video option | 12 | p:T,H,F; v:T,H |
| AP, language A physical preference | 6 | p:T,H |
| AV, language A video option | 6 | p:T,H; v:T,H |
| BP, language B physical preference | 6 | p:W,F |
| BV, language B video option | 6 | p:W,F; v:W,F |

**12-C — Clinical/resource protocol, 14 January.** N/C appointments require a consultant. S/language appointments may use either a consultant or an authorised practitioner; assign one role for the whole appointment. Practitioners cannot cover N/C or the consultant review. Nurse time is additional, not a substitute clinician. Language A and B interpreters cannot substitute for each other. All per-appointment times below are minutes, including ordinary documentation. No telephone language appointments are allowed.

| Type/mode | Assigned clinician | Nurse | Booking admin | Exam room | Video booth | Relevant interpreter |
|---|---:|---:|---:|---:|---:|---:|
| N p | 30 | 10 | 8 | 30 | 0 | 0 |
| C p | 20 | 10 | 8 | 20 | 0 | 0 |
| Any S p | 20 | 5 | 6 | 20 | 0 | 0 |
| S t | 15 | 0 | 8 | 0 | 0 | 0 |
| S v | 15 | 0 | 10 | 0 | 15 | 0 |
| Any language p | 20 | 5 | 10 | 20 | 0 | 20 |
| Any language v | 20 | 0 | 14 | 0 | 20 | 20 |

**12-D — Guaranteed session resources, managers, 14 January.** Separate pools, minutes/session; unused rooms cannot provide staff. Weekly booking-admin capacity is 1,000 minutes, freely schedulable within that week; it is not a separate allowance per session.

| Session | Consultant | Practitioner | Nurse | Exam rooms | Video booths | Interpreter A | Interpreter B |
|---|---:|---:|---:|---:|---:|---:|---:|
| M | 300 | 0 | 100 | 300 | 0 | 0 | 0 |
| A | 180 | 240 | 120 | 360 | 0 | 0 | 0 |
| T | 180 | 300 | 120 | 420 | 60 | 120 | 0 |
| W | 240 | 240 | 140 | 300 | 90 | 0 | 120 |
| H | 180 | 300 | 120 | 420 | 60 | 120 | 0 |
| F | 120 | 300 | 120 | 360 | 30 | 0 | 120 |

**12-E — Pilot requirements and exceptions, clinical/operations leads, 15 January.** Each session containing any remote appointment consumes an additional five practitioner minutes for remote handover, even when its appointments use consultants. Each session containing video also adds ten booking-admin minutes. In W1–W2, any remote activity adds a further 40 booking minutes per week for onboarding. Above 20 remote appointments in a week, a 60-minute consultant review must occur in session W; no alternative reviewer/session is available. Review consumes capacity even if cases run smoothly. Maximum 36 remote/week. In W3–W4 only, a previously committed vaccination service reduces H's practitioner and examination-room capacity by 20 minutes each. Other resources are unchanged. Apply these reductions as well as concession effects; they are not spare weekly capacity elsewhere.

**12-F — Conditional six-week offers, 15 January.** None has been accepted. Offer codes are separate from session codes: teaching offer T changes Wednesday session W, not Tuesday session T. Capacities below are weekly/session effects. T, V, P must be bought for all six weeks; no selected-week purchases. R has no cash charge. Offsets are mandatory; do not keep the original capacity as well.

| Offer | Effect and total commitment | Required sign-off |
|---|---|---|
| T, teaching redeployment | W:+90 consultant minutes, but −60 practitioner minutes for teaching cover; replacement teaching £900 after pilot, committed now | Education lead Rae Holt and Arun; dated replacement-teaching plan |
| R, report waiver | Suspend the duplicate weekly narrative utilisation return, releasing 100 admin minutes/week; replacement digest uses 15, so net +85 | Finance lead Evan Cho; identify suspended optional report and digest |
| V, video conversion | H:+120 booth minutes but −120 examination-room minutes; £150/week=£900 | Estates lead Mara Finn and Arun |
| P, physical-session expansion | F:+120 consultant,+60 nurse,+240 examination-room minutes; −60 practitioner minutes for supervision; F's original 30 booth minutes become unavailable; £450/week=£2,700 | Dr Shah, Mara and Arun |

V and P use the same temporary facilities team and cannot coexist. T and P are technically compatible, but their combined £3,600 exceeds Arun's authority. Later payment does not remove T from the cap. There are no other interactions or charges.

**12-G — Stakeholder positions, 15 January; discussion, not agreement.** Dr Shah wants continuity, the specified review, and an explicit response to lost capacity. Elin Price, administration manager, will not support a plan that works only by averaging onboarding with later weeks. Jo Mercer, patient representative, asks for eight language-supported video offers/week, including at least three in each language: travel is burdensome, but some patients prefer physical contact. This is an advocacy request, not a quota or patient consent. Explain any shortfall and the allocation principle; do not describe more remote activity as automatically better care. Rae wants teaching replaced and dated. Evan will consider R only if the replacement digest retains weekly appointment/choice/workload information. Mara wants one stable facilities commitment. Arun wants all 120 served within authority, and accepts that a more predictable arrangement might justify a premium. No combined package is signed.

**12-H — Decision and delivery rights, signed service charter, 11 January.** Dr Shah approves the clinical arrangement and any clinical prioritisation; Elin accepts booking feasibility; each concession needs its listed sign-offs; Arun authorises expenditure/start. Individual booking acceptance belongs to the patient; Jo cannot bind a cohort. Propose specific agreement terms, owners and deadlines, distinguishing proposals from commitments. Use existing records/digest for proportionate weekly review; any additional collection burden must fit capacity. Report unserved requests and preferred modes not offered, with a transparent allocation rule instead of silently prioritising the easiest patients. Temporary concessions expire after W6. The service board alone approves overspending or continuation. If take-up/resources fail, stop unsupported booking promises, quantify the deficit and seek a bounded decision; do not force a different mode. Existing service provides 96 physical appointments/week, leaving 24 unserved; this is a fallback requiring an explicit decision, not successful delivery.

### Browser deliverable and completion conditions

A proposed agreement with two inspectable session templates (and week-specific variations where needed), a commitment/approval register and negotiation decisions. Required controls are arrangement and week selection, plus withdrawal of one explicitly selected concession as a bounded resource contingency. Recompute that change's affected capacities, overheads, cost and session/resource breaches; show an invalidated arrangement honestly rather than silently reallocating patients. All displayed base arrangements must respect cohort totals, allowed session/mode/role combinations, all seven session resource pools, weekly admin, overheads, exceptions and six-week cost. A green weekly total is insufficient. Arbitrary cohort/session/role editing and automatic re-optimisation are optional extensions. Record offered/accepted/delivered status separately; a toggle cannot grant consent. Preserve the initial proposal and include a clear return to the gallery.

The page must work in the supplied browser/runtime; a download button or file preview alone is insufficient. Include a clear “Return to gallery” link using the shared shell route, or ../index.html if no route is supplied. Required controls must change the dependent results, not just their appearance. Original evidence and the initial dated position must remain recoverable; hypothetical changes do not create approvals or alter source records. Optional exports are secondary.