Choose an evidenced delivery plan
Ask: confirm the revised equipment date and compare a verified recovery offer with a week-14 replan. Do not promise week 12 from an unconfirmed backup.
Evidence owner: Supply lead.
Decision authority: not supplied; identify the authorised schedule and purchasing decision-maker.
Decision point: before committing integration dates or any recovery purchase.
Consequence: with no further hold, removing two weeks of delay restores the model’s week-12 finish; accepting the reported delay gives week 14. Recovery feasibility and premium are unknown.
Evidence and decision conditions
EQ-12 · day 10: “Two-week delay”; action: “Confirm backup and delivery date”. Anomaly flagged; score 5.
E04: “IF integration is scheduled THEN verify equipment delivery date”. Obtain a dated delivery confirmation, backup availability, compatibility and full cost before choosing.
The £8,000 option has no supplied scope; it is not assumed to buy equipment recovery. Record the chosen basis, accountable approver and revisit trigger outside this simulator.