Question 15 · Repair & Reuse · Procurement choices

Buy delivery protection, not a promised earlier launch

Which supplier choices protect the critical path within the budget?

Base-case recommendation: for a schedule-first launch, provisionally choose Expedited. Its £8,000 premium buys two weeks of equipment delivery protection and keeps the modelled launch at week 12 for £226,400, leaving £13,600 below the £240,000 cap after contingency. It does not accelerate the launch: fit-out already runs to week 6.

Backup is the £5,000, one-week hedge. Standard is cheapest but has no equipment float. No reliability, quality or contractual evidence is supplied, so this is a conditional planning recommendation; a verified supplier must still pass the purchase checkpoints below.

Fictional what-if workspace. Changes stay in this tab and reset on reload; no record is saved and no external system is changed.

The dependency to protect

Integration waits for both fit-out and usable equipment. With all six staff assigned to fit-out, 24 staff-weeks take four weeks after the two-week design. Integration, pilot and readiness then consume six sequential weeks. To finish at week 12, both branches must be ready at week 6.

Standard: equipment and fit-out jointly control. Backup or Expedited: fit-out controls until delivery slippage uses their one- or two-week margin. Shared staff or equipment conflicts that delay fit-out cannot be cured by purchasing faster equipment alone.

Stress the purchasing choice

Controls are assumptions, not observed supplier performance. Delivery slippage is applied equally to all three offers for a like-for-like stress test. Staff remain fixed at six; costs include keeping that team for the entire modelled launch.

Selected launch
Launch cost incl. contingency
Further equipment slip toleratedbefore the selected launch moves

Every offer under the same assumptions
OfferEquipment usableLaunch / latenessTotal / cap headroomControlling branchPlan result

Selected dependency chain

Elapsed project weeks from the 5 January 2026 baseline; week 12 is 30 March 2026. Bars show durations, not probabilities. Dashed red line marks the week-12 target.

Internal workOrder to usable equipmentWeek-12 deadline

Three supply risks that matter

  1. Late equipment or a late order release. Standard has zero float; Backup has one week and Expedited two. Require a dated production/dispatch commitment for the full two-hub quantity. Review at design freeze and at the supplier's confirmed dispatch milestone. The stress test does not assign failure probabilities.
  2. Unusable or incomplete equipment at handover. Compatibility, safety evidence, missing accessories or partial delivery can block integration even if a shipment arrives on time. Define acceptance criteria before purchase, inspect documentation before dispatch and hold the week-6 integration gate until the responsible assessor accepts the equipment.
  3. A nominal fallback that shares the same bottleneck. “Backup” is only a fixture label: stock, underlying manufacturer, carrier independence and six-person integration capacity are unknown. Check real availability and common dependencies before relying on it. Adding a second order, cancellation or switching costs are not priced here.

This ranking is authored from critical-path exposure, not an incident history or quantified likelihood. Supplier acceleration leaves the separate fit-out risk fully exposed.

Purchase checkpoints and a reviewable decision

Decision gates for the selected scenario
WhenEvidence / actionHold point
Before week 2Confirm specification, quantities for both hubs, safety/compatibility criteria and named assessor. Obtain all-in quotes and reserve a delivery slot if contractually possible.No binding order based on a lead-time label alone.
Design freeze, week 2Responsible purchaser checks budget, authority, delivery commitment and acceptance obligations before any actual order.
Latest release is a mathematical limit, not a reason to wait. Escalate before margin reaches zero.
Supplier-confirmed dispatch milestoneReconcile remaining lead time with the week-6 usable-equipment requirement. Request proof of complete kit and acceptance documents.If recovery is unproven, re-plan; do not count an uncontracted alternative as secured.
Week 6 integration gateBoth hubs' fit-out and usable equipment must be ready; assessor accepts safety and compatibility evidence.A favourable cost or schedule calculation cannot waive safety or approve launch.

For this simulation only: mark evidence you want to assume has been verified. These boxes do not verify anything or confer purchasing authority.

Produces a result below, in this tab. Correct the controls or assumed checks and run again. Reset clears the result; reload also discards it. No order, saved file, approval or supplier contact is created.

Evidence, assumptions and decision rule

Supplied synthetic fixtures

  • Case: 12 weeks, £240,000 budget, six cross-trained staff.
  • Design 2 weeks; fit-out 24 staff-weeks; integration, pilot and readiness each 2 weeks.
  • Standard: 4-week lead, no premium. Backup: 3-week lead, £5,000 premium. Expedited: 2-week lead, £8,000 premium.
  • Fixed cost £120,000; staff £1,200 per person-week; contingency £12,000.

Sources: benchmark v1.0.0, question 15, taskFixtures.suppliers and case.fixtures. These are the only substantive inputs used.

Interpretation and limits

  • Fit-out and supplier lead time start after design. Integration → pilot → readiness is sequential. No extra stage overlap or two-hub staggering is assumed.
  • The full six-person team is paid from start to finish, including any waiting. All six can perform fit-out; no separate staff demand is modelled in parallel.
  • Fixed launch cost is assumed to include Standard equipment; supplier premiums are added once. Check that inclusion before trusting totals.
  • Lead time means usable equipment for both hubs. Testing, shipment defects and acceptance delays must be included as slippage if not already covered.
  • Contingency stays reserved at £12,000 in every scenario; “headroom” is additional room below the cap. No taxes, cancellation, dual-source costs or probabilistic risk valuation are supplied.

Fit-out ready = 2 + 24 / 6 + extra fit-out weeks Equipment ready = 2 + release delay + supplier lead + delivery slippage Launch = max(fit-out ready, equipment ready) + 2 + 2 + 2 Cost = £120,000 + 6 × £1,200 × launch weeks + £12,000 + supplier premium A feasible plan requires launch ≤ 12 AND cost ≤ £240,000. A simulated procurement-review candidate also requires all four assumed evidence checks. No simulated result constitutes actual approval or proof of supplier capability.

The base-case choice is therefore a preference trade-off: Standard saves £8,000 against Expedited; Backup saves £3,000 but gives up one week of equipment protection. Expedited is the schedule-first choice, not a proven expected-value winner. All three need evidence checks. Without supplier probabilities or delay consequences beyond staff cost, the optimal risk-adjusted purchase cannot be established.

Acceptance checks and authoring status

Controlling dependencies and three supply risks are identified above. Every supplier scenario exposes readiness, launch, cost and budget status; the purchasing table shows design freeze, latest release, dispatch and integration checkpoints. Local arithmetic and interaction checks are documented privately for the reviewer. Browser review is a separate parent-agent step; this page does not assert field validation or operational performance improvement.