Same percentage.
Different accepted units.
Status at 10 May 2027, 17:00, reconstructed for reporting on 12 May. Preserve the record available then and the verified restatement side by side.
Reconstructed reporting draft · not evidence of publicationA preserved comparison, not an overwritten spreadsheet
| Reporting record | Available by cutoff | Verified restatement through 12 May |
|---|---|---|
| Accepted / authorised | 8 / 12 · 66.7% | 8 / 12 · 66.7% |
| Membership retained | W101 · W103 · W104A · W105 · W106 · W1089 · W111 | |
| W102 | Accepted on I2 | Not accepted: B12 revokes I2 |
| W110 | Not accepted: no available inspection | Accepted: I14 + verified A12, event 9 May |
| Other nonaccepted units | W104B · W107 · W112 | |
B12's defect was not visible in the original register; knowing it on 12 May does not make the original 10 May assessment unreasonable. I14/A12 establishes a pre-cutoff event; I15 is a later test and cannot do so. 10-R5 · 10-R6
Count authorised units, not rows or certificates
W101–W112 · 1 May
−W104 + W104A + W104B · 6 May
−W108 − W109 + W1089 · 8 May
Effective at 10 May 17:00
16 contractor rows cover 11 current units by resolved reference. C3/C4 are one duplicate claim pair; C5 is retired-parent history; C10/C11/C12 relate to one merged unit; C16 remains U-99, unresolved. W104B has no recorded claim. None of these counting adjustments turns a claim into acceptance. 10-R2 · 10-R4
Claim coverage means a linked claim exists, not that its location or quality qualifies. A contractor claim is not an acceptance prerequisite. Distance uses √((observed easting − authorised easting)² + (observed northing − authorised northing)²). Dates are the supplied local reporting dates; no time-zone conversion or forecast is assumed. 10-R1
Current-unit acceptance register
Every row is one authorised current acceptance unit. Retired parents, component IDs and unresolved claims are retained in lineage rather than promoted into additional units.
| Current unit / lineage | Claim and inspection | Authorised position / distance | Decision and evidence |
|---|
No current units match these filters. U-99 is an unresolved claim shown separately below.
Follow the identity and evidence trail
Selected current-unit record
Reconciliation and action queue · 12 May
This queue uses the latest supplied evidence on 12 May, independently of the historical-view selector. Actions below are proposed next steps, not approvals or completed work. Named people beyond Priya are not supplied; accountable owners are the specified authority roles. 10-R8
| Exception / state | Required next step and closure evidence | Accountable owner / support | Reporting boundary |
|---|
Subsequent events · keep outside 10 May
W112: I15 is a valid pass performed and issued 11 May, at (1100,100). This is later work, so it belongs in an 11 May or later report, never either 10 May numerator. It does not approve U-99 or alter scope. 10-R1 · 10-R6
No forecast of final acceptance, no invented completion date, and no whole-project 12 May percentage is presented. The requested report fixes the event cutoff at 10 May 17:00. By contrast, W110's 11 May issue date concerns a verified 9 May event and is a correction to that fixed cutoff.
Disposition of the 10 May assertions
| Assertion in 10-R7 | Reporting decision |
|---|---|
| Contractor: sixteen completions; merging repeats means everything is done | Reject as acceptance evidence. Sixteen rows resolve to claims covering eleven current units, plus retained parent history and U-99. Acceptance is eight of twelve. 10-R1 · 10-R4 |
| PM: all twelve accepted; latest CAD and parent certificate suffice | Reject. W107 is 30 m outside the authorised position; split children each need their own post-split pass. W104B failed. PM publication authority cannot change these rules. 10-R2 · 10-R3 · 10-R5 |
| Supervisor: U-99 must be W112 because of the same place | Reject the inferred match. No authorised alias exists and co-location is insufficient. Preserve C16 independently. 10-R2 · 10-R7 |
| Owner: no U-99 alias or W107 coordinate change approved; keep lineage | Apply. Neither the contractor's CAD nor the supervisor's assertion supplies owner approval. 10-R3 · 10-R7 |
Original supplied evidence
Verbatim supplied records, preserved as issued. Their assertions remain distinguishable from the reconciled decisions above. Click any source citation to open its record.
10-R1 — Baseline/acceptance policy, asset owner, issued 1 May 2027.
