Conflicting reports
How should we reconcile contradictory completion reports before releasing a launch gate?
Hold the gate for the North electrical test station. Match both reports to the same asset, completion criteria and cutoff, then obtain the required dated signed readiness inspection. The photo and checklist disagree; averaging their reliability would conceal the disagreement.
Fictional what-if workspace. Changes stay in this tab and reset on reload; no record is saved and no external system is changed.
The evidence we actually have
| Record | Claim | Supplied reliability | What is missing |
|---|---|---|---|
| Photo | Complete | 80% | Date, asset identifier on the image, completion criteria, calibration and provenance. |
| Checklist | Incomplete | 85% | Date, failed items, signatory, calibration and whether it reused the photo. |
Supplied prior completion: 50%. Common identity: confirmed in the fixture. Required follow-up: Dated signed readiness inspection for the same identified station.
Case: a fictional two-hub launch in 12 weeks within £240,000, with six cross-trained staff. Schedule or budget pressure does not change the evidence standard. “Complete” here is assumed to mean that this station meets its agreed readiness criteria; the fixture does not provide those criteria or the wider launch-gate authority.
Reconciliation result
Hold · inspection missing
The supplied photo and checklist disagree. Confirm comparable scope and timing, then obtain the dated signed readiness inspection for the North electrical test station.
Initial fixture assessment. No simulated follow-up has been selected.
Inputs changed. This result describes the previous scenario. Select “Simulate reconciliation” to replace it.
Result lifecycle: ephemeral scenario in this page only. No readiness record, inspection, file or approval is created. Correct an assumption above and simulate again; Reset restores the supplied values and initial result. Reload discards all changes. There is no saved History or external action to withdraw.
Assumptions, acceptance checks and limits
Acceptance: the prior, observed-claim likelihoods and resulting posterior are visible in step 2. Clearing common identity suppresses joint calculation and forces a hold; selecting shared evidence also refuses fusion. Unknown dependence and missing comparable dates make the combined figure illustrative only.
No release threshold is supplied. This answer therefore does not invent one. Even a high computed probability cannot substitute for the mandatory inspection. A hypothetical signed pass can make this station's package ready for gate review, but it cannot demonstrate the other hub, shared dependencies or overall launch readiness.
Limits: no original photo, checklist, inspection, timestamps, calibration sample or completion definition is available. The binary model omits partial completion and defect severity. A single “reliability” value cannot ordinarily identify both likelihoods. Conditional independence is an additional assumption. Priors must reflect evidence available before these reports, or evidence will be counted twice.
Source and configuration: fictional benchmark v1.0.0, question 12, assigned conflictingReports fixture only. Authored as plain HTML/CSS/JavaScript with local calculation checks, no dependencies or network calls. Developed by an isolated question author with coordinating review; browser QA is recorded separately in the private run receipt. No comparative performance improvement is asserted.