Read the complete supplied case · BPB2-07
# BPB2-07 — Aerospace prototype programme — allocate scarce specialists
Suite BPB2 v0.3-pilot; Foray 247, third essai.
### Scenario
Northwake Instruments owes two prototype evidence packages to different customers. Programme manager Elis Price has credible work-package estimates but conflicting promises for specialists and test facilities. The flight demonstrator has a hard customer commitment; endurance evidence has a costly but negotiable date. Elis must issue a resource-backed recovery recommendation before work starts on 6 September 2027, showing whether equipment rental, a borrowed specialist or a combination changes what the programme can actually deliver.
### Exact task prompt
Produce one usable in-browser answer page for the named practitioner, using the supplied fictional evidence. Keep observed facts, forecasts, assumptions and proposed decisions distinguishable, and cite source IDs beside material claims. No external research or real-world certification is required.
Produce Elis's executable allocation and recovery recommendation for the twelve remaining work packages. Show who does each task, when, on which facility, with dependencies and dated customer deliverables. Compare the minimum useful intervention with the package needed to meet both commitments, demonstrate why cheaper-looking purchases do or do not suffice, and identify the approval or customer decision required. Treat the first-priority commitment as a hard planning constraint unless explicitly escalated as unachievable. Provide at least one complete feasible schedule for your recommendation and an intelligible lower-bound argument for the principal rejected alternative; an unverified Gantt chart is insufficient.
### Supplied records
**07-R1 — Planning rules, programme office, 1 September 2027.** D1 is Monday 6 September; count weekdays only, no holidays, through D24. Duration occupies whole working days; successors start no earlier than the next working day. Every task is non-preemptive and uses the assigned person and facility throughout. No overtime, fractional staff, unlisted skill substitution or overlapping work on one resource is permitted. Estimates already include normal preparation and documentation. Work cannot start before D1.
**07-R2 — Work-package baseline, engineering leads, 2 September.** A choice in the person column is an actual authorised skill substitution. There are no additional prerequisite tasks.
| ID | Package | Days | Predecessors | Qualified person | Facility |
|---|---|---:|---|---|---|
| A | Controls build | 3 | — | Ada | — |
| B | Power build | 3 | — | Ben | — |
| C | Demonstrator integration | 2 | A,B | Ada or Ben | Integration bench |
| D | Static verification | 2 | C | Cara | Integration bench |
| E | Demonstrator tuning | 2 | D | Ada | Integration bench |
| F | Customer-witnessed demonstration test | 2 | E | Cara | Integration bench |
| G | Flight evidence report | 1 | F | Ada | — |
| H | Endurance fixture build | 3 | B | Dev | Integration bench |
| I | Endurance instrumentation | 2 | H,L | Ben | Thermal chamber |
| J | Endurance run | 3 | I | Cara or approved Fran | Thermal chamber |
| K | Endurance findings | 1 | J | Ben | — |
| L | Common interface verification | 2 | A,B | Ada or Ben | — |
**07-R3 — Staff register, functional heads, 2 September.** Ada, Ben, Cara and Dev are fully available D1–D24 but each can perform only the roles listed in R2. Cara alone is approved for static verification and the customer-witnessed demonstration test. Fran is an equally qualified endurance-test witness only; she cannot replace Cara on D or F, nor replace Ben or Dev. A qualified person is required on every day of a test; an unattended run is not permitted by these fictional project rules.
**07-R4 — Owned facilities, laboratory manager, 2 September.** One integration bench is available except D6–D7 inclusive, when a non-movable overhaul closes it. One thermal chamber is available except D7–D10 inclusive, when another customer's committed test occupies it. Equipment cannot be shared by tasks. Endurance instrumentation and the subsequent run must use the same physical chamber; moving an instrumented assembly is not an available acceleration. The chosen chamber remains reserved between I's start and J's finish. No other task in this programme requires it during that reservation.
**07-R5 — Firm recovery offers, 3 September.** Offers are independent, may be combined, and must be reserved by end D3. Prices include mobilisation, equipment equivalence checks and all listed days; no further preparation task or per-day fee is needed. Owned-facility closures remain in force.
| Option | Cost | Availability and limitation |
|---|---:|---|
| B: second integration bench | £5,000 | D4–D10 inclusive; equivalent to the owned bench, but no staff supplied |
| T: mobile thermal chamber | £4,000 | D7–D12 inclusive; equivalent; both instrumentation and run must fit its rental window |
| F: borrow Fran | £3,000 | D9–D13 inclusive; may perform J only and must cover its complete three-day run |
**07-R6 — Customer priorities, commercial director, 3 September.** Flight report G is promised by end D13 and is first priority. No alternative demonstration date is currently available; a plan later than D13 must be identified as failing that commitment, not silently accepted. Endurance findings K are promised by end D13. Their contract charges £2,500 for each working day delivered after D13; no partial-day rounding issue. This charge is the complete quantified lateness consequence. Commercial director must notify and agree a proposed revised delivery date; the model must not claim customer agreement. Earlier endurance delivery has no additional monetary benefit in the fixture.
**07-R7 — Funding and authority, sponsor, 3 September.** Elis may authorise £5,000. Sponsor has a £10,000 recovery allocation; committing more requires a specific additional-funding decision before D3 ends. Endurance lateness charges come from the same project forecast but do not increase the recovery-purchase allocation automatically. The sponsor wants the total purchase-plus-known-lateness consequence shown, together with resource feasibility and date margin. Spending a purchase budget does not itself authorise moving either customer's milestone.
**07-R8 — Package-lead claims, coordination notes, 3 September.** Controls lead: “An extra bench gives us parallel tests.” Test lead: “Fran is the key; the chamber should then sort itself out.” Commercial lead: “Buying the mobile chamber alone must pull endurance forward.” None has supplied a resource-level schedule. These are proposals to test, not approved facts. Durations, availability and skills in R1–R7 take precedence.
### Browser deliverable and completion conditions
Provide the resource allocation, customer dates and decision brief in one navigable page. Users must be able to compare no purchase, bench only, bench plus chamber, and all three purchases, with conflicts or unachievable commitments explicit. Validated scenario schedules are acceptable instead of a general optimiser. Selecting a task must expose its predecessor, qualified person and facility. Purchase totals, lateness charges, approval gap and delivery dates must stay consistent; preserve a workable fallback if the additional funding is not approved by D3.
The page must work in the supplied browser/runtime; a download button or file preview alone is insufficient. Include a clear “Return to gallery” link using the shared shell route, or ../index.html if no route is supplied. Required controls must change the dependent results, not just their appearance. Original evidence and the initial dated position must remain recoverable; hypothetical changes do not create approvals or alter source records. Optional exports are secondary.