Initially twelve units W101–W112. Denominator means current authorised acceptance units effective at reporting cutoff, not rows/photos. Acceptance needs resolved identity and required signed pass at an authorised position within 10 m, for an event no later than cutoff. A contractor claim is not acceptance and is not prerequisite to a correctly evidenced inspection. Event time determines asset/alias applicability; issue time determines evidence availability. Restatement may use a verified later correction to establish/revoke a pre-cutoff event; tests performed later cannot count retrospectively. These are complete fictional rules, not safety certification.
10-R2 — Authorised changes, asset owner.
Each issued on its effective date before 17:00, available by 10 May. Unlisted aliases are unapproved; position alone cannot establish identity.
| Record | Effective rule |
|---|---|
| S06, 6 May | Retire W104; replace by separately accepted W104A and W104B. Each needs its own pass performed on/after 6 May; parent pass cannot cover children. W104-A aliases W104A from 6 May. |
| M08, 8 May | Merge W108/W109 into W1089. Existing component inspections may carry, but both components plus a post-merge signed mapping check are required. Old IDs remain component references, not two current units. |
| A01, 1 May | A-01 means W101; W-103 means W103 throughout. |
| A08, 8 May | OLD-17 means W105 for events through 7 May23:59; from 8 May00:00 it means W111. The stale 1 May alias export shows only the old assignment. |
10-R3 — Position register/revisions, owner and survey office.
Local easting/northing metres. Authorised positions: W101(100,100); W102(200,100); W103(300,100); W104A(400,100); W104B(420,100); W105(500,100); W106(640,100); W107(700,100); W1089 east(800,100)/west(820,100); W110(900,100); W111(1000,100); W112(1100,100). Retired W104 parent was(410,100). Owner-approved V2 issued 9 May, effective 4 May, corrects W106 from(600,100) to(640,100). Contractor CAD C3 dated 10 May puts W107 at(730,100), but has no owner approval and cannot supersede the register. No other coordinate change exists.
10-R4 — Contractor sheet, issued 10 May15:00.
All rows marked complete. Event is claimed work date, not submission date. Identical P03 confirms C3/C4 duplication only; it creates no other identity rule.
| Row | Reference | Event | Position | Photo |
|---|---|---|---|---|
| C1 | A-01 | 6 May | (100,100) | P01 |
| C2 | W102 | 8 May | (200,100) | P02 |
| C3 | W103 | 9 May | (300,100) | P03 |
| C4 | W-103 | 9 May | (300,100) | P03 |
| C5 | W104 | 5 May | (410,100) | P04 |
| C6 | W104-A | 9 May | (400,100) | P05 |
| C7 | OLD-17 | 7 May | (500,100) | P06 |
| C8 | W106 | 7 May | (640,100) | P07 |
| C9 | W107 | 10 May | (730,100) | P08 |
| C10 | W108 east | 6 May | (800,100) | P09 |
| C11 | W109 west | 7 May | (820,100) | P10 |
| C12 | W1089 mapping complete | 9 May | both components | P11 |
| C13 | W110 | 9 May | (900,100) | P12 |
| C14 | OLD-17 | 9 May | (1000,100) | P13 |
| C15 | W112 | 10 May | (1100,100) | P14 |
| C16 | U-99 | 10 May | (1100,100) | P15 |
10-R5 — Signed inspection register available at cutoff, inspection lead.
Each issued on its event date before 17:00. Signatures/evidence are valid except the explicit failure and later correction. P02 was represented as correctly supporting W102; its audit below is new information, not a discrepancy visible in the cutoff register.
| Inspection | Reference | Event | Result and position/evidence |
|---|---|---|---|
| I1 | A-01 | 6 May | Pass,(100,100) |
| I2 | W102 | 8 May | Pass,(205,100), labelled P02 |
| I3 | W103 | 9 May | Pass,(300,100),P03 |
| I4 | W104 | 5 May | Pass,parent(410,100) |
| I5 | W104A | 9 May | Pass,(400,100) |
| I6 | W104B | 9 May | Fail,(420,100),incorrect label |
| I7 | W105 | 8 May | Pass,(500,100) |
| I8 | W106 | 7 May | Pass,(640,100) |
| I9 | W107 | 10 May | Pass,(730,100),using CAD C3 |
| I10 | W108 east | 6 May | Pass,(800,100) |
| I11 | W109 west | 7 May | Pass,(820,100) |
| I12 | W1089 | 9 May | Pass,combined mapping and both component identities verified |
| I13 | OLD-17 | 9 May | Pass,(1000,100) |
10-R6 — Later evidence, issued 11–12 May; corrections jointly verified by inspection lead/asset owner.
I14, issued 11 May, records W110 pass at(900,100) performed 9 May. Audit A12 issued 12 May verifies its event date and unit against timestamped field records; it was unavailable 10 May. Audit B12 issued 12 May revokes I2: W102's signed pass was misattributed; no valid W102 inspection exists at/before cutoff. Purported P02 evidence came from another visit, undetectable from the register issued 8 May. I15, issued 11 May, is a valid W112 pass at(1100,100), actually performed 11 May. No later evidence changes W104B, W107,U-99 or scope.
10-R7 — Project log, 10 May16:00.
Contractor: “Sixteen completions; after merging repeats, everything is done.” PM: “All twelve current units accepted; use the latest CAD and the parent certificate for both children.” Supervisor: “U-99 must be W112: same place.” Owner: “No U-99 alias or W107 coordinate change approved. Keep lineage.” These are assertions to assess, not additional authority.
10-R8 — Action authority, 12 May.
Owner approves identities, relationships and positions; inspection lead corrects inspections; contractor supplies original claims/location evidence; PM publishes status/restatement. Priya reconciles but cannot approve aliases or turn failed/absent tests into passes. Preserve superseded records with issue/effective dates. Later work belongs in a subsequent-events note, not either 10 May numerator.
Read the complete supplied case · BPB2-10
# BPB2-10 — Water utility asset migration — establish a trustworthy status Suite BPB2 v0.3-pilot; Foray 247, third essai. ### Scenario Bracken Water's migration includes split and merged records, reused legacy identifiers and survey corrections. Asset information manager Priya Vale must reconstruct the position at 10 May 2027, then explain what later verified corrections change without rewriting what was knowable then. An unchanged overall percentage may conceal changes in which units were actually accepted. Priya needs a defensible reporting record on 12 May, with lineage, justified exceptions and specific owners for the remaining reconciliation work. ### Exact task prompt Produce one usable in-browser answer page for the named practitioner, using the supplied fictional evidence. Keep observed facts, forecasts, assumptions and proposed decisions distinguishable, and cite source IDs beside material claims. No external research or real-world certification is required. Produce Priya's status for 10 May17:00 in two views: the position supportable by records issued by that cutoff, and a labelled restatement using verified information issued by 12 May about events at/before the same cutoff. Preserve both. Reconstruct authorised acceptance units, resolve only justified identities, and distinguish claims, acceptance and later work. Explain any unchanged headline hiding changed membership. Give the exception/action queue without overwriting sources or inventing matches. A single deduplicated spreadsheet or percentage is insufficient. ### Supplied records **10-R1 — Baseline/acceptance policy, asset owner, issued 1 May 2027.** Initially twelve units W101–W112. Denominator means current authorised acceptance units effective at reporting cutoff, not rows/photos. Acceptance needs resolved identity and required signed pass at an authorised position within 10 m, for an event no later than cutoff. A contractor claim is not acceptance and is not prerequisite to a correctly evidenced inspection. Event time determines asset/alias applicability; issue time determines evidence availability. Restatement may use a verified later correction to establish/revoke a pre-cutoff event; tests performed later cannot count retrospectively. These are complete fictional rules, not safety certification. **10-R2 — Authorised changes, asset owner.** Each issued on its effective date before 17:00, available by 10 May. Unlisted aliases are unapproved; position alone cannot establish identity. | Record | Effective rule | |---|---| | S06, 6 May | Retire W104; replace by separately accepted W104A and W104B. Each needs its own pass performed on/after 6 May; parent pass cannot cover children. W104-A aliases W104A from 6 May. | | M08, 8 May | Merge W108/W109 into W1089. Existing component inspections may carry, but both components plus a post-merge signed mapping check are required. Old IDs remain component references, not two current units. | | A01, 1 May | A-01 means W101; W-103 means W103 throughout. | | A08, 8 May | OLD-17 means W105 for events through 7 May23:59; from 8 May00:00 it means W111. The stale 1 May alias export shows only the old assignment. | **10-R3 — Position register/revisions, owner and survey office.** Local easting/northing metres. Authorised positions: W101(100,100); W102(200,100); W103(300,100); W104A(400,100); W104B(420,100); W105(500,100); W106(640,100); W107(700,100); W1089 east(800,100)/west(820,100); W110(900,100); W111(1000,100); W112(1100,100). Retired W104 parent was(410,100). Owner-approved V2 issued 9 May, effective 4 May, corrects W106 from(600,100) to(640,100). Contractor CAD C3 dated 10 May puts W107 at(730,100), but has no owner approval and cannot supersede the register. No other coordinate change exists. **10-R4 — Contractor sheet, issued 10 May15:00.** All rows marked complete. Event is claimed work date, not submission date. Identical P03 confirms C3/C4 duplication only; it creates no other identity rule. | Row | Reference | Event | Position | Photo | |---|---|---|---|---| | C1 | A-01 |6 May|(100,100)|P01| | C2 | W102 |8 May|(200,100)|P02| | C3 | W103 |9 May|(300,100)|P03| | C4 | W-103 |9 May|(300,100)|P03| | C5 | W104 |5 May|(410,100)|P04| | C6 | W104-A |9 May|(400,100)|P05| | C7 | OLD-17 |7 May|(500,100)|P06| | C8 | W106 |7 May|(640,100)|P07| | C9 | W107 |10 May|(730,100)|P08| | C10 | W108 east |6 May|(800,100)|P09| | C11 | W109 west |7 May|(820,100)|P10| | C12 | W1089 mapping complete |9 May|both components|P11| | C13 | W110 |9 May|(900,100)|P12| | C14 | OLD-17 |9 May|(1000,100)|P13| | C15 | W112 |10 May|(1100,100)|P14| | C16 | U-99 |10 May|(1100,100)|P15| **10-R5 — Signed inspection register available at cutoff, inspection lead.** Each issued on its event date before 17:00. Signatures/evidence are valid except the explicit failure and later correction. P02 was represented as correctly supporting W102; its audit below is new information, not a discrepancy visible in the cutoff register. | Inspection | Reference | Event | Result and position/evidence | |---|---|---|---| | I1 | A-01 |6 May|Pass,(100,100)| | I2 | W102 |8 May|Pass,(205,100), labelled P02| | I3 | W103 |9 May|Pass,(300,100),P03| | I4 | W104 |5 May|Pass,parent(410,100)| | I5 | W104A |9 May|Pass,(400,100)| | I6 | W104B |9 May|Fail,(420,100),incorrect label| | I7 | W105 |8 May|Pass,(500,100)| | I8 | W106 |7 May|Pass,(640,100)| | I9 | W107 |10 May|Pass,(730,100),using CAD C3| | I10 | W108 east |6 May|Pass,(800,100)| | I11 | W109 west |7 May|Pass,(820,100)| | I12 | W1089 |9 May|Pass,combined mapping and both component identities verified| | I13 | OLD-17 |9 May|Pass,(1000,100)| **10-R6 — Later evidence, issued 11–12 May; corrections jointly verified by inspection lead/asset owner.** I14, issued 11 May, records W110 pass at(900,100) performed 9 May. Audit A12 issued 12 May verifies its event date and unit against timestamped field records; it was unavailable 10 May. Audit B12 issued 12 May revokes I2: W102's signed pass was misattributed; no valid W102 inspection exists at/before cutoff. Purported P02 evidence came from another visit, undetectable from the register issued 8 May. I15, issued 11 May, is a valid W112 pass at(1100,100), actually performed 11 May. No later evidence changes W104B, W107,U-99 or scope. **10-R7 — Project log, 10 May16:00.** Contractor: “Sixteen completions; after merging repeats, everything is done.” PM: “All twelve current units accepted; use the latest CAD and the parent certificate for both children.” Supervisor: “U-99 must be W112: same place.” Owner: “No U-99 alias or W107 coordinate change approved. Keep lineage.” These are assertions to assess, not additional authority. **10-R8 — Action authority, 12 May.** Owner approves identities, relationships and positions; inspection lead corrects inspections; contractor supplies original claims/location evidence; PM publishes status/restatement. Priya reconciles but cannot approve aliases or turn failed/absent tests into passes. Preserve superseded records with issue/effective dates. Later work belongs in a subsequent-events note, not either 10 May numerator. ### Browser deliverable and completion conditions Provide the current-unit register, source lineage and exception/action queue with both historical views labelled. Switching views must change membership/reasons without overwriting the earlier report. Trace a split, merge, reused alias and correction; filter unresolved items; keep later work separate. Display counts and accepted-unit lists so an unchanged percentage cannot conceal a correction. The page must work in the supplied browser/runtime; a download button or file preview alone is insufficient. Include a clear “Return to gallery” link using the shared shell route, or ../index.html if no route is supplied. Required controls must change the dependent results, not just their appearance. Original evidence and the initial dated position must remain recoverable; hypothetical changes do not create approvals or alter source records. Optional exports are secondary